The following question has been certified to this Court by the United States District Court for the District of South Carolina:
Under the facts of this case, what exceptions, if any, to an unambiguous no-damages-for-delay clause in a construction contract would the South Carolina Supreme Court recognize?
*132 FACTS
Metric, general contractor for construction of a new federal prison in Estill, S.C., hired Williams Electric Company as the major electrical subcontractor. The contract, written by Metric, contains the following no-damages-for-delay clause:
7. Extensions of Time_ In the event the Subcontractor’s performance of this Subcontract is delayed or interfered with by acts or omissions of the Owner, Contractor or other subcontractors, Subcontractor may request an extension of time for the performance of this Subcontract as hereinabove provided, but shall not be entitled to any increase in the subcontract Price or to damages or additional compensation as a consequence of such delays or interference except to the extent that the Contract entitles Contractor to compensation therefor and then only to the extent of any amounts that Contractor, on behalf of Subcontractor, recovers from Owner for such delays or interference.
During construction of the prison, Williams suffered delays caused primarily by Metric’s failure to properly coordinate and manage the subcontractors. As a result, Williams incurred more labor and material costs than anticipated and was required to remain on the project for months after its scheduled completion date. Subsequent to completion of the prison, Williams brought this action in the Federal District Court under the Miller Act 1 for additional expenses caused by the delays. Metric answered and sought summary judgment, contending it is not liable by virtue of the no-damages-for-delay clause.
DISCUSSION
Generally, no-damage-for-delay provisions are valid and enforceable so long as they meet ordinary rules governing the validity of contracts.
See
Annot,
Validity and Construction of “No Damage Clause
”
with Respect to Delay in Building or Construction Contract,
We premise our discussion by recognizing that, in South Carolina, there exists in every contract an implied obligation of good faith and fair dealing.
Adams v. Creel,
a. Delay caused by fraud, misrepresentation, or other bad faith.
The most widely recognized exception to the enforceability of a no-damage-for delay clause is fraud, misrepresentation or bad faith.
Clearly, fraud, misrepresentation and bad faith in performance of one’s contractual duties would give rise to a violation of the implied obligation of good faith and fair dealing.
See O’Quinn v. Beach Associates,
*134 is a logical extension of South Carolina law and join the majority of jurisdictions in adopting this exception.
b. Delay caused by active interference
A majority of courts also adopt an exception to a no-damage-for-delay clause in cases of direct, active, willful interference with the work of the contractor.
c. Unreasonable delay justifying abandonment of the contract
A number of courts recognize an exception to a no-damage clause where delays are so unreasonable in length or
*135
duration that they amount to an abandonment of the contract, or would justify the contractor’s abandonment.
d. Delays not contemplated by the parties.
The most contested of the exceptions is that for “delay not contemplated by the parties.” Under this exception, a number of courts find that a “no damage” provision will not bar claims resulting from delays caused by the contractee if the delays “were not within the contemplation of the parties at the time they entered into the contract.”
Corinno Civetta Const. v. City of New York,
However, this view is not universally accepted and has recently been questioned by a number of courts.
See e.g. State Highway Administrator v. Greiner,
Indeed, the adoption of a no-damage-for-delay clause shows that the parties realize that some delays cannot be contemplated at the time of the drafting of the contract.... The parties can deal with delays they contemplate by adjusting the start and completion dates or by including particular provisions in the contract. “[I]t is the unforeseen events which occasion the broad language of the clause since foreseeable ones could be readily provided for by specific language.” City of Houston v. R.F. Ball Constr. Co., Inc.,570 S.W.2d 75 , 78 (Tex.Civ.App.1978).
It has long been the law in this State that when a contract is unambiguous, clear and explicit, it must be construed according to the terms the parties have used, to be taken and used in their plain, ordinary sense.
See C.A.N. Enterprises v. S.C. Health and Human Services,
e. Delays caused by gross negligence
The final exception to a “no-dama.ge-for delay” clause referenced in the district court’s certification order is “gross negligence.” Several jurisdictions have adopted this exception.
See North Star Contracting Corp. v. City of New York,
CONCLUSION
We hereby adopt, consistent with the implied obligation of good faith and fair dealing, the exceptions for delay caused by fraud, misrepresentation, or other bad faith; active interference; delay which amounts to an abandonment of the contract; and gross negligence. We decline to adopt an exception for “delays not contemplated by the parties.”
CERTIFIED QUESTION ANSWERED.
Notes
. 40 U.S.C. § 270a et seq. The Miller Act requires contractors on federal construction projects to furnish a payment bond to protect subcontractors.
. South Carolina also recognizes an action for willful interference with contract.
See Martin v. One Chevrolet Truck,
. Metric does not oppose adoption of this exception, but urges us to adopt the definition of "active interference” embraced by the Iowa court in
Peter Kiewit Sons' Co.
v.
Iowa Southern Utilities Co.,
... to be guilty of “active interference" ..., the defendants herein would have to have committed some affirmative, willful act, in bad faith, to unreasonably interfere with plaintiff’s compliance with the terms of construction contract_ [U]se of the term "active” to modify “interference” ... clearly implies more than a simple mistake, error in judgment, lack of total effort, or lack of complete diligence ...
As there is already a specific exception for bad faith, we decline to adopt so much of this definition as requires a showing of "bad faith.” Trial courts of this state may, however, utilize the remainder of the Kiewit definition in fashioning an appropriate jury charge.
