Tyner v. Scofield

11 Ind. 550 | Ind. | 1859

Hanna, J.

This was an action by Tyner, assignee of Wilcox, upon an agreement under seal between Wilcox and Scofield, by which Wilcox sold and transferred to Sco*551field “ all the right, title, and interest of the said Wilcox in and to any and all moneys,” &c., “that would have been paid to said Wilcox and Scofield by the New Trenton, &c., Bridge Company, for the wood-work of a bridge contracted to be constructed by said Wilcox and Scofield for said company, at,” &c., “for the sum of 225 dollars, to be paid to said Wilcox by said Scofield, out of the money received as the final estimate on said work.” Then follows- a stipulation by which Scofield binds himself to complete the work according to the contract of Wilcox and Scofield, and to release Wilcox from all responsibility on said contract,.and that Scofield was “to pay said Wilcox the above-named sum at the time and in the manner above mentioned.”

The issues make no question as to parties.

There was a demurrer overruled to the fourth paragraph of the answer, which will be first noticed.

The first paragraph of the complaint alleged that a final estimate had been made, and averred a demand and failure to pay said 225 dollars, &c.

The second paragraph averred, among other things, that no final estimate had been made, but that in lieu thereof the defendant settled with the said company for the sum due him on his work, including the sum that would have been due upon a final estimate, and accepted, in full satisfaction, certain claims, &c., by means whereof the said sum of 225 dollars became due, which was demanded, &e.

The fourth paragraph of the answer averred that on, &c., Wilcox and the defendant contracted with said New Trenton, &c., Bridge Company, to construct the wood superstructure of a bridge, &c.; that the interest of Wilcox mentioned in the writing sued on, is the same as that named in this contract, and that the same was transferred by said Wilcox to said Scofield, subject to all of the contingencies and conditions set forth in said contract and answer, and that said 225 dollars was to be paid only out of the final estimate, &c. Averment of readiness to perform said work, but that on, &c., said company failing to have funds, &c., discharged, as by the contract they had a right to, said defendant, and would not permit him to com*552píete said work, and that he only received a partial estimate thereon, a great part thereof remaining unpaid on account of the insolvency of the said company; that there was no final estimate, nor did he receive, on compromise or otherwise, the moneys out of which said 225 dollars was to be paid, &c.

The stipulations of the contract referred to in the answer, bearing upon this point, were, that an estimate was to be made May 1, 1852, and every sixty days thereafter, of which sums 10 per cent, was to be reserved until the work should be completed; and if, from want of funds, the company should find it necessary to suspend the construction of said work, they should have the right to do so at any stage of the work, and if such suspension should be for a longer period than one year, the 10 per cent, should be paid up.

The demurrer to this fourth paragraph was for want of sufficient facts to constitute a defense.

We are of opinion the demurrer to the fourth paragraph of the answer was correctly overruled. Whatever might have been the rights of Wilcox, or his assignee, in reference to the recovery of the 225 dollars, if the construction of the bridge had been completed, and the contract in regard thereto complied with by both parties, it is not necessary to decide; for it is surely apparent from the pleadings that the contract between Wilcox and Scofield, so far as that 225 dollars was involved, was made with reference to anticipated profits upon the bridge contract. If such sum had been payable absolutely, it might have presented a different question. Here it was payable out of the money received from the final .estimate. This fourth paragraph not only denies that a final estimate was ever made and the money received thereon, but also controverts the averments of the complaint that upon a compromise between the bridge company and Scofield, sums had been by him received, out of which this sum should be paid.

This, so far as we can see, was the material issue to be tried, and the finding by the jury was for the defendant.

The point raised by the motion for a new trial, not dis*553posed of already, was as to whether this verdict was sustained by the law and the evidence.

J. D. Howland, for the appellant. N. Trusler and G. Trusler, for the appellee.

We have, with care, examined the evidence, and think it tended to sustain the verdict, and it will not, therefore, be disturbed.

Although there is no question made as to parties, yet we cannot but see that there is an agreement in the record that Tyner had not, at the time of the suit, any interest in the claim or suit.

Per Curiam. — The judgment is affirmed with costs.