11 Ind. 550 | Ind. | 1859
This was an action by Tyner, assignee of Wilcox, upon an agreement under seal between Wilcox and Scofield, by which Wilcox sold and transferred to Sco
The issues make no question as to parties.
There was a demurrer overruled to the fourth paragraph of the answer, which will be first noticed.
The first paragraph of the complaint alleged that a final estimate had been made, and averred a demand and failure to pay said 225 dollars, &c.
The second paragraph averred, among other things, that no final estimate had been made, but that in lieu thereof the defendant settled with the said company for the sum due him on his work, including the sum that would have been due upon a final estimate, and accepted, in full satisfaction, certain claims, &c., by means whereof the said sum of 225 dollars became due, which was demanded, &e.
The fourth paragraph of the answer averred that on, &c., Wilcox and the defendant contracted with said New Trenton, &c., Bridge Company, to construct the wood superstructure of a bridge, &c.; that the interest of Wilcox mentioned in the writing sued on, is the same as that named in this contract, and that the same was transferred by said Wilcox to said Scofield, subject to all of the contingencies and conditions set forth in said contract and answer, and that said 225 dollars was to be paid only out of the final estimate, &c. Averment of readiness to perform said work, but that on, &c., said company failing to have funds, &c., discharged, as by the contract they had a right to, said defendant, and would not permit him to com
The stipulations of the contract referred to in the answer, bearing upon this point, were, that an estimate was to be made May 1, 1852, and every sixty days thereafter, of which sums 10 per cent, was to be reserved until the work should be completed; and if, from want of funds, the company should find it necessary to suspend the construction of said work, they should have the right to do so at any stage of the work, and if such suspension should be for a longer period than one year, the 10 per cent, should be paid up.
The demurrer to this fourth paragraph was for want of sufficient facts to constitute a defense.
We are of opinion the demurrer to the fourth paragraph of the answer was correctly overruled. Whatever might have been the rights of Wilcox, or his assignee, in reference to the recovery of the 225 dollars, if the construction of the bridge had been completed, and the contract in regard thereto complied with by both parties, it is not necessary to decide; for it is surely apparent from the pleadings that the contract between Wilcox and Scofield, so far as that 225 dollars was involved, was made with reference to anticipated profits upon the bridge contract. If such sum had been payable absolutely, it might have presented a different question. Here it was payable out of the money received from the final .estimate. This fourth paragraph not only denies that a final estimate was ever made and the money received thereon, but also controverts the averments of the complaint that upon a compromise between the bridge company and Scofield, sums had been by him received, out of which this sum should be paid.
This, so far as we can see, was the material issue to be tried, and the finding by the jury was for the defendant.
The point raised by the motion for a new trial, not dis
We have, with care, examined the evidence, and think it tended to sustain the verdict, and it will not, therefore, be disturbed.
Although there is no question made as to parties, yet we cannot but see that there is an agreement in the record that Tyner had not, at the time of the suit, any interest in the claim or suit.
Per Curiam. — The judgment is affirmed with costs.