The resolution of intention for the grading of Bay Street from Jones to Dupont was adopted by the Board of Supervisors March 25th, 1867, and the resolution ordering the work done was adopted April 8th, 1867. In 1868, a contract was let at forty cents per cubic foot, and the contractor having been released, a second contract was let in January, 1869, at fifty-five cents per cubic foot; and that contractor having been released, the third contract was awarded to the defendant in April, 1869, at the
The seventh sec. of the Act of 1862 as amended in 1863, (Stats. 1863, p. 526) authorized the Superintendent,, “under the direction of the Board of Supervisors,” to extend the' time, as fixed in the contract, for the completion of street work; that is to say, power is given to the Board of Supervisors to direct an extension of the time, and the Superintendent enters such extension upon the contract.
The question here presented is a question of power—after the expiration of the time fixed in the contract, and after having refused to extend the time, has the Board the power to grant an extension of the time for the completion of the work under the contract ? The language of the act is: “ And said Superintendent shall fix the time for the commencement and completion of the work under all contracts' entered into by him, and may extend the time so fixed from time to time under the direction of the Board of Supervisors.” Were there no provision of this character in the statute, the power to extend the time could only be claimed as arising by necessary implication, and it might be extremely difficult to uphold the power; and were the question now for the first time presented to this Court, whether a valid extension of time could be g’ranted after the expiration of the time fixed in the contract, we would feel great hesitation'in holding, as was done in Taylor v. Palmer, 31 Cal. 246, that an