46 Neb. 211 | Neb. | 1895
Alonzo J. Tullock sued Webster county in the district court thereof, which sustained a demurrer to Tul lock’s petition. He refused to plead further, whereupon the court entered a judgment dismissing his action, to reverse which he has prosecuted here a petition in error.
The allegations of Tullock’s petition necessary to an understanding of the points made here are in substance that on the 16th day of June, 1887, Tullock entered into a contract in writing with Joseph Garber, Alfred McCall, and Reese Thompson, “ bridge committee for and in behalf of said Webster county,” By the terms of the contract Tullock agreed to furnish the material and labor and construct a bridge for the bridge committee over the Republican river south of Red Cloud and have the same completed by the 1st day of November, 1887. The petition then alleged that Tullock fully performed his contract before the date last mentioned and that “ during the execution of said contract the said defendant, Webster county, directed and required and then and there consented and agreed to pay the said plaintiff for the extra work and materjal hereinafter more particularly set forth, viz.: That after Tullock had excavated the bed of the river to the first stratum of rock, for the purpose of building the north pier of said bridge according to the plans and specifications made a part Oof the contract, that Tullock was requested and required by Webster county to make said excavation to the second stratum of rock; that he did so; that Webster county then and- there agreed to pay Tullock for the -extra work and material required to carry the pier to the second stratum of rock; that said extra labor and material were of the value of $942.20.”
Webster county during the entire year of 1887 was under township organization, and at the time the contract for this bridge was entered into by the “ bridge committee”
“Sec. 1. That in counties under township organization the expense of building, maintaining, and repairing bridges on public roads over streams shall be borne exclusively by the counties within which such bridges are located.
“ Sec. 2. The county board of every such county shall build, maintain, and repair every such bridge, and make prompt and adequate provision for the payment of the expense thereof.”
The legislature of 1887 adjourned on the 31st day of March of that year, consequently this law did not take effect before the 1st day of July of that year, and there is no allegation in the petition as to the date when Webster county contracted with Tulloek to furnish the extra labor and material, nor is there any allegation in the petition showing when he furnished such extra labor and material. The allegation is that the labor and material were furnished at the request of Webster county during the time that Tullock was constructing the bridge; that is, sojne time between the 16th day of June, 1887, and the time of the completion of the work. This is too indefinite. We cannot presume from this language that the county contracted for nor that Tulloek furnished the extra labor and material subsequent to the 1st of July, 1887. Thq legislature did not intend by the act just quoted to make counties under township organization liable for the payment for bridges already constructed ; nor for the payment of repairs made on bridges, which repairs had been made prior to the pas
' The petition does not allege that the bridge built by Tullock, and towards the construction of which the extra labor and material sued for were furnished, was in Webster county. It appears from the petition that the value of the extra labor and material was more than $100; but the petition does not allege that the supervisors of Webster county, before they let the contract to Tullock to build this bridge or to furnish the extra material and labor therefor, advertised for bids; nor does it allege that the amount of money on hand in the county road fund derived from the levy of previous years and two-thirds of the levy for the current year, 1887, together with the amount of money in the district road fund of the district where such bridge was situate was equal to the amount agreed to be paid for such extra labor and material; nor does the petition allege that Tullock was the lowest competent bidder. If the act of March 24, 1887, quoted above, had been in force at the
The question of the power of a municipal corporation to ratify the invalid contracts of its officers was before this court in Guita Percha & Rubber Mfg. Co. v. Village of Ogalalla, 40 Neb., 775. The provision of the statute (Compiled Statutes, sec. 89, ch. 14,) entitled “Cities of the Second Class and Villages” is as follows: “No contract shall be hereafter made by the city council or board of trustees, or any committee or member thereof; and no expense shall be incurred by any of the officers or departments of the corporation, whether the object of the expenditure shall have been ordered by the city council or board of trustees or not, unless an appropriation shall have been previously made concerning such expense, except as herein otherwise expressly provided.” It appears that the trustees of the village of Ogalalla, or some of them, purchased of the manufacturing company certain hose, hose-carts, reels and ladders, and that the articles purchased were accepted and used by the village; but it further appears that no appropriation for the purpose of purchasing and paying for these articles had previously been made. The village having refused to pay for the fire apparatus, the manufacturing company sued it, and it was argued in this court that the village could not repudiate its contract after having received the benefits thereof; in other words, that by accepting the fire apparatus and using it, the village had thereby ratified the unauthorized contract of its officers in purchasing the apparatus. The court said: “The cases bearing upon the question of the power of municipal corporations to ratify their unauthorized contracts are confusing and apparently irreconcilable. It would subserve no useful purpose to
Affirmed.