5 A.2d 153 | Pa. | 1939
For an understanding of the legal questions here involved it is not necessary to give a detailed account of the accident which was the forerunner of the present litigation. Suffice it to say that the S.S. "Tercero," coming up the Delaware River to Philadelphia, arrived abreast of the pier where it was to be docked, and a spring line was thrown out from the forecastle head and fastened to a cleat on the dock. Because of packed ice in the river the ship could not get nearer to the pier than 15 to 20 feet. The "Indian," which was one of two tugboats assisting in the docking operation, received orders from the bridge of the "Tercero" to back in between the side of the ship and the pier, in order, by the action of its propeller, to churn out the ice. While this maneuver was being executed the spring line for some reason became slack, thereby interfering with the progress of the "Indian," *17 and, upon an order which emanated either from the captain of the "Indian" or from the bridge of the steamship, — the testimony on this point is not clear, — the slack was taken up by heaving the line over a metal mooring post on the pier some forty feet distant from the cleat. Edward E. Barnes, the pier superintendent of the company to which the cargo of the "Tercero" was consigned, was standing on the dock between the spring line and the tug when, probably because of the pressure of the ice pushing the bow of the steamship away from the pier, the line suddenly became taut and, being considerably higher at the vessel than at the cleat end, whipped over the top of the mooring post, struck Barnes in the back and catapulted him onto the deck of the "Indian," causing him severe injuries.
Barnes brought an action in tort for damages against A/S Ivarans Rederi as the alleged owner, and Moore McCormack, Inc., as the charterer of the "Tercero," and also against Tugboat Indian Company as the alleged owner and operator of the tugboat, and Henry J. Wolfinger, the linesman whose employees took the line on the dock and placed it over the cleat. No service was obtained against A/S Ivarans Rederi. The court granted a nonsuit as to Moore McCormack, Inc. Tugboat Indian Company also asked for a nonsuit but the motion was refused. Being apprehensive as to the amount of damages which the jury might award against it, Tugboat Indian Company thereupon settled with Barnes by paying him $2,500, taking from him a release and an assignment of his rights against the S.S. "Tercero," its owners, underwriters and charterers.
Upon the commencement of the action by Barnes, counsel for Tugboat Indian Company wrote letters to A/S Ivarans Rederi and Moore McCormack, Inc., demanding that they undertake the defense of the suit, and again wrote to their counsel prior to effecting the settlement with Barnes, giving notice of the proposed payment and expressly reserving right of action by way *18 of subrogation. Tugboat Indian Company then began the present suit in assumpsit against A/S Ivarans Rederi, Moore McCormack, Inc.,1 and Moore McCormack Co., Inc., to recover the sum of $2,500 paid to Barnes, together with expenses of $1,299.30 incurred in connection with the defense of the Barnes suit. A verdict was rendered by the jury in favor of plaintiff in the amount of $2,500, the item of expenses having been eliminated by the trial judge. Subsequently the court granted a motion for judgment n. o. v. Plaintiff now appeals for a restoration of the verdict.
This is not a suit by one tort-feasor against another for contribution. Neither is it an action based upon Barnes' assignment of his claim, plaintiff evidently realizing that unliquidated damages in tort cannot be assigned: Patten v.Wilson,
Plaintiff was in no such perilous position. Had it persisted in its defense in the Barnes suit that it was in no way responsible for the accident, and had the jury rendered a verdict in its favor, it would thus have exonerated itself without the necessity of any payment or further action on its part; on the other hand, had a verdict and judgment been rendered against it, this would have established that it was in fact negligent and was therefore not entitled to the relief which it claims on the ground that defendants alone were at fault. Plaintiff did not, however, choose to abide the issue of the Barnes trial, but settled because it entertained the fear that a just verdict might not be reached, although it would have had the complete protection of judicial review, both by the trial court and on appeal, of any verdict rendered. It is significant that in the present action the jury returned a verdict in plaintiff's favor on the ground that it was not negligent; why should it have been supposed that the jury in the Barnes suit would not have come to the same conclusion? It is true that plaintiff was called upon to decide whether to take the chance of a possibly unfavorable verdict or to settle the claim, but this is a situation inherent in all jury trials, and the necessity *20 of a litigant's exercise of judgment to determine the better policy to pursue is not duress within the meaning of the law. It cannot be said that one is coerced when he has ample opportunity to have his rights litigated and can utilize all the processes of the law to protect himself against an unwarranted demand. If, instead of availing himself of such protection, he chooses to compromise the claim, a payment thus made is not compulsory and does not entitle him to a right of recovery over by way of subrogation or indemnity.
The Pennsylvania cases are unanimous in denying restitution to a person who, contending that another has no valid claim against him, nevertheless makes payment solely because of the threat or the institution of litigation to enforce the demand. "The threat of a distress for rent is not . . . duress, because the party may replevy the goods distrained, and try the question of liability at law: . . . The threat of legal process is not such duress, for the party may plead and make proof, and show that he is not liable": Hospital v. Philadelphia County,
Confronted by the weakness of its case thus indicated, plaintiff seeks refuge in an alternative theory upon which to base its cause of action, namely, that where a person is secondarily liable for damages to an injured party he may recover indemnity from one primarily responsible, and in such a case it is not a prerequisite that he should have defended an action against him to the very end. On the contrary, he may pay or settle the claim voluntarily and recover against the person from whom he is entitled to indemnity, provided he has given proper notice and can establish that the settlement was fair and reasonable: Wise Shoes, Inc., v. Blatt,
Judgment affirmed.