44 Md. 453 | Md. | 1876
delivered the opinion of the Court.
The bill in this case was filed by Heise and Company against the contractors, and the Trustees of the Church, and the several lien claimants, to enforce a lien against the Church edifice, for the building of which they had furnished the contractors lumber ; the balance due on their claim being $3,489.13, according to the account filed. .
With the proceedings on this bill were consolidated the proceedings on a bill filed by Frederick and Herman Wehr, partners, trading as F. & II. Wehr, also to enforce a lien claim against the Church edifice, for bricks furnished the contractors, used in the erection of the building ; the amount of their claim being $5,949.33.
In these proceedings the several lien claimants were required to come forward and establish their claims, and their right to liens ; and among those whose claims were passed upon by the decrees appealed from, were Heise & Company, A. Weiskittel & Company, A. Storck & Son, and F. & H. Wehr, and from the allowance of whose claims the Trustees of the Church have appealed ; and for
Proceedings were conducted and proofs taken in support of claims until the 23rd of March, 1875, when the cause was submitted to the Court below without argument; whereupon the' Judge ordered that the cause be referred to the auditor, to report the pleadings, facts, and his opinion ther-eon. Under this order of reference, the auditor made a statement of the several lien claims filed, and o.f the facts offered in support thereof; and as to several of the claims the auditor stated his opinion to be that they were not sustained by the proof.
Upon this- report of the auditor, Heise & Company, Weiskittel & Company, and A. Storck & Son, made application to the Court for leave to take additional evidence as to certain objections to their claims stated by the auditor ; and the Court granted the applications, and allowed additional evidence to be taken. Under this leave, witnesses were re-examined as to the same subject-matter upon which they had been formerly examined by the claimants ; and to the allowance of this additional evidence to be taken, and to the re-examination of witnesses upon the same subject-matter, the Trustees of the Church have filed exceptions, and insist that such evidence should be excluded.
In the argument at bar, a good deal was said as to the form of the reference, and the power of the auditor to proceed as he did to examine the claims, and to declare his opinion as to whether they were established or not. But in what was done by the auditor, under this order of reference, we can perceive nothing irregular or unwarranted by the practice of the Court. The auditor is the calculator and accountant of the Court, and when any calculations or statements are required, all the pleadings, exhibits and
But the auditor having made his report, under the reference made on the submission of the case, the question is, whether the taking of additional evidence, and the reexamination of witnesses as to facts or subjects upon which they had been previously examined, should have been allowed.
As to the power of the Court to allow additional evidence to be taken, ev.eu after the cause has been submitted, that would seem to be clear, though the power is not generally exercised except in cases where, from accident or inadvertence, omissions or defects of proof have occurred, which the party could have readily supplied. A large number of the cases upon this subject are brought together and reviewed by Vice-Chancellor Shadwell, in the case of Hood vs. Pimm, 4 Sim., 101, where it is shown that a Court of Equity will, at any stage of the proceedings before final decree, allow defects in proof to be supplied, provided the party applying has not precluded himself from such indulgence by negligence or delay. This, however, is a discretionary power, from the exercise of which no appeal will lie, and is not therefore a subject of review by an Appellate Court. '
In this case, leave was obtained to take additional testimony in reference to certain objections made to the accounts
Having thus disposed of the question of evidence, applicable to the cases of Heise & Company, Weiskittel & Company, and Storck & Son, we shall now proceed to consider the claims separately, as presented in the record, and determine whether they are established or not.
1. As to the claim of Heise & Company:
This claim, is lor lumber furnished the contractors, and which was used in the erection of the Church. There is no question as to the quantity of lumber furnished; nor is there any question as to the regularity or form of the proceedings taken to fix the li'en.
The objections to the. claim are, first, that the materials were not furnished under a continuous contract, and, as nearly all the materials were furnished more than sixty days before notice given of claimants’ intention to claim a lien,-under the Code, Art. 61, sec. 11, and more than six months before the time of filing the lien claim for record, under the 23rd section of the same Article of the Code, therefore the lien is not good, except for the materials actually furnished within those periods; and, secondly,
The account for lumber furnished the Church commenced on the 3rd of April, 1872, and concluded on the 14th of February, 1873. Notice of the claimants’ intention to take the lien was given on the 9th and 12th of April, 1873, and the lien claim was filed for record on the 21st of June, 1873. If, therefore, the theory of the appellants, the trustees, be correct, there is but a very small portion of the account embraced by the lien.
The account, as stated and filed with the claim for lien, and which is proved to be correct, shows that the materials were continuously furnished within the period stated, during the progress of the building. The items are very' numerous, and deliveries were made at short intervals of a few days, as the materials were wanted at the building; and this course of dealing continued during the entire period covered by the account.
The lien law, Code, Art. 61, secs. 1 and 11, speaks of the contract for furnishing work or materials to the builder, or other person than the owner ; but we do not understand from this that it is incumbent upon the claimant to establish the fact that there was an express antecedent contract made with respect to the exact quantity of work or materials to be done or furnished by him. In the absence of evidence of such express contract, the character of the account, the time within which the work was done or the materials were furnished, and the object of the work or materials, may afford proper grounds for the presumption that the work was done or the materials were furnished with reference to an understanding from the commencement that such work or materials should be done or furnished, if required by the builder ; and in such case, it is from the last item in the account that the notice, and the time within which to take the lien, shotild date. If this were not so, in every case where there is no express con
In this case, there was such a continuous dealing, and running account of the materials furnished, and the deliveries were at such short intervals, and in such quantities, that the presumption arises that it was understood from the beginning that the claimants were to furnish the materials charged for as they were required in the progress of the building. And this presumption, we think, upon a fair construction of the evidence, is not overcome or removed by anything stated either in the testimony of William Heise, or his witness, J. Gr. Jones. We are therefore of opinion that the Court below was correct in regarding this lien as established ; but to what extent will depend upon the next question to be considered.
And that question is, how are certain credits tobe applied to the discharge of the debit items of the account?
It appears that there were large dealings between Heise & Company and Siegman & Jones, the contractors. The former kept but one general account of the materials furnished to-the latter, the materials being furnished for different buildings; but in charging the materials it was noted in the account for what particular building or object the materials were supplied. This general account ran from 1871 to June, 1873. On this account several credits were entered, with no other special application than such entries on the credit side of the account, with dates and amounts, will have assigned them by law'. When the
The general principle governing the application of payments, in a case like the present, is well settled. It is perfectly clear upon all the authorities since Clayton’s Case, 1 Merv., 585, decided by Sir Wm. Grant, that where divers debts are due from a person, and he pays money to his creditor, the debtor may, if he thinks proper, appropriate the payment to the discharge of any one or other of those debts ; and if he does not appropriate it, the creditor may make an appropriation ; but if there is no special appropriation by either party, and there is a current account betioeen them, as was the case here, the law makes an appropriation according to the order of the items of the account, the first item on the debit side of the account being the item discharged or reduced by the first item on the credit side. Pemberton vs. Oakes, 4 Russ., 154. And where the demand is entire, as the general account against Siegman ds Jones was, at the time of the payments made and entered, the creditor will not be allowed to separate or split such demand into parts, and appropriate a general payment to that part which is most advantageous to him
From these principles it follows that the payments made by Siegman & J ones on the general account must be applied according to the order of the items of the accoimt as it stood at the time of the payments made, and before the segregation of the items furnished for the Church. This can he done upon the re-adjustment of the claim, upon the cause being remanded to the Court below.
As to the question of interest, involved in the appeal taken by Heise & Company, we need only say, that we think they are entitled to a reversal of the decree in that respect. Interest is not charged or claimed in the account on which ■ the lien was taken, and hence it is contended that none should be allowed. But we think, upon principle and analogy, inasmuch as the lien became a claim of record, enforcible without stay or condition, interest should be allowed from the time of filing the lien claim for record. From that time, therefore, interest will be allowed on whatever may be ascertained to be the amount due.
2. As to the claim of A. Weiskittel & Co.:
This claim is for materials furnished, and was filed on the 18th of July, 1873. The notice of the intention to
As decided in the case of Thomas vs. Barber, 10 Md., 380, the object of the notice is to impart information to the owner of the amount and character of the claim intended to be fixed as a lien upon the property, so that he may protect himself in his future dealings with the contractor. The requirement of the law in this respect imposes no hardship upon the party asserting the claim, but only secures to the owner, as means of protection, what the Legislature intended for his benefit. The notice here would seem to be fatally defective ; but if this were not so, the lien fails for other and distinct causes.
And the first of these is, that the notice was not given in time. As we have seen, the last item embraced in the amount for which the lien is claimed, was furnished January 3rd, 1873, and the notice was not given until the 11th of March following, — more than sixty days after the last item to which the notice refers. It was attempted to be shown that there was a mistake in the date of this last item in the copy of the account filed in the cause and inserted in the record ; that instead of January 3rd, it should have been February 3rd, 1873; but that attempt failed. The recording clerk proves that the account filed for record was originally recorded by him, and that he transcribed the item in question as of January 3rd, 1873, and it was from the record thus made that the copy was furnished which was filed in this cause. He now states that upon a closer examination he thinks it is more like' February, and and that he has corrected the record to correspond with that belief. But there was no attempt to show how the fact really was, whether the materials charged were really de
But there is still another objection which is equally fatal to the lien, and that is, that the materials charged as of January 3rd, 1873, were furnished under a separate and distinct contract or order from that under which the other articles in the account were furnished ; and even if the notice had been otherwise sufficient, and within time to embrace the articles charged as delivered on January 3rd, it would not be in time to embrace the previous part of the account. The evidence on the subject is explicit, and leaves no room for doubt.
For the reasons stated, this lien claim must be wholly rejected.
3. As to the claim of A. Storck & Son:
This claim is also for materials furnished to the contractors for the Church, and was filed for record on the 8th of July, 1873, for $3,297.54. Notice was given on the 18th of March, 1873, of the intention to take the lien, and the only question raised upon the enforcement of the claim is, whether the articles charged in the account filed with the claim of lien were furnished under such contract or understanding as to be embraced -by the notice. The first item in the account is charged as of June 25th, 1872, and the last as of January 29th, 1873.
It would appear that it was understood from the commencement of the account, that the materials charged for
4. As to the appeal of Wilson & Hunting:
The claim of the appellants is for materials furnished the contractors for the Church, and the last item in the account was delivered on the 9th of January, 1873, the notice of intention to take the lien was given on the 6th of March, 1873, and the claim was filed for record on the 9th of July following.
There is no dispute in regard to the claim, or the right to the lien, provided it was filed at or before the expiration of six months after the materials were furnished, as required by the Code, Art. 61, sec. 23. The Court below determined that the claim was barred by the limitation in the section of the statute to which we have referred, and accordingly dismissed the hill as to this claim ; and it is from such disposition of the claim that the claimants have appealed.
It is contended for the claimants, that under the 23rd section before referred to, they had six months after the completion of the building within which to file the claim lor lien; but in this construction we do not agree. The word “finished,” used in the statute, has reference alone to work for which a lieu may he taken, and in that connection is not to be read as synonymous with completion of the building upon which the work lias been bestowed.
But, upon the construction which we place upon the terms of the statute, we think the claim in question ought to be allowed. The day upon which the last item in the account is charged should be excluded, in the computation of the time within which the lien claim could he filed. In this case the six months commenced to run'on and with the 10th of January, 1873, the 9th, the day on which the last item in the account was delivered, being regarded as an entirety, or as a mere point of time, and hence excluded from the computation. This would seem to he in accordance with the rule now generally established, though there may he exceptions to it. Bigelow vs. Wilson, 1 Pick., 465; Connell vs. Moulton, 3 Denio, 163; Sheets vs. Selden, 2 Wall., 177 ; Webb vs. Fairmaner, 3 M. & W., 473 ; Calvert vs. Williams, 34 Md., 672. There is no sufficient reason suggested why the rule should not be applied'to this case; and, according to the rule, the entire day of the 9th of July, 1873, was included within the six months allowed to the claimants for filing their claim for lien. The decree, therefore, as to this claim, must he reversed.
5. As to the claim, of F. & H. Wehr:
This claim was presented by a separate bill in equity, filed by the claimants against the contractors and the Trustees of the Church, seeking to enforce the lien, by a decree for sale of the Church building and ground, upon default of payment of the claim. The claim is for
The contract for the building of the church was executed on the 22nd of January, 1872, and was signed by Siegman & Jones, the contractors, and the building committee on behalf of the church corporation. This contract provides, among other things, that the contractors should find, provide and deliver, at their own cost and charge, free from all claims, liens and charges wholsoever, all and every kind of material, and work and labor which might “be necessary and proper for the complete execution of the building, and erect, build, furnish and complete in a good and perfect manner, (to the entire satisfaction of the architects,) the building and works, agreeably and conformably in all and every respect to the specifications, drawings, dimensions and explanations which may become necessary, according to the true intent and meaning of the drawings and specifications.” It further provides, “that should the building committee appointed by said congregation desire to make any changes from the drawings or specifications at any time during the progress of the works, the same shall be carried out by said Siegman & Jones, without making void, or in any manner affecting this contract; such changes, whether in addition to or deduction from the original works, shall be specified in writing, signed by the contractors, and the architects and the building committee. The sum to be paid or allowed for said changes or alterations, to be fixed or allowed by the architects, and specified in the writing aforesaid. The decision of the architects on this and all other matters,
The contract price for the building was $35,235.00, and the building was to be completed by the 1st of November, 1872, provided one additional month should be allowed in case it was found necessary to pile the foundation.
On the same day of the execution of this contract, the contractors, together with Frederick and Herman Wehr, and two others, as their sureties, executed their joint and several bond to the Church corporation, in the penalty of fifty thousand dollars, for the faithful execution of the contract. The condition of the bond is, that the contractors, Siegman & Jones, “shall well and faithfully fulfil their said contract, and in all respects perform and keep all and singular the stipulations on their part to be done and performed under the same.”
The Trustees of the Church, in their answer, set tip the contract and the bond, by way of defence, and deny the right of the claimants to assert or enforce their lien while they are under an obligation to protect the proj)erty from all claims, liens, and charges whatsoever, for and in respect of work done and materials furnished for the erection of the Church. .The Trustees aver, that the contractors have been paid more than two-thirds of the contract price of the building, and that such payments were made on the faith of the security that the Church corporation held in the bond ; and that there are lien claims asserted against the property, including that attempted to be enforced by the present claimants, to the amount of about $19,500. The Trustees also aver, that the contractors
To this answer the claimants put in the general replication ; and in the proof, though not in the pleadings, they undertake to relieve themselves of the defences set up by the Trustees, by showing that there were extensive changes and alterations made in the contract, other than those provided for, without the assent of the sureties, and such as enlarged the liability of the contractors ; and that, therefore, the sureties are discharged.
Upon these questions a large mass of very conflicting evidence has been produced.
The Court below held that the claimants were not es-topped from asserting their lien against the property, and that the defendants, the Trustees of the Church, could not set up any claim for damages for the non-performance of the contract by Siegman & Jones, by way of counter claim or set-off against the lien claim of the claimants sought to ho enforced, hut that the defendants should pursue their remedy at law by an action on the bond, and accordingly decreed a sale of tbe Church property, for the satisfaction of the claim, unless the amount was paid within thirty days from the date of the decree.
It does not appear that the Court below passed upon the question of the discharge of the sureties in the bond, hut left that question to be determined when the bond was sued on at law. In this we think tbe Court was right. The question of the discharge of the sureties, as also the question of the non-performance of the contract by the contractors, depending as they do upon a great variety of conflicting evidence, should be tried with the assistance of a jury. j
Rut we think the Court below was in error in decreeing as it did with respect to tlie claim of the claimants. Unless the bond lias been discharged, as contended by the claimants, it stands liable for all the liens that have been
The Court, therefore, should have retained the hill of the claimants, giving the Church corporation a reasonable time within which to bring an action on the bond, to have tried and determined the questions, whether the sureties on the bond have been discharged, as contended by them, and if not, to what extent they are liable for the defaults of their principals, the contractors. If it should be determined, from anything that has occurred, that the sureties have been discharged, (in regard to which we intimate no opinion,) then, of course, the lien can he enforced ; but if it be determined otherwise, and there should he a recovery on the bond, that judgment may be made a set-off to the lien claim of the present claimants. Such application of the doctrine of set-off or compensation is well established in Courts of equity, and the ordinary principles of justice would seem to require it in this case. In the case of Smith & Talbott vs. Donnell, 9 Gill, 89, it was said by this Court, that “the doctrine, that in Chancery equitable set-offs will be allowed, where reason and justice require it, although not authorized by any statutory enactment, is so fully established, as to render unnecessary reference to adjudications on the subject.” The Court referred to the case of Lindsay vs. Jackson, 2 Paige, 581 ; but for addi
If the property has to be sold for the satisfaction of other lien claims against it, the amount distributable to the present claimants, upon the assumption that they may ultimately be enabled’ to enforce their lien, should be set aside to abide the result of the action on the bond.
It follows from what we have said, that the decrees appealed from, as well as that passed in the case of Heise & Company against the Trustees and others, as that passed in the case of E. & H. Wehr against the Trustees of the Church, must be reversed; and the cause will bo remanded that such orders and decrees may be passed therein, as will conform to the principles stated in this opinion.
Decrees reversed, and cause remanded.