Trustees of Columbia University v. SiegelTrustees of Columbia University v. Siegel
This action was commenced to recover damages suffered by plaintiff-appellant as a result of defendants’ allegedly defective design and construction of plaintiff’s East Campus Housing Facility, a complex consisting of student residences and various other facilities. Defendant-respondent Morse/Diesel served as construction manager for the project, under an agreement which arranged for Morse/Diesel to serve as a design consultant and to provide technical advice to plaintiff, including cost monitoring and schedule coordination, to award and administer necessary subcontracts, to bear responsibility for coordinating and overseeing the work of the subcontractors, to advise plaintiff concerning costs, to obtain all necessary permits and to "assume and undertake all responsibilities of causing the Project to be completed to the Owner’s satisfaction within the Guaranteed Maximum Price”.
The project had a long and troubled history extending well after, as a result of plaintiff’s severe student housing shortage, students began to live there in 1981. The problems included extensive leakage, ponding of water in the plaza, the necessary replacement of a substantial portion of the arcade deck and of the eastern portion of the plaza, frozen pipes due to inadequate insulation, water seepage through the tile facade and extensive deterioration of bathroom tiling.
In 1988, after the buildings were fully occupied, a large chunk of the facade fell into the complex’s internal courtyard. Fortunately, although the courtyard was regularly used by students and other pedestrians, no one was injured. Because of the great danger posed by the falling facade, plaintiff immediately undertook emergency safety measures, including the erection of barricades and scaffolding, and emergency repairs to contain deteriorated areas of the facade. Plaintiff also conducted an investigation, which, it is alleged, revealed "extensive cracking of tiles, deteriorated caulking, corroded and improperly set fasteners, deteriorated lath and severe displacement of tile panels.” As a result, plaintiff determined that the facade was so severely deteriorated that it would have to be completely replaced, requiring the demolition of the original facade and the design and construction of a new facade and related building systems.
Plaintiff brought this action seeking damages, both compensatory and punitive, for breach of contract, negligence and
On a prior appeal (
Contrary to the IAS Court, we find that, particularly given the fact that only limited discovery has taken place, plaintiff has made a showing that Morse/Diesel bore, and breached, "a legal duty independent of the contract itself’ (Clark-Fitzpatrick, Inc. v Long Is. R. R. Co.,
Contrary to the trial court, we do not find that the cause of action for negligence is precluded by the decision in Bellevue S. Assocs. v HRH Constr. Corp. (
While we find that plaintiff’s negligence claim should be reinstated, we agree that plaintiff’s claim for strict liability may not stand. The construction contract in this case was clearly for the performance of a service, and, as such, it does not fall within the sphere of strict products liability (Milau Assocs. v North Ave. Dev. Corp.,
Finally, on the cross appeal, we find that defendant Emery Roth & Sons, P. C., has failed to show that it has been prejudiced as a result of the increase in the ad damnum clause from "at least” $10 million to "at least” $25 million. In the absence of prejudice, leave to amend an ad damnum clause is freely granted, and we find no reason to disturb the court’s exercise of its discretion.
Accordingly, the order of the Supreme Court, New York County (David B. Saxe, J.), entered on or about January 7, 1992, which, inter alia, granted partial summary judgment dismissing plaintiff’s twelfth and thirteenth causes of action, for strict liability and negligence, against defendant Morse/ Diesel, Inc., and granted plaintiff’s cross motion to increase the ad damnum clause, should be unanimously modified to reverse that portion of the order which granted defendant’s motion for summary judgment on plaintiff’s thirteenth cause of action, sounding in negligence, and to deny the motion as to that cause of action, and should otherwise be affirmed, without costs.
Milonas, J. P., Ellerin, Kassal and Rubin, JJ., concur.
Order, Supreme Court, New York County, entered on or about January 7, 1992, unanimously modified to reverse that portion of the order which granted defendant’s motion for summary judgment on plaintiff’s thirteenth cause of action, sounding in negligence, and to deny the motion as to that cause of action, and otherwise affirmed, without costs.