delivered the opinion of the court:
Plaintiff, the Trunkline Gas Company, filed four separate petitions in the circuit court of Champaign County seeking to condemn, for a pipe-line right of way, an easement strip extending across farm lands owned by the respective defendants. In each instance, defendants filed a cross petition for damages to land not taken and the causes were thereafter consolidated for purposes of trial. After trial by a jury, which viewed the premises, defendants recovered verdicts and judgments totaling $3,865.50 for 6.5 acres lying within the easement strip. As to the cross petitions, however, the court directed verdicts for the plaintiff and it is from this action of the court that defendants appeal. The sole issue raised is whether the court properly excluded the testimony by which defendants sought to prove damages to land lying outside the easement strip.
Before looking to the disputed testimony, a better understanding of the issue involved requires a brief explanation of the project to be undertaken by the plaintiff. The allegations of the petition, which are binding on the condemnor, (East Peoria Sanitary Dist. v. Toledo, Peoria and Western Railroad Co.
Howard Hibbler, plaintiff’s project engineer, testified there would be no valves, pipe or structures above the surface of the ground on defendants’ land and that all construction activities would be carried out within the limits of the 66-foot easement strip. He explained that a crew first cuts fences, then clears and grades the right of way, after which a trench, 36 inches wide and 4 feet 8 inches deep is dug. Pipe is then hauled onto the property on large trucks and is placed in the trench, which is then backfilled. The latter operation, he stated, would leave a ridge 38 inches wide and from 6 to 8 inches in height, which the witness estimated would settle to the level of the surrounding ground within a period of one month, or after the first substantial rainfall. When cross-examined extensively about the procedure when drain tile was encountered, Kibbler testified that the trench bottom was lowered to allow a clearance of 6 inches between the pipe and the tile, that the tiles were swabbed to check for leakage, and that, during the backfill operation, earth under the tile is padded by hand. He likewise explained the process by which a leak in the line would be repaired and said that once the line was in operation, an airplane would patrol it every two weeks to check for erosion or leakage.
To sustain their burden of proving damage to land not taken, (See: City of Chicago v. Provus,
Edward C. Butzow and Earl C. Haddock, two of the defendants, sought to give testimony in their own behalf, and although each was shown to have long experience in farming, including the cultivation of areas where excavations had been made for drainage tile, the trial court agreed with plaintiff that the witnesses were not qualified to give their opinions because they had never farmed land over a pipe line.
The question of the market valúe of real property has been said to be one of fact, not of art or science, (Illinois Power and Light Corp. v. Talbott,
There remains, however, the question of whether the testimony of these witnesses, and the three remaining witnesses, was properly refused because their opinions as to value were based upon remote, speculative and improper elements of damage. To warrant a recovery for damage to land not taken, the damage must be direct and proximate, (Illinois Power and Light Corp. v. Barnett,
We see no useful purpose in setting forth the testimony of each witness in detail, or in relating all of the elements of damage upon which they based their opinions that the land not taken would be depreciated in value. In general, the elements mentioned by all were: the inconvenience in farming that would be caused by the pipe line, the possible effects upon surface and tile drainage, and the dangers of fire and explosion attending the pipe line.
In the matter of agricultural lands, permanent interference with farming caused by an improvement, as distinguished from temporary interference or inconvenience, has at various times been held to be a proper element of damage to land not taken. (See: Illinois Power and Light Corp. v. Barnett,
Two witnesses speculated that the improvement would affect the surface drainage upon the lands not taken, but made no explanation as to why this was so, and two witnesses likewise stated their opinions were based on the possibility that the line would interfere with future tiling, if any should be needed. On the state of the record, these demerits are not only speculative, but also overlook that plaintiff bound itself by its petitions to restore all drain tile to the condition in which it existed before the improvement.
The majority of the witnesses testified that the danger of fire and explosion attending a leakage of gas from the line would depreciate the value of the land not taken. While we are of the opinion such dement of damage would be entirely proper where a high pressure gas line is situated in close proximity to buildings or habitations, (cf. Northern Indiana Public Service Co. v. Darling,
. Defendants likewise urge upon us numerous railroad right-of-way cases where the danger of fire from passing trains has been considered as a proper element of damage to land not taken. (Eg. Chicago, Peoria and St. Louis Railway Co. v. Blume,
Without the discussion of other elements relied upon by the witnesses which we deem improper, we conclude, on the basis of the particular record before us, that the testimony of defendants’ witnesses was properly excluded. Accordingly, the judgment of the circuit court of Champaign County is affirmed.
Judgment affirmed.
