66 Conn. App. 681 | Conn. App. Ct. | 2001
Lead Opinion
Opinion
In this action, which was commenced pursuant to the Connecticut Product Liability Act (act),
The following facts and procedural history are relevant to the disposition of the plaintiffs’ appeal. On November 23,1998, the plaintiffs filed an amended complaint in which they alleged that the defendant was hable to them for damages resulting from a fall Mary Truglio had suffered while walking on a sidewalk in 1996. In support of that allegation, the plaintiffs pleaded the following: (1) a defect in the sidewalk caused Mary Truglio to fah; (2) the defendant constructed that sidewalk in a defective manner; (3) that sidewalk was a “product” under the act; (4) the defendant was a “product seller,” as defined in the act; and (5) the defendant was hable under the act for damages resulting from the fall.
On March 21, 2000, the court granted the defendant’s motion for summary judgment, concluding that (1) the sidewalk that the defendant had constructed was not a “product” and (2) therefore, the plaintiffs’ claims were beyond the scope of the act. In so doing, the court consulted the Model Uniform Product Liability Act (model act), 44 Fed. Reg. 62,714-50 (1979), because the legislature, in General Statutes § 52-572m et seq., had not defined the word “product.” The model act provides in relevant part: “ ‘Product’ means any object possessing intrinsic value, capable of deliveiy either as an assembled whole or as a component part or parts, and produced for introduction into trade or commerce. . . .”44 Fed. Reg. 62,717. Applying that definition, the court concluded that the on-site construction of a sidewalk using the form and pour method was not a product but a service. After reviewing the parties’ affidavits, the
INTRODUCTION
For the plaintiffs to succeed ultimately in this product liability action, they must establish that the sidewalk that the defendant constructed was a product. See Zichichi v. Middlesex Memorial Hospital, 204 Conn. 399, 403, 528 A.2d 805 (1987); see also General Statutes § 52-572n (a). The act does not include a definition for the term “product;” a definition for the term “product seller” is provided, however. General Statutes § 52-572m (a). “ ‘Product seller’ means any person or entity, including a manufacturer, wholesaler, distributor or retailer who is engaged in the business of selling such products whether the sale is for resale or for use or consumption. The term ‘product seller’ also includes lessors or bailors of products who are engaged in the business of leasing or bailment of products.” General Statutes § 52-572m (a).
The definition of “product seller” provided by § 52-572m (a) is identical to the definition provided by § 102 (1) of the Draft Uniform Product Liability Law (draft act), 44 Fed. Reg. 2996, 2997-98 (1979). Also, the draft act, like § 52-572m et seq., does not include a definition for the term “product.” See id., 2996-3019. Those are not mere coincidences, for, as our Supreme Court previously has stated, the legislature based § 52-572m et seq. on the draft act (not on the model act). See, e.g., Potter v. Chicago Pneumatic Tool Co., 241 Conn. 199, 230, 694 A.2d 1319 (1997); Elliot v. Sears, Roebuck &
The commentary to § 102 (1) of the draft act provides in relevant part: “The Act does not address several definitional problems of ‘product seller.’ First, it does not address the problem of the product seller engaged in a service. See ‘Newmark v. Gimbel’s Inc.,’ 54 N.J. 585, 258 A.2d 697 (1969). It is suggested that a party be considered a product seller where a sale of a product is a principal part of the transaction and where the essence of the relationship between the buyer and seller is not the furnishing of professional skill or services. See Annot., 29 ‘A.L.R.’ 3d 1425 (1970).” (Emphasis in original.) 44 Fed. Reg. 3003.
As we conclude in this opinion, the affidavits and other evidence in the present case disclose that the defendant constructed the sidewalk using the form and pour method. See part II. The essence of the relationship between the defendant and the buyer was the furnishing of a service, not the sale of a product, because the sidewalk was composed of concrete that was transported in liquid form to the site and then used by the defendant to pour the sidewalk. See footnote 6. With that conclusion in mind, we now consider the plaintiffs’ procedural claim and, thereafter, explain the basis for our conclusion that the defendant constructed the sidewalk using the form and pour method.
I
First, the plaintiffs claim that the court improperly permitted the defendant to challenge the legal suffi
The following procedural history is relevant to the plaintiffs’ claim. In their operative complaint, the plaintiffs alleged, inter alia, that “the defendant . . . caused to be designed, constructed, manufactured and installed the sidewalk-in-issue which is a product pursuant to [General Statutes] § 52-572m.” The defendant did not file a request to revise the amended complaint; see Practice Book § 10-35;
In its motion for summary judgment, the defendant raised the following three part argument: (1) a sidewalk is not necessarily a “product,” i.e., a sidewalk constructed using the form and pour method is not a “prod
The plaintiffs claim that they were prejudiced by the court’s decision to consider, and later credit, the defendant’s three part argument in favor of summary judgment. Specifically, the plaintiffs maintain that they were prejudiced when the court considered a challenge to the legal sufficiency of their complaint (a motion to strike) in the context of the motion for summary judgment. We recognize that “[tjhere is a substantial difference between a motion for summary judgment and a motion to strike. The granting of a defendant’s motion for summary judgment puts the plaintiffs out of court, as it did in this case. See Practice Book § 17-49. The granting of a motion to strike allows the plaintiff to replead his or her case. See Practice Book § 10-44.” Rivera v. Double A Transportation, Inc., 248 Conn. 21, 38 n.3, 727 A.2d 204 (1999) (Berdon, J., concurring in part, dissenting in part).
Given the procedural history of the case, we instead believe that the following inquiry must be undertaken to resolve the plaintiffs’ claim: (1) whether the plaintiffs were capable of obtaining additional affidavits or other evidence in their effort to contradict Hayes’ affidavit, which indicated that the defendant used only the form and pour method when constructing sidewalks, and, if so, (2) whether the procedural latitude that the court afforded the defendant prevented the plaintiffs from obtaining that evidence in time to aid in their efforts to oppose the defendant’s motion for summary judgment. The record discloses that the plaintiffs did not file a motion for extension of time to file their opposition to the defendant’s motion for summary judgment. The record discloses also that the plaintiffs did not otherwise indicate to the court that they were capable of obtaining additional affidavits or other evidence to aid in their efforts to contradict Hayes’ affidavit. Moreover, in their appeal, the plaintiffs have not asserted that, since filing their opposition to the motion for summary judgment, they obtained additional evidence that would have aided in their efforts to contradict Hayes’ affidavit. From those circumstances, we infer that the plaintiffs were not capable of obtaining additional evidence in
II
The plaintiffs claim that the court improperly granted the defendant’s motion for summary judgment. Specifically, the plaintiffs argue that the court improperly concluded that they failed to contradict Hayes’ affidavit averring (1) that the defendant used only the form and pour method, and (2) the defendant constructed the sidewalk in question using that method. We disagree.
“ ‘The standards governing our review of a trial court’s decision to grant a motion for summary judgment are well established. Practice Book § 384 [now § 17-49] provides that summary judgment shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. ... In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party. . . . The party seeking summary judgment has the burden of showing the absence of any genuine issue [of] material facts which, under applicable principles of substantive law, entitle him to a judgment as a matter of law . . . and the party opposing such a motion must provide an evidentiary foundation to demonstrate the existence of a genuine issue of material fact.’ ” (Citations omitted.) Rivera v. Double A Transportation, Inc., supra, 248 Conn. 24.
When viewed in the light most favorable to the plaintiffs, the affidavits and other proof submitted by the parties disclose that Hayes’ affidavit is uncontradicted.
Halprin, in his affidavit, averred in relevant part: “3. In my experience, construction is sometimes accomplished by the forming of concrete slabs at a central location and the transportation of those slabs for installation at the site. 4. The front walkway at the post office could have been installed by means of delivery to the site of precast concrete slabs.”
Contrary to the plaintiffs’ assertion, Halprin’s affidavit does not contradict Hayes’ affidavit.. At best, Halprin averred that (1) sidewalks are sometimes composed of prefabricated concrete slabs that are merely installed on-site and (2) the sidewalk on which Mary Truglio allegedly fell could be composed of prefabricated concrete slabs. “It has long been recognized that, in order to avoid speculation and conjecture, ‘[a] trier is not concerned with possibilities but with reasonable probabilities.’ Boland v. Vanderbilt, 140 Conn. 520, 525, 102 A.2d 362 (1953). . . . ‘Whether an expert’s testimony is expressed in terms of a reasonable probability that an event has occurred does not depend upon the semantics of the expert or his use of any particular term or phrase, but rather, is determined by looking at the entire substance of the expert’s testimony.’ Struckman v. Burns, 205 Conn. 542, 555, 534 A.2d 888 (1987).” (Citations omitted.) Vickers v. Jessup, 32 Conn. App. 360, 363-64, 629 A.2d 457, cert. granted, 227 Conn. 922, 632 A.2d 701 (1993) (appeal withdrawn March 18, 1994).
The judgment is affirmed.
In this opinion SPEAR, J., concurred.
General Statutes § 52-572m et seq.
See General Statutes § 52-572n (a), which provides: “A product liability claim as provided in sections 52-240a, 52-240b, 52-572m to 52-572q, inclusive, and 52-577a may be asserted and shall be in lieu of all other claims against product sellers, including actions of negligence, strict liability and warranty, for harm, caused by a product.” (Emphasis added.)
Practice Book § 10-35 provides in relevant part: “Whenever any party desires to obtain (1) a more complete or particular statement of the allegations of an adverse party’s pleading . . . the party desiring any such amendment in an adverse party’s pleading may file a timely request to revise that pleading.”
Practice Book § 10-39 (a) provides in relevant part: “Whenever any party wishes to contest (1) the legal sufficiency of the allegations of any complaint, counterclaim or cross claim, or of any one or more counts thereof, to state a claim upon which relief can be granted, or (2) the legal sufficiency of any prayer for relief in any such complaint, counterclaim or cross complaint . . . that party may do so by filing a motion to strike the contested pleading or part thereof.”
In the first part of its three part argument, the defendant maintained that a sidewalk constructed using the form and pour method is not a “product” under General Statutes § 52-572m et seq.
In his affidavit, Hayes stated in relevant part: “2. I make this affidavit of my own free will and based on my personal knowledge.
“3.1 have been employed by The Hayes Construction Company since May 1973, and by MS&P Construction Co. since August 1983.
* ** *
“7. The sidewalks and walkways at the Post Office [the location where Mary Truglio allegedly fell] were constructed on site by the form and pour’ method, which is the only way that sidewallcs or walkways are and have been created by MS&P (now known as The Hayes Construction Company).
“8. The ‘form and pour’ method consists of the following: After the placement of the structural fill, and compaction of that material, which in the case of the Post Office was done by Reliable Excavating Company, Inc., sidewalk forms were constructed of lumber by an MS&P (Hayes) employee. The inside of the wood forms were coated with a petroleum spray for easy stripping of the wood forms once the concrete has set up. A concrete mixture was delivered to the job site by a concrete mixer and was poured from a chute into the wood forms. A straight edge known as a screed, was then dragged across the top of the form to smooth out the contents. Concrete finishers then hand floated the concrete surface using wood or metal floats. A ‘broom finish’ was then given to the hardening concrete, using a com broom. That gave the concrete texture. The wood forms were removed approximately twenty-fours after the concrete was poured.”
Additionally, we note that the plaintiffs claim that Hayes’ affidavit was not based on personal knowledge and, therefore, was invalid. Because the plaintiffs failed to brief that claim adequately, we deem it abandoned and, therefore, decline to review it. See State v. Mims, 61 Conn. App. 406, 410, 764 A.2d 222, cert. denied, 255 Conn. 944, 769 A.2d 60 (2001).
Concurrence Opinion
concurring. I concur respectfully with the result reached by the majority, but I disagree with the route taken to reach that result. I also disagree with the plaintiffs’ claim that the defendant used the motion for summary judgment as amotion to strike, i.e., to test the legal sufficiency of the complaint, and that the trial court gave the defendant procedural latitude in granting its motion for summary judgment.
A motion to strike tests the legal sufficiency of a complaint to state a recognized cause of action. Practice
The plaintiffs’ cause of action rises and falls on how the sidewalk was constructed.
The court then decided as a matter of law that a sidewalk created by the form and pour method was not a product under our products liability act. I agree with that portion of the majority opinion affirming the trial court’s resolution of that issue. The court properly rendered summary judgment in favor of the defendant because the defendant would have been entitled to a directed verdict as a matter of law. Because the court rendered summary judgment in keeping with our law and procedure, it did not afford the defendant any procedural latitude by treating the motion for summary judgment as a motion to strike.
The plaintiffs appear to have constructed their argument in this court around the sequence of the defendant’s argument in the trial court. Appellate courts must resist the temptation to adopt the labels assigned and logic followed by parties if the appellate mind is of a different opinion.
“In an appeal from a judgment following the granting of a motion to strike, we must take as true the facts alleged in the plaintiffs complaint and must construe the complaint in the manner most favorable to sustaining its legal sufficiency. ... A motion to strike admits all facts well pleaded. ... A determination regarding the legal sufficiency of a claim is, therefore, a conclusion of law, not a finding of fact. Accordingly, our review is plenary. ... If facts provable in the complaint would support a cause of action, the motion to strike must be denied. . . . Moreover, we note that [w]ha.t is necessarily implied [in an allegation] need not be expressly alleged.” (Citations omitted; internal quotation marks omitted.) Emerick v. Kuhn, 52 Conn. App. 724, 728-29, 737 A.2d 456, cert. denied, 249 Conn. 929, 738 A.2d 653, cert. denied sub nom. Emerick v. United Technologies Corp., 528 U.S. 1005, 120 S. Ct. 500, 145 L. Ed. 2d 386 (1999).
The majority states in the first sentence of its introduction that for the plaintiffs to succeed ultimately, they must prove that the sidewalk that the defendant constructed was a product. Implicitly, before the plaintiffs can prove that the sidewalk was a product, they must prove that there was no genuine issue as to how the sidewalk was constructed.
I also disagree with the majority’s citing of Boucher Agency, Inc. v. Zimmer, 160 Conn. 404, 409-10, 279 A.2d 540 (1971). As this court has twice before stated; see Gould v. Mellick & Sexton, 66 Conn. App. 542, 554 n.12, 785 A.2d 265 (2001); Burke v. Avitabile, 32 Conn. App. 765, 772 n.9, 630 A.2d 624, cert. denied, 228 Conn. 908, 634 A.2d 297 (1993); Zimmer is anomalous and limited to the unusual facts and procedural posture of that case. At the time that Zimmer was decided, a motion for summary judgment could be filed only when the pleadings were closed. Effective October 1, 1992, our rules of practice were amended to permit a motion for summary judgment to be filed at any time. Practice Book § 379, now § 17-44.