Trucco Constr. Co., Inc. v. FremontTrucco Constr. Co., Inc. v. Fremont
Allen L. Rutz, Shantae D. Clayborn, and Mitchell A. Tobias, for appellants.
DECISION AND JUDGMENT
HANDWORK, J.
{¶ 1} This appeal is from the February 27, 2012 judgment of the Sandusky County Court of Common Pleas denying a
THE TRIAL COURT ERRED IN CONCLUDING THAT THE ARDADIS APELLANTS WERE NOT IMMUNE FROM APPELLEE‘S TORT CLAIMS PURSUANT TO
R.C. 2744.03(A)(6) .
{¶ 2} The following facts are alleged in Trucco‘s complaint. In 2009, the city of Fremont and Trucco, an Ohio corporation engaged in the construction business, entered into a contract for the phase one construction of a 727 million gallon raw water reservoir (hereinafter the “project“). During construction of the reservoir, issues arose regarding the availability of a sufficient amount of clay soil on the site needed to make the reservoir.
{¶ 3} Trucco alleges the design and specifications for the project did not include an imported or man-made clay liner or a requirement that the existing soils would need to be mixed with a soil sealer. Furthermore, Trucco claimed that the city of Fremont and appellants concealed from Trucco the fact that a “Raw Water Supply Study” indicated that one of these options was necessary and soil testing by Toltest, Inc. resulted in warnings of a potential reservoir leakage and the possible need for a synthetic liner to control leakage. Furthermore, Trucco was not informed that other bidders for the project
{¶ 4} Trucco alleged that appellant Harmsen had estimated that more than $5 million in charges would result from change orders. Regular meetings were being held between Trucco and the city of Fremont and appellants to discuss the extra costs incurred by Trucco. The onsite representative of appellants, Jerry O‘Kenka, would direct Trucco to perform work in a certain manner to minimize the need to remove waste material. Trucco continued to take exclusive directions from appellants and O‘Kenka. Trucco communicated to the city of Fremont through appellants and appellants responded directly to Trucco as the city relied solely upon appellants to make all decisions related to the day-to-day construction of the project.
{¶ 5} During the course of the project and when Trucco sought additional compensation for additional expenses incurred due to appellants’ changes in the construction design, appellants had the of city of Fremont review its draft responses to Trucco‘s requests for additional compensation before it responded to Trucco. Trucco
{¶ 6} In January 2010, the city of Fremont terminated the project contract for convenience pursuant to the general conditions of the contract. Thereafter, Trucco also terminated the contract for convenience and submitted its claim to the city of Fremont as required by the project contract. Both the city of Fremont and Trucco brought suit against the other. Trucco asserted that the city of Fremont refused to pay Trucco for expenses under the contract totaling $247,074.52.
{¶ 7} In 2011, Trucco amended its complaint a second time to add appellants as additional defendants. ARCADIS is a construction business registered to do business in Ohio providing consultancy, design, engineering, and management services in the fields of infrastructure, water, environment, and buildings. Harmsen, Zimmerman, and Barhorst, all ARCADIS employees, served as design engineers on the project. Trucco asserted claims against appellants; of professional negligence intentional misrepresentations (that the project was buildable, that there was enough clay on site to build the project, and that this was a balanced site) which were made with malice or fraudulently; negligent misrepresentations; and tortious interference with contract by inducing the city of Fremont to breach the project contract. Trucco sought damages of $4,826,277.72.
{¶ 9} The trial court held a hearing on the motion on February 22, 2012. The trial court denied appellants’ motion to dismiss without explanation on February 27, 2012. Appellants sought an appeal from this judgment on March 13, 2012.
{¶ 10} In their sole assignment of error, appellants argue that the trial court erred by failing to find that they should be included under the city of Fremont‘s sovereign immunity protection as its agents and were employees acting within the scope of their employment with the city. Furthermore, appellants argue that none of the exceptions to statutory immunity apply.
{¶ 11} An appellate court reviews a trial court‘s ruling on a
{¶ 12} In the case before us, appellants argue that Trucco cannot assert tort claims against appellants because the General Assembly has precluded claims against them under the doctrine of statutory immunity.
{¶ 13} An employee of a political subdivision is defined in
“Employee” means an officer, agent, employee, or servant, whether or not compensated or full-time or part-time, who is authorized to act and is
acting within the scope of the officer‘s, agent‘s, employee‘s, or servant‘s employment for a political subdivision. “Employee” does not include an independent contractor * * *.
{¶ 14} Appellants first argue that the issue of whether they fall within the definition of “employee” under this statute has already been admitted by Trucco because it acknowledged throughout its complaint that appellants were authorized to act as agents for the city and Trucco looked to appellants for any information about the project.
{¶ 15} We disagree. While Trucco may have imprecisely used the term “agent” in its complaint, it is clear that when appellants asserted a claim of statutory immunity, Trucco argued in its response to the motion to dismiss that appellants are independent contractors, not employees. Therefore, we do not find that Trucco waived any right to challenge appellants’ claim of immunity.
{¶ 16} Appellants argue they are “employees” of the city of Fremont because they acted as agents for the city of Fremont to deal with Trucco and that appellants always acted within the scope of their employment. Appellants contend that the substance of Trucco‘s tort allegations closely align with appellants’ duties defined in the construction and engineering contracts.
{¶ 17} Trucco first argues that ARCADIS cannot be an “employee” within the definition of employee under
{¶ 18} Appellee also argues that appellants do not fall under the definition of “employee” because they are independent contractors of the city of Fremont.
{¶ 19} Numerous courts have considered the extent of the term “employee” under
{¶ 20} Courts also consider how a contract between the political subdivision and a party defined their relationship. Zacharias v. Ampco Systems Parking, 9th Dist. No. 18672, 1998 WL 312540 *3 (June 10, 1998) (parking management company was an “employee/agent” of the city pursuant to its contract with the city for managing a city parking garage) and Kiep v. City of Hamilton, 12th Dist. No. CA96-08-158, 1997 WL 264236, *8 (May 19, 1997) (the issue of whether or not a tree contractor was immune from suit by a homeowner was not fully litigated because it was unclear under its contract with the city whether the tree contractor was an agent of the city or an independent contractor).
2.01 The Project has been designed by ARCADIS U.S., Inc., who is hereinafter called ENGINEER and who is to act as OWNER‘S representative, assume all duties and responsibilities and have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents.
The “General Conditions” of this contract provide that:
9.01 OWNER‘S representative
A ENGINEER will be OWNER‘s representative during the construction period.
* * *.
9.09 Decisions on Requirements of Contract Documents and Acceptability of Work
A. ENGINEER will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. * * *.
B. When functioning as interpreter and judge under this paragraph 9.09, ENGINEER will not show partiality to OWNER or CONTRACTOR
and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity. * * *. * * *.
9.10 Limitations on ENGINEER‘s Authority and Responsibilities
A. Neither ENGINEER‘s authority or responsibilities under this Article 9 or under any other provision of the Contract Documents nor any decision made by Engineer in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise, or performance of any authority or responsibility by ENGINEER shall create, impose, or give rise to any duty in contract, tort, or otherwise owed by ENGINEER to CONTRACTOR, any Subcontractor, any Supplier, any other individual or entity, or to any surety for or employee or agent of any of them.
* * *.
{¶ 22} Secondly, a party is classified as an independent contractor, rather than an employee or agent, based upon the ability of the political subdivision to control the work to be performed. When a party agrees to produce some end product or result without the other political subdivision having any right to control the method of accomplishing the specific work/services to be performed, that party is deemed to be an independent contractor. See Councell v. Douglas, 163 Ohio St. 292, 126 N.E.2d 597 (1955), paragraph one of the syllabus; Bobik v. Industrial Comn., 146 Ohio St. 187, 192, 64 N.E.2d 829 (1946); Gillum v. Indus. Comm., 141 Ohio St. 373, 48 N.E.2d 234 (1943), paragraph two of the syllabus. See also Weldon v. Prairie Twp., 10th Dist. No. 10AP-311, 2010-Ohio-5562, ¶ 13 (township not liable for damages caused by contractor‘s repair of sewer line because the township did not control the contractor‘s repair).
{¶ 23} Since the determination of whether a party is an employee/agent or an independent contract generally involves issues of fact for the trier of fact to determine, the specific facts of a particular case could alter application of the general rule. Bostic v. Connor, 37 Ohio St.3d 144, 524 N.E.2d 881 (1988), paragraph one of the syllabus. However, when there is no conflicting evidence, the issue becomes a question of law. Schickling v. Post Publishing Co., 115 Ohio St. 589, 155 N.E. 143 (1927) syllabus.
{¶ 24} Upon a review of the evidence in this case, we find that there was no conflicting evidence presented. The city of Fremont entered into a standard engineering contract with ACRADIS for the creation of plans and specifications to build a reservoir, supervision of the construction phase of the project, and a final inspection of the construction. Even though the contracts in this case provide that ARCADIS would act as the city of Fremont‘s representative during the construction phase, those provisions do not give rise to an agency or employment relationship. These provisions simply provide that the engineers would be the city‘s liaison with Trucco because the city of Fremont relied upon the professional skills of ARCADIS to ensure that the plans and specifications would be properly accomplished. For this reason, ARCADIS was named as a neutral party to interpret the requirements of the contract when disputes arose. There
{¶ 25} Having found that the trial court did not commit error prejudicial to appellants, the judgment of the Sandusky County Court of Common Pleas is affirmed. Appellants are ordered to pay the court costs of this appeal pursuant to App.R. 24.
Judgment affirmed.
A certified copy of this entry shall constitute the mandate pursuant to App.R. 27. See also 6th Dist.Loc.App.R. 4.
Peter M. Handwork, J.
Arlene Singer, P.J.
Thomas J. Osowik, J.
CONCUR.
JUDGE
JUDGE
JUDGE
This decision is subject to further editing by the Supreme Court of Ohio‘s Reporter of Decisions. Parties interested in viewing the final reported version are advised to visit the Ohio Supreme Court‘s web site at: http://www.sconet.state.oh.us/rod/newpdf/?source=6.