262 P. 320 | Cal. | 1927
Action brought to foreclose a mechanic's lien. The plaintiff and defendant, Joe Siegel, entered into a contract whereby plaintiff was to construct a frame dwelling-house and garage upon a certain lot owned by defendant Siegel situated in the city of Anaheim, county of Orange, and for which said defendant agreed to pay plaintiff the sum of $2,850, $1,000 of which sum was paid. Work under this contract was commenced on May 16, 1923, and the contract was completed about July 28, 1923, and on August 6, 1923, plaintiff filed for record his claim of lien against said real property. In the meantime, however, the defendant Siegel had borrowed of the defendant, the State Mutual Building Loan Association, the sum of $2,800, evidenced by a promissory note in said amount, which note was secured by a trust deed to said real property, executed by defendant Siegel and wife in favor of the Title Insurance Trust Company of Los Angeles, as trustee. This trust deed was delivered and recorded *708 five days after plaintiff commenced work under his contract to construct said house. The interest on said promissory note not having been paid when due, the trustee advertised and sold said real property according to the terms of said trust deed to satisfy the indebtedness evidenced by said promissory note, and at said sale the defendant, the State Mutual Building and Loan Association, became the purchaser of said real property and thereby became the owner of the legal title to the same. At the trial of said action the court sustained an objection to the introduction of said claim of lien upon the ground that by its terms it failed to meet the requirements of section 1187 of the Code of Civil Procedure, which provides that claims of lien shall contain among other things "a general statement of the kind of work done or materials furnished by him, or both." Judgment was rendered in favor of defendant, State Mutual Building Loan Association, and against plaintiff. From this judgment the plaintiff has appealed, and the sole point involved in this appeal is the sufficiency of the statement in said claim of lien "of the kind of work done or materials furnished" by plaintiff under his said contract. Plaintiff's claim of lien was as follows:
"Lot 3 of the Scenic Tract according to a map thereof recorded in the office of the county recorder of Orange county, California.
"That the name of the owner or reputed owner of said premises is Joe Siegel, and the name of the contractor who engaged with the said Joe Siegel to erect said building is George E. Trout, the undersigned.
"That no notice of completion of said building has been filed as required by law.
"That the said contractor agreed to erect the building above indicated, and to furnish the materials to be used in the building and construction thereof, excepting the paint *709 and painting, upon the terms, at the times given and upon the conditions as follows, to-wit:
"Full contract price to be paid to the said contractor when the building was completed and all bills against the same shown to have been paid by the undersigned, which building was to have been completed 45 days from and after the commencement of work, but after the date of said contract, the same was amended so as to provide for greater dimensions and to include the building of a garage on said premises by the undersigned.
"That said contract has been fully performed on the part of said George E. Trout that all materials furnished were actually used in the construction of said building that said building was finished on the 28th day of July, 1923.
"That the amount of contract price for said building furnished as aforesaid is $3,050.00 in current lawful money of the United States, specified in the contract, but after the execution of said contract, it was understood and agreed between the said owner and said contractor that the same should be reduced $200.00, and the said contractor released from the obligation of painting said building, which undertaking the said owner took upon himself on account of said reduction in contract price, that the sum of $1,000.00 has been paid on account of said contract price and that the sum of $1,850.00 is still due and owing thereon to said contractor, George E. Trout, after deducting all just credits and offsets.
"Wherefore the said George E. Trout claims a lien upon the above described premises for the amount of said contract price still unpaid.
"GEO. E. TROUT."
It will be observed that this notice of lien states that the contract is "for the construction and erection of a certain building on the premises," describing them; that the contractor (plaintiff) agreed to erect said building and "to furnish the materials to be used in the building and construction thereof, excepting the paint and painting" and that said contract has been fully performed and "all of said materials furnished were actually used in the construction of said building that said building was finished on the 28th day of July, 1923." *710
[1] The statutes of this state giving to mechanics and others liens upon real property for work done or materials furnished in the construction of buildings or other structures are to be liberally construed (sec. 14, chap. 681, Stats. 1911, p. 1319;Continental etc. Assn. v. Hutton,
[2] In the case of Wagner v. Hensen,
The court erred to the serious prejudice of appellant in sustaining respondent's objection to the introduction of said claim of lien.
The judgment is therefore reversed.
Preston, J., and Seawell, J., concurred.