80 Ct. Cl. 559 | Ct. Cl. | 1935
delivered the opinion of the court:
This case arises under a contract entered into between plaintiff and the United States for dredging a certain area in Fore Fiver, Portland Harbor, Maine. Plaintiff was required to furnish all labor and material, perform all work required, and was to be paid 32 cents a cubic yard for the material removed. The specifications mentioned the fact that a certain railroad bridge which spanned the area to be dredged had recently been removed and also stated that “ The material to be removed is believed to be soft mud and soft clay with some broken pile ends in the site of the old railroad bridge, but bidders are expected to examine the work and decide for themselves as to its character and to make their bids accordingly.” When plaintiff commenced work it found a large number of driven piles in and about the bridge area not specifically mentioned in the specifications and it now seeks to recover the additional cost incurred in removing the piles and other debris which made its work more expensive than.it otherwise would have been. In support of this part of the claim it is urged that the conditions found were so different in character from those represented by the specifications that they operated to the prejudice of the contractor and gave rise to a claim for extra payment for the work involved.
Plaintiff makes no claim of fraud or positive misrepresentations on the part of the Government in its invitation for bids or in the specifications, or that the Government with
With respect to an examination of the area it is urged by plaintiff that it had only ten days from the date of the invitation for bids to the date it was required to submit its bid, and that within that time it could not have made such an examination as would have advised it fully as to the character of obstructions encountered. The specifications were clear and it does not appear that plaintiff made any serious attempt to determine for itself the character of the material to be dredged. Its examination consisted of “ punching the job out with a rod.” Upon examination it submitted its bid at the price which the defendant paid. The examination made shows that plaintiff was not relying upon statements made in the invitation for bids as positive representations. At the time plaintiff submitted its bid it was carrying on a dredging operation in an area immediately adjacent to the one on which its bid was submitted and it was not only familiar with the area but knew that the railroad bridge had only recently been removed. The fair inference from these facts would seem to be that plaintiff was as fully advised as to the character of the material to be dredged as was the defendant and that it was satisfied from such examination as it made and its general knowledge of the area to take a chance on its
It should be further observed that even after plaintiff found the obstructions of which it complains, it failed to take any of the steps provided in the contract in order to obtain relief. No written protest was filed with the contracting officer, nor was appeal taken to the head of the department concerned. All it did was to protest by telephone conversation with the senior civilian engineer and rest its case with such a statement until several months later when the contract was about completed. Plaintiff was familiar with the terms of the contract in question and had carried out other contracts of a similar nature with the Government. To allow recovery in this instance would amount to a disregard of many of the provisions of the contract and establish a dangerous precedent in cases of this character. Sanford & Brooks Co. v. United States, 267 U. S. 455.
It is also shown that at the time bids were invited a competitor of plaintiff was engaged in dredging an area which crossed the site of the old railroad bridge. It is fair to suppose that in submitting its bid it took into consideration the obstructions which it doubtless knew to exist, and since plaintiff was the successful bidder it is a reasonable conclusion that the competitor submitted a higher bid than that of plaintiff. In effect plaintiff asks that it be compensated for work that was reasonably covered by the specifications and which other bidders may well have considered in making their bids, but which plaintiff contends it did not consider in making its bid and for which it did not request a change order during the period of operations. In such circumstances relief cannot be given.
The foregoing conclusion disposes of plaintiff’s claim that it should be compensated for the cost of bringing an additional lighter to the scene of operations and also for the delays which occurred when the obstructions were encountered.
The further contention is made that the defendant erroneously deducted $6,340 as liquidated damages for failure to complete the work within the time specified in the contract. The specifications that accompanied the invitation for bids provided that the successful bidder should begin work within 15 days after notice from the defendant to proceed. The specifications also provided for the dumping of the dredged material at a point some five miles from the channel to be dredged, but gave to the bidder the privilege of selecting another dumping ground which would be considered in making the award. Before such substituted grounds would be agreed to by the defendant it was necessary that the successful bidder furnish the defendant with evidence of written consent on the part of the owner of the substituted grounds. All expenses in connection with such substituted grounds were to be borne by the successful bidder.
Plaintiff submitted its bid May 9, 1930, at or about which time it was found that it was the low bidder. Its bid, however, stated that it proposed to dispose of the material at a place other than that named by the defendant. At the time the bid was submitted, plaintiff was engaged in a dredging
The contract provided that the work should be completed October 19, 1930. It was not completed until September 1, 1931. The defendant assessed liquidated damages at $20 a day for 317 days, such period being the number of calendar days from the date the contract should have been completed until the date the work was finished.
The principal objection made by plaintiff is that when the defendant accepted the substituted dumping grounds there was thereby a modification of the contract to the extent that plaintiff was not required to begin work under the contract until it finished its work with The Texas Company and until that company was ready to receive the dredged materials. We cannot agree. The contract made specific provision as to when the work should begin, and it also gave the bidder the privilege of either using the dumping grounds provided by the defendant or suggesting substituted grounds. Plaintiff stated in its bid that it proposed to use certain sub
Some suggestion is made that in any event liquidated damages should not be assessed for the period from December 15,1930, to April 1,1931, when the plaintiff was not required under article 3 of the specifications to carry on operations. That period, however, would only be excepted when the completion period specified in a contract extended beyond such
It follows that the petition must be dismissed. It is so ordered.