OPINION
Tri-Corp Management Inc. (“TriCorp”), an Ohio corporation, sought to construct a development of fourteen single-family condominiums on property it owned in Hubbard, Ohio. After the Hubbard City Engineer issued a stop work order that prevented Tri-Corp from completing its construction plans, Tri-Corp filed a § 1983 civil rights suit in federal court against the City of Hubbard and three city officials: George Praznik, the Mayor of Hubbard and a member of the Hubbard Planning and Zoning Commission (the “PZC”); William Colleta, the Hubbard City Service Director and a member of the PZC; and David Kelly, the current Hubbard City Engineer. In its two-count complaint, Tri-Corp claimed that by issuing a stop work order, the defendants violated TriCorp’s due process rights and unconstitutionally took Tri-Corp’s property. The defendants moved to dismiss the complaint, arguing that (i) the complaint raised only a regulatory takings claim and (ii) the regulatory takings claim was not ripe for federal court review. The district court granted both components of defendants’ motion and dismissed Tri-Corp’s complaint without prejudice. Tri-Corp appealed both issues. We AFFIRM the district court’s judgment in part, REVERSE in part, and REMAND for further proceedings consistent with this opinion.
I.
According to the allegations in the complaint, Tri-Corp sought to construct fourteen modular homes on its property at 752 Elmwood Drive in Hubbard, Ohio (the “Property”). In February 1997, the president of Tri-Corp discussed construction plans with William Mariotti, who was then the Hubbard City Engineer. Mariotti believed that Tri-Corp’s proposed construction of fourteen modular homes complied with the zoning requirements, but recommended that the PZC approve the plans. Based on Mariotti’s advice, Tri-Corp submitted preliminary plans to the PZC, which the PZC unanimously approved in January 1998. With the PZC’s approval in place, Tri-Corp received a zoning permit and began construction.
Shortly after Tri-Corp commenced developing the Property, it encountered resistance from the Hubbard City Council. At its March 2, 1998 meeting, members of
Tri-Corp never received permission to build the remaining thirteen units. Although it resubmitted the same development plans that the PZC previously approved, the PZC voted against a motion to re-approve those plans. The PZC also voted down a motion to reject Tri-Corp’s plans. Thus, the plans were technically neither approved nor rejected by the PZC. With the PZC paralyzed on the issue and with the stop work order in place, TriCorp sued defendants in federal court under 42 U.S.C. § 1983.
Tri-Corp’s .complaint contained two counts. Count I claimed that through the issuance of the stop work orders, defendants violated the due process clauses of the Fourteenth Amendment and Section 16 of the Ohio Constitution. In support of this claim, Tri-Corp alleged that defendants acted arbitrarily in issuing the stop work orders and that defendants engaged in a “confiscatory action” by stopping the previously permitted development. Count II claimed that the stop work orders unconstitutionally took property from TriCorp without providing just compensation as required by the Fifth Amendment and Section 19 of the Ohio Constitution.
In reply to Tri-Corp’s complaint, the defendants filed a motion to dismiss. Defendants first moved to merge the two counts into a single regulatory takings claim. Second, defendants moved to dismiss the regulatory takings claim on ripeness grounds because Tri-Corp did not exhaust state remedies. The district court granted both components of defendants’ motion and Tri-Corp appealed both aspects of the district court’s decision.
II.
Although not labeled as such, the defendants’ motion to dismiss before the trial court contains two distinct components: a Rule 12(b)(6) motion to dismiss all claims except for a regulatory takings claim and a Rule 12(b)(1) motion to dismiss the regulatory takings claim for lack of subject matter jurisdiction due to its lack of ripeness.
A. Standard of Review
A district court’s dismissal of a civil rights claim for failure to state a claim for relief under Rule 12(b)(6) is a question of law that we review de novo. See Mertik v. Blalock,
With respect to a ripeness challenge, federal courts should not consider questions that do not amount to a case or controversy. See Dixie Fuel Co. v. Comm’r of Soc. Sec.,
Because defendants do not dispute the facts underlying the ripeness of Tri-Corp’s complaint, they present a facial challenge, as opposed to a factual challenge, to federal subject matter jurisdiction. See generally RMI Titanium Co. v. Westinghouse Elec. Corp.,
B. The Dismissal of All of Tri-Corp’s Claims Except the Regulatory Takings Claim
The district court read Tri-Corp’s two-count complaint as alleging only a single regulatory takings claim. On appeal, TriCorp relies on Pearson v. City of Grand Blanc,
1. Procedural Due Process
Tri-Corp does not set forth a procedural due process claim. In this Circuit, a plaintiff states a § 1983 procedural due process claim through one of two methods: “(1) [by] demonstrating that he is deprived of property as a result of established state procedure that itself violates due process rights; or (2) by proving that the defendants deprived him of property pursuant to a ‘random and unauthorized act’ and that available state remedies would not adequately compensate for the loss.” Macene v. MJW, Inc.,
Tri-Corp never alleges that it was deprived of property without either of the fundamental elements of procedural due process: notice or an opportunity to be heard. See Yellow Freight Sys., Inc. v. Martin,
Tri-Corp’s complaint also fails to state a claim for relief under the second method. Tri-Corp’s complaint alleges that the May 15 stop work order “was issued in direct contradiction to the prior city zoning and planning and engineers [sic] approval.” Even if this statement is interpreted as an allegation that the stop work order was unauthorized, the complaint never hints, let alone alleges, that the stop work order was a random event or that the post-deprivation remedies that the state provides would not adequately compensate Tri-Corp. See Parrott v. Taylor,
2. Equal Protection
Tri-Corp’s complaint also does not state an equal protection claim. (This conclusion should not be too shocking because nowhere in Tri-Corp’s complaint does it mention the phrase “equal protection”). To state an equal protection claim, a party must claim that the government treated similarly situated persons differently. See Silver v. Franklin Township, Bd. of Zoning Appeals,
3. Due Process Takings
Tri-Corp also does not allege a due process takings claim. In recognizing a claim for a due process taking, the Pearson opinion relied heavily on the discussion of different classes of federal zoning claims laid out in Eide v. Sarasota County,
4. Substantive Due Process
Tri-Corp’s complaint does set forth a substantive due process claim. We have recognized that “citizens have a substantive due process right not to be subjected to arbitrary or irrational zoning decisions.” Pearson,
Tri-Corp sufficiently alleged that it had a constitutionally protected property inter
Tri-Corp also complies with the “arbitrary and capricious” requirement of a substantive due process claim. The complaint asserts that the defendants’ actions were arbitrary and unreasonable. Based on that allegation and a liberal reading of the complaint, Tri-Corp sufficiently pleaded the arbitrary and capricious requirement for a substantive due process violation.
In sum, the district court’s conclusion that only “a single regulatory takings claim” remained of Tri-Corp’s complaint was correct to the extent that it dismissed the procedural due process, equal protection, and due process takings claims. But, the district court erred to the extent that it dismissed Tri-Corp’s substantive due process claim.
C. The Ripeness of Tri-Corp’s Remaining Claims
The district court considered the ripeness of only the regulatory takings claim. Because it is now clear that the complaint states two causes of action—a substantive due process claim as well as a just compensation regulatory takings claim—it is appropriate to consider the ripeness of both claims. We conclude that (1) TriCorp’s substantive due process claim is ripe for review and (2) the district court correctly concluded that Tri-Corp’s regulatory takings claim was unripe.
1. Ripeness of the Substantive Due Process Claim
Tri-Corp’s substantive due process claim is ripe for review because it presents an “existing, substantial controversy, not hypothetical questions or possibilities.” Dixie Fuel Co.,
2. Ripeness of the Just Compensation Regulatory Takings Clause Claim
Tri-Corp’s regulatory takings claim is not ripe for federal court review. The Takings Clause does not prohibit the government from taking private property; it prohibits the government from taking private property without just compensation. Williamson,
Because Ohio does not have an inverse condemnation or other formalized procedure for seeking just compensation for a taking, this Circuit has focused on whether Ohio’s writ of mandamus provides a “reasonable, certain, and adequate provision for obtaining compensation.” Although we have twice addressed that question, our holdings appear to be at odds with one another. We first evaluated whether Ohio’s writ of mandamus provided a “reasonable, certain, and adequate provision for obtaining compensation” in Silver v. Franklin Township, Board of Zoning Appeals, which was a regulatory takings case.
We hold that Ohio affords no “reasonable, certain and adequate provision for obtaining compensation” after private property is taken by public authorities without following the mandatory pretaking appropriation procedures set out in Ohio Rev.Code §§ 163.01-163.62. Ohio’s decisional law in this area is anything but certain. Ohio has no statutory provision for relief under the circumstances of this case. The fact that the State’s courts recognize an action in mandamus, where the State has no mandated procedures governing inverse condemnation, cannot be equated to a “reasonable, certain and adequate provision for obtaining compensation,” after the property has been physically taken in violation of the appropriations statutes. An action for the extraordinary writ of mandamus is, at best, a procedure which must be invoked in the absence of any statutory framework in an attempt to obtain wholly equitable relief for an injury already inflicted.
Although the Silver and Kruse holdings appear to be contradictory, they can be reconciled by limiting each to its facts. Under that approach, Silver’s pronouncement that a writ of mandamus is a “reasonable, certain, and adequate provision for obtaining compensation” applies to regulatory takings claims, and Kruse’s pronouncement that a writ of mandamus does not provide such protection applies to physical takings claims.
Complicating matters further, we note that a recent Ohio Supreme Court decision may shed additional light on whether the writ of mandamus in Ohio is a “reasonable, certain, and adequate provision for obtaining compensation” for an unconstitutional taking. In State ex rel. Elsass v. Shelby County Board of Commissioners, the Ohio Supreme Court explained that “[mjandamus is the appropriate action to compel public authorities to institute appropriation proceedings where an involuntary taking of private property is alleged.”
Rather, we decide this issue on a deficiency in Tri-Corp’s complaint. Where a property holder asserting a regulatory takings claim “has not resorted to state procedures for obtaining just compensation and has made no claim that these procedures are inadequate, his takings claim is not ripe for federal court review.” Silver,
III.
Through only a passing, casual reference in the briefs and a short mention at oral argument, counsel noted that prior to this lawsuit, Tri-Corp had filed a mandamus action in state court on July 6, 1999. Instead of curing Tri-Corp’s pleading deficiency (for the unripeness in Tri-Corp’s regulatory takings claim), this fact alerted us to a potentially more serious issue not addressed by the parties—whether principles of Younger abstention apply to either stay or dismiss this case. See Younger v. Harris,
IV.
With respect to the Rule 12(b)(6) portion of defendants’ motion, the district court correctly dismissed the procedural due process, equal protection, and due process takings claims. However, a valid substantive due process claim remained amidst those several insufficiently pleaded claims. With respect to the Rule 12(b)(1) ripeness facial subject matter challenge, the district court correctly dismissed Tri-Corp’s just compensation regulatory takings claim, but the substantive due process claim is ripe for review. For those reasons, we AFFIRM the district court judgment in part, REVERSE in part, and REMAND for further proceedings consistent with this opinion.
