Lead Opinion
Appellant Trelltex, Inc. d/b/a Texcel (Texcel) appeals from a judgment awarding appellee and cross-appellant Intecx, L.L.C. d/b/a Rocky Mountain Industrial Technologies (RMIT) $21,589.88 in damages for underpaid commissions occurring between October 1, 2001 and May 1,- 2006, $43,179.76 in treble damages under Colorado law, and' $76,235.10 in reasonable attorney’s fees and court costs. On appeal, Texcel argues that the trial court erred in awarding damages for underpaid commissions between October 1, 2001 and May 1, 2006 because any such damages are barred by the four-year statute of limitations applicable to breach of contract claims. We conclude that the damages awarded- by the trial court are barred by the statute of limitations and therefore reverse and render judgment that RMIT take nothing on these claims. Because we do so, we also reverse the trial court’s award of treble damages under Colorado law and the, trial court’s award of attorney’s fees and court costs.
, In a single issue on cross-appeal, RMIT contends that the trial court erred in concluding that it waived its right to damages from underpaid commissions occurring after May 1, 2006. We hold RMIT waived its right to any damages not barred by the statute of limitations. We therefore affirm the portion of the.trial court’s judgment denying any relief not granted.
. Background
In August 2001, Texcel entered into a Sales Representative Agreement with RMIT. In pertinent part, the agreement provided: “The commission rate is 9% for all sales, existing and new sales.” The agreement went on to state:
NOTE: This'commission' structure has been designed for the. benefit of both parties. It -is understood that, this rate will be evaluated after some time and possibly adjusted as necessary to allow a greater territory expansion for RMIT as warranted and or a different commission rate. , ,
[[Image here]]
From time to time a specific order may suggest a mutually agreed upon commission rate. This will be discussed and agreed upon at the tim.e of quotation.
In a section entitled Revisions, the agreement stated: “Any revisions to this agreement must be done in writing and accepted by both parties.”
In October 2001, Texcel lowered • the commission rate to five percent. The trial court found that the reduction was without RMIT’s knowledge or agreement.- The parties operated under the agreement until Texcel terminated the agreement. The termination went into effect on February 29, 2012. The parties do not dispute that from October 1, 2001 until the agreement was terminated, Texcel paid RMIT a five-percent commission on all sales.
On September 10, 2012, RMIT filed suit against Texcel to collect the underpaid commissions. RMIT asserted that Texcel breached the contract by paying commissions at five percent between January 2008 and February 2012. when the contract called for nine percent.- RMIT also asserted a, violation of a Colorado statute which allowed it collect treble damages on the underpaid commissions.
In its answer, Texcel asserted numerous affirmative . defenses, including . that RMIT’s claims had been waived and were barred by the statute of limitations. Tex-cel also filed a counterclaim seeking a declaratory judgment that the agreement did not require it to obtain written approval from RMIT to change the commission rate
Following a bench trial, the trial court rendered judgment in favor of RMIT. The court awarded $21,589.88 for underpaid commissions from October 1, 2001 to May 1, 2006 and $43,179.76 in additional damages under the Colorado statute. It also awarded RMIT $76,235.10 in reasonable attorneys’ fees and court costs. Subsequently, the trial court signed findings of fact and conclusions of law. Texcel filed a notice of appeal, and RMIT filed a notice of cross-appeal.
Analysis
I. The damages awarded by the trial court for commissions underpaid from October 1, 2001 to May 1, 2006 are barfed by limitations.
In its first issue, Texcel argues that the trial court erred in awarding damages for alleged underpayments occurring between October 1, 2001 and May 1, 2006 because any such damages are barred by the statute of limitations. We begin our analysis by considering whether Texcel preserved this issue for our review.
Limitations is an affirmative defense that must be specifically pleaded and proved. Intermedics, Inc. v. Grady,
' In this case, Texcel’s pleadings raised the statute of limitations repeatedly as an affirmative defense. Texcel also requested findings of fact and conclusions óf law, which the trial court issued.' In firiding of fact 6, the trial court concluded Texcel underpaid commissions from October 2001 until February 2012. In finding of fact nine, the trial court included a chart in which it calculated the amount of commissions that Texcel owed but did not- pay RMIT in each year from 2001 until 2012. In conclusion of law three, the trial 'cdurt concluded that these - underpayments breached the parties’ contract. Because the trial court concluded that RMIT had waived its right to receive underpaid commissions owed after May 1, 2006, it awarded RMIT damages for the underpaid commissions only from October 1, 2001 to May 1, 2006. In conclusion of law eleven, the trial court concluded that Texcel “failed to prove any of its alleged affirmative defenses other than waiver.” No motion for new trial, objection to the trial court’s findings of fact or conclusions of law, or request for additional or amended findings or conclusions appear in our record, and the parties do not argue that any was made.
The trial court’s findings establish elements of Texcel’s limitations defense by charting when the underpayments .occurred. No party has contended that any other disputed facts needed to be resolved in order to determine whether RMIT’s claims for breach of contract regarding those underpayments were barred by limitations. For these reasons, no request for additional findings was necessary to pre
Having concluded that Texcel preserved the limitations issue for our review, we next analyze whether, in light of the trial court’s unchallenged findings about when the underpayments occurred, the trial court’s -legal conclusion that Tex-cel failed to prove its defense is erroneous. The statute of limitations for breach-of-contract actions is four years from the date of accrual. Tex. Civ. Prac. & Rem. Code Ann. § 16.051 (West 2015). An action for breach of contract accrues immediately upon breach. Barker v. Eckman,
If the parties’ agreement contemplates a continuing contract for performance, the limitations period usually does not commence until the contract is fully performed. Intermedics, Inc. v. Grady,
Texcel contends that because RMIT filed suit on September 10, 2012, it cannot recover any purported underpayments that occurred before September 10, 2Q08.
RMIT argues that the agreement between the parties was a continuing’ contract and thus the limitations period did not commence until Texcel terminated the agreement in 2012. This argument misses the mark for the reasons explained in Davis Apparel v. Gale-Sobel, a Division of Angelica Corp.,
On appeal, Davis Apparel argued that the agreement was a continuing contract that was not breached until it expired in May 1997. Id. at 18. The Eastland Court of Appeals took a different view, concluding that the evidence supported the jury’s finding that the first breach occurred in March 1994. Id. The court of appeals therefore affirmed the trial court’s take-nothing judgment with regard to claims arising more than four years before suit was filed (before December 1, 1996), but reversed the judgment for claims arising after that date and remanded those claims for trial. Id. at 19. The court of appeals explained:
[Ijrrespective of the jury’s determination of when the earliest breach of the contract occurred, limitations should notbar claims for damages arising after December . 1, 1996. The evidence in the record demonstrates that the parties treated their agreement as an installment contract whereby Gale-Sobel made ; monthly payments - of commissions to .Davis Apparel. As,we noted in Slusser, a separate cause of action arises for each missed payment under an. installment contract. .
Id.
As in Davis Apparel, the agreement in this case féqüired 'periodic commission payments, and recovery for any underpayments occurring more than four years before RMIT filed suit is therefore barred by the statute of limitations. During oral argument, RMIT asserted that the payments Texcel was required to make under the agreement were not fixed because they were based on commissions that varied from month to month. Although the payments varied in amount, they were fixed in that the agreement required them to be made using a specified formula on particular dates. The commission payments also varied in amount in Davis Apparel, yet the court concluded that payments missed outside the four-year limitations period were barred.
For these reasons, we sustain Texcel’s first issue. We therefore reverse the trial court’s award of $21,589.88 iii damages to RMIT for any underpaid commissions Occurring between October 1, 2001 and May 1, 2006.- As a result, we also reverse the trial court’s award of $43,179.76 in additional damages for underpaid commissions under Colorado law. We likewise reverse the trial’s award of $76,235.10 in reasonable attorneys’ fees and court costs because RMIT is no longer a prevailing party on its breach of contract claim and has not recovered damages. See Ashford Partners, Ltd. v. ECO Res., Inc.,
In its sole issue on cross-appeal, RMIT argues “there is no evidence or insufficient evidence” that it waived by implication its right to receive any commissions not paid between May 1, 2006 and February 29, 2012. RMIT asks us to reverse the trial court’s conclusion of law that Texcel proved waiver and to render judgment in its favor for $128,153.27 in commissions underpaid during that period. RMIT also asks us to reverse the trial court’s factual findings that RMIT received monthly statements from Texcel after May 1, 2006 from which it could have calculated that it was being paid only five-percent commissions, and that RMIT never complained about the underpaid commissions before the agreement was terminated. As explained below, however, RMIT’s brief does not demonstrate that the evidence is insufficient to support these findings. Instead, RMIT largely argues that these findings are insufficient to support the legal conclusion that an implied waiver occurred. We focus our analysis on that question.
The sales agreement calls'for commissions to be paid on the last day of the month following that in which the commissions were earned. Because RMIT filed suit on September 10, 2012, any underpaid commissions due from May 1, 2006 through August 31, 2008 are barred.by the' four-year statute of limitations, as discussed above.
A. Standard of review
When, as in this case, specific findings of fact and conclusions of law are filed and a reporter’s record is before the appellate court, the findings, will be sustained if there is evidence to support them, and the appellate court will review the legal conclusions drawn.from the facts found to determine their correctness. CD. Holdings, Inc. v. H.D.H. Land & Timber, L.P., 407 S.W3d 856, 859 (Tex.App.-Tyler 2013, no pet.). Findings of fact have the same force and dignity as a jury’s verdict and are reviewable under the same standards of legal and factual sufficiency. Foley v. Capital One Bank, N.A.,
Texcel bore the burden to prove its affirmative defense of waiver. Accordingly, we review RMIT’s legal sufficiency challenge under a “no evidence” standard. City of Keller v. Wilson,
We review a trial court’s conclusions of law de novo. State v. Heal,
In reviewing the factual sufficiency of the evidence, we must examine the entire record, considering both the evidence in favor of, and contrary to, the challenged findings. See Maritime Overseas Corp. v. Ellis,
B. Applicable law
Waiver may be asserted as an affirmative defense against a party who intentionally relinquishes a known right or engages in intentional conduct inconsistent with claiming that right. Singleton v. Elliott, 14-13-00040-CV,
Waiver is largely a matter of intent, and for implied waiver to be found through a party’s conduct, intent must be clearly demonstrated by the surrounding facts and circumstances. In re Gen. Elec. Capital Corp.,
C. Implied waiver
In its fourth conclusion of law, the trial court stated that “Texeel has proven RMIT waived its rights to receive the underpaid commissions that were owed to RMIT by Texeel after May 1, 2006.” RMIT asserts that the evidence and findings show “mere” acceptance of payments and possibly a lack of care on its part, which are insufficient to support a legal conclusion of implied waiver. RMIT asserts there is “no evidence or insufficient evidence” of its intent to yield its right to payment of nine-percent commissions. Thus, according to RMIT, we must reverse the trial court’s conclusion that Texeel proved waiver.
We conclude that the findings and supporting evidence provide a sufficient basis for the trial court’s conclusion that RMIT waived its right to collect any underpaid commissions after May 1, 2006. The evidence at trial demonstrated, and the trial court found, that RMIT received commission payments at a rate of five percent beginning in October 2001. The trial court also found that after May 1, 2006, RMIT received monthly statements showing the amount of monthly sales and the amount of commissions paid. From this information, the trial court found, RMIT could have calculated it was being paid only five-percent commissions, though it never made those calculations.
As previously explained, silencé or inaction for so long a period as to show an intention to yield the known right is sufficient to prove waiver. See Tenneco,
Similarly, RMIT’s conduct in this ease together with 'its silence or inaction — accepting commission payments calculated at a rate of five percent for nearly six years without complaint — was intentional conduct inconsistent with claiming a known right to receive commissions at a rate of nine percent. We therefore hold that the evidence summarized above is legally and factually sufficient to" support the ’ trial court’s findings and its conclusion of waiver. See Shaver v. Schuster,
RMIT argues that Texeel was required to prove that RMIT actually (1) calculatéd the percentage of the commissions it was paid, (2) knew that the legal effect of those payments was to breach the contract, and (3) intended to accept the non-compliant payments. RMIT is incorrect. Waiver requires either actual intent to relinquish a right or intentional conduct inconsistent with claiming the right— not both.
In this case, however, the key to establishing waiver identified in Tenneco and Clear Lake is. present. . .The trial court found that after May 1, 2006, RMIT received monthly ‘ statements from Texcel showing both the amount of sales revenue and the amount of commissions paid. Each month’s commissions amounted to five percent of the sales revenue, and there is no dispute that RMIT knew the contract entitled it to a commission rate of nine percent for all sales. RMIT thus had actual knowledge of the facts pertinent to the breach — that is, of material facts sufficient to support a legal conclusion that the contract had been breached
To buttress its argument that the trial court erred in concluding Texcel proved waiver, RMIT points to the trial court’s findings of fact sixteen through nineteen, which state:
16. RMIT never expressly relinquished its right to be paid the 9% commission called for in the contract.
17. RMIT never approved the unilateral reduction of its commission from 9% to 5% under the contract.
18. RMIT never intended to make TEXCEL’s unilateral reduction of the commission from 9% to 5% valid.
19. RMIT never agreed to modify or revise the commission rate under its contract with TEXCEL from 9% to 5%. In considering these findings, we are
bound to assume the validity of the trial court’s judgment. Leonard v. Eskew,
Conclusion
Having held that the damages awarded by the trial court are barred by the statute of limitations, we reverse the trial court’s judgment awarding $21,589.88 for breach of contract by underpaying commissions between October 1, 2001 and May 1, 2006, together with the related awards of additional damages under. Colorado law, attorney’s fees, and court costs. We render judgment that RMIT take nothing on these claims. In addition, because Texcel proved RMIT waived any right to damages not barred by the four-year limitations period, we affirm the portion of the judgment denying all other requested relief.
(Frost, C.J., dissenting)
Notes
. But see Dunn v. Dunn,
. RMIT's fourth amended petition alleges that it was underpaid $110,899,31 from 2008 to 2012. In the section titled Damages, RMIT asserts only that it is entitled to this amount in damages as a result of Texcel’s breach. RMIT’s petition does not discuss the damages it suffered from any breaches occurring between October 1, 2001 and May 1, 2006. Texcel does not argue on appeal, however, that the trial court erred by awarding relief not requested in RMIT’s petition. We therefore do not address that issue.
. RMIT also contends that Davis Apparel is distinguishable because the parties in that case did not sign a contract specifying the commission percentage, and after a dispute arose during the first three months of the agreement, Davis Apparel made several demands for the underpaid commissions.
. Texcel contends in its second issue that the trial court erred by finding that Texcel breached the agreement and by denying its counterclaim for declaratory relief. Given our holding above that limitations bars the damages awarded to RMIT for any breach of the agreement by underpaying commissions before May 1, 2006, as well as our holding below that RMIT waived its claim to underpaid commissions not barred by limitations, we need not address Texcel’s second issue. In its third issue, Texcel asserts that the trial court erred in awarding additional damages under Colorado law. In its fourth issue, Tex-cel contends the trial court erred by awarding attorneys’ fees because the claims for the damages awarded by the trial court were never presented. Having reversed the trial
. Any sales commissions earned during August 2008 were not due until September 30, 2008. These sales commissions were therefore not barred by - the four-year statute of limitations.
. Given’ the payment schedule in the sales agreement, any commissions earned on sales cluring February 2012 were not due until March 31, 2012. In finding of fact 6, the trial court found Texcel underpaid commissions until the contract was termináted “effective February 29, 2012.” The parties have not addressed this one-month discrepancy in their briefs. In any event, we need not resolve the matter because we conclude RMIT waived its right to any damages stemming from the alleged underpaid commissions that occurred during the four-year limitations period.
. Our dissenting colleague focuses on the finding that RMIT never made the calculations, arguing that this finding is supported by the evidence and forecloses implied waiver. As we explain below, however, actually mak-tag the calculations is not legally required for implied waiver. Accordingly, we need not set aside this finding in order to affirm the trial court’s waiver holding.
. To the extent our dissenting colleague suggests that implied waiver requires evidence that a party had actual knowledge of a breach of contract, that position is contrary to Texas Supreme Court precedent in two ways. ' First, the "actual knowledge” element of' waiver analysis focuses on "an- existing right," Ulico Cas. Co.,
. See also Slay v. Burnett Trust,
. See In re Longoria,
. See Ford v. Culbertson,
. We recognize, of course, that Texcel did not use the words "five percent” in the monthly statements. But RMIT does not contend that the use of those words was necessary to show a breach or, put another way, that the facts contained" in the statements do not constitute- a breach.- To the contrary, the trial court found that Texcel did breach the contract by making the commission payments as shown on the statements.
. These facts also distinguish the present case from Davis-Lynch, Inc. v. Asgard Technologies, LLC,
. For this same reason, our dissenting colleague’s reliance on Shannon v. Memorial Drive Presbyterian Church U.S. is misplaced.
Dissenting Opinion
dissenting.
“Should have known” is not the standard for common-law waiver under Texas law. Yet, today the court holds that a party waives its right to recover if the party should, have known that its failure to act was inconsistent with its known rights. Because today’s holding goes against our court’s precedents, I respectfully dissent.
Insufficiency of the Evidence to Support Waiver
Appellee Intecx, L.L.C. d/b/a/ Rocky Mountain Industrial Technologies (“RMIT”) argues on cross-appeal that the record contains insufficient evidence that it waived its right to receive commissions not paid between May 1, 2006 and February 29, 2012. The majority holds the statute of limitations bars recovery of some of these commissions and that waiver bars recovery of the rest.
The statute of limitations bars all of RMIT’s claims to funds owed before September 10, 2008, as the majority concludes. But, there is no waiver, so waiver does not bar recovery of the funds owed between September 2008 and February 2012. The majority errs in holding otherwise.
The majority notes that waiver may be asserted as an affirmative defense against a party who intentionally relinquishes a known right or engages in intentional conduct inconsistent with claiming that right.
Actual knowledge is a prerequisite to intentional conduct inconsistent with claiming a known right.
Citing Tenneco Inc. v. Enterprise Products Company,
In Clear Lake Center, L.P. v. Garden Ridge, L.P., our court explained that the Tenneco Inc. holding is based on the party’s actual knowledge of the facts constituting the breach.
The majority misreads Clear Lake Center as holding that a party intentionally acts inconsistently with claiming a known right if the party knew, facts pertinent to its right of recovery but did not act' upon its right to recover.
The majority points out that a party is presumed to know the contents of any contract the party signs and the contract’s legal effects. The statement is true but the majority misapplies it. As properly applied to this case,, the presumption means that if RMIT knew Texcel was not paying the proper amount of commission— nine percent of the sales revenue — RMIT presumptively would know that this failure by Texcel constituted a breach of the contract. The presumption does not mean that the court should presume RMIT knew Texcel was not paying the proper amount because RMIT knew some facts pertinent to the breach. As the majority acknowledges, the question of whether RMIT knew Texcel was not paying the proper amount is a question of fact.
In Clear Lake Center, the party with’ the known right of recovery (Garden Ridge) took an action that was inconsistent with claiming that right.
Lack of awareness of any facts pertinent to a breach is sufficient, but not necessary, to meet the standard Clear Lake Center articulates.
Today’s holding is at odds with Clear Lake Center. Though the majority purports to follow that precedent, the majority opinion clashes with Clear Lake Center’s interpretation of Tenneeo Inc. on the central issue. : Rather than follow that, interpretation, as other panels have done,
The trial court found RMIT lacked actual knowledge.
The majority characterizes the dissenting opinion as stating that “implied waiver requires direct evidence that a party had actual knowledge of a breach of contract.”
The trial court found that “RMIT could have calculated that it was only being paid 5%,” but that “RMIT never made those calculations.” The evidence is sufficient to support the trial court’s finding that RMIT never calculated the percentage of commissions it was receiving. In making this finding, the trial court found RMIT did not have actual knowledge of the facts constituting the breach. The majority is not the fact finder. This court should give deference to the trial court’s express finding
Although the majority criticizes reliance on the trial court’s findings, the majority does not set aside the trial court’s finding that RMIT did not have actual knowledge that it was being underpaid. Absent actual knowledge, RMIT’s inaction was not intentional conduct inconsistent with its known right to recover the full amount of commissions owed under the contract, even if RMIT’s silence and inaction could be considered conduct inconsistent with its known right of recovery.
Relying on the trial court’s findings that RMIT could have discovered that its conduct was inconsistent with its known right of recovery, the majority skirts the requirement that for a party to act intentionally in a way that is inconsistent with the party’s rights, the party must have actual knowledge of the facts constituting the breach. Just as Garden Ridge in Clear Lake Center lacked actual knowledge that the fee it paid was improper,
Conclusion
RMIT did not know its inaction was inconsistent with its right to recover the full amount of commissions owed under the contract, so RMIT’s inaction does not operate as a waiver of its right to pursue recovery. Neither the record nor this court’s binding precedent supports the majority’s waiver analysis.
. Singleton v. Elliott, 14-13-00040-CV,
. Ulico Cas. Co. v. Allied Pilots Ass’n,
. See
. See ante at 15.
. See Clear Lake Ctr., L.P. v. Garden Ridge, L.P.,
. See id. at 542.
. See id.
. Id-, at 543.
. See id. at 542-43.
. Id.
. Id. at 542-43.
. See ante at 15-16.
. See Clear Lake Ctr.,
. Id. at 542-43. See also Shannon v. Memorial Drive Presbyterian Church U.S.,
. See ante at 13-14.
. See Clear Lake Ctr.,
. Id.
. Id. at 543. The court was not referring to a lack of knowledge by Garden Ridge that it had a right to sue for breach of contract. Id.
. See id.
. See id.
. See id. at 542.
. At one point, the majority suggests that the "facts pertinent to the breach” equate to the "material facts sufficient to support a legal conclusion that the contract had been breached." See ante at .18. The problems inherent in using actual knowledge of "facts pertinent to the breach”, as the legal standard apply with equal force vis a vis to the legal standard of actual knowledge of "material facts sufficient to support a legal conclusion that the contract had been breached." Although the majority states RMIT knew material facts that would have enabled it to learn of the facts constituting the breach, the trial court specifically found that RMIT did not know the facts constituting the breach. The majority does not suggest RMIT knew the facts constituting the breach. "Should have known” is not the standard, but that is the standard the majority applies.
. To the extent the majority relies upon Slay v. Burnett Trust as authority for the proposition that a party waives its right to recovery if it knows "facts pertinent to the breach,” Slay did not involve common-law waiver. See
. See Shannon, 476 S,W.3d at 627; Davis-Lynch, Inc., 47-
. See Chase Home Fin., L.L.C. v. Cal Western Reconveyance Corp.,
. See id.
. See ante at 15 n. 7.
. See ante at 15 n.7.
. Nothing in this dissent suggests that implied waiver requires direct evidence. And, nothing in this dissent suggests that the trial court’s findings of fact are not supported by sufficient evidence. The dissent does not conflict with Ulico Cas. Co.,
. See id.
. See Clear Lake Ctr.,
. See ante at 14-17.
. See Shannon,
. See Shannon,
