37 Pa. Commw. 20 | Pa. Commw. Ct. | 1978
Opinion by
On January 15, 1975, Rexnord, Inc. (Rexnord), a supplier of materials for use in the construction of a sewage treatment plant for the Mid-Mon Valley Water Pollution Control Authority, filed this action in assumpsit against Travelers Indemnity Company (Travelers), surety on the labor and materialmen’s payment bond. The case was consolidated for trial with an earlier action brought by. Rexnord against N. Victoria, Inc. (Victoria), the contractor on the job and the principal on Travelers’ bond. The case, as
Travelers’ principal contention is that the action against it was not timely brought and should, therefore, have been barred. In order to assess the validity of this argument, a chronological recitation of the facts is necessary.
The labor and material payment bond was issued by Travelers on January 28, 1972. Included in the terms of that bond is the provision:
[T]hat no such suit shall be commenced pri- or to ninety (90) days from the date upon which said person, co-partnership, association or corporation furnished, supplied or performed the last of the material or labor for which the said claim is made, and every such suit shall be commenced not later than one (1) year from the date when the cause of action accrued.
On February 10, 1972, after preliminary negotiations had been concluded, Victoria ordered certain materials from Rexnord. As set forth in the purchase order, the terms of payment required ninety per cent of the purchase price due on delivery, with the remaining ten per cent due ninety days thereafter. Rexnord delivered the materials in May of 1973, but Victoria
It is Travelers’ position that the cause of action accrued no later than September 1, 1973, which was ninety days after Rexnord furnished the materials to Victoria, and that the bond provision requiring suit to be brought within one year from that date barred the present action. We do not agree.
The flaw in Travelers’ argument is that it overlooks the subsequent agreement entered into between
A surety’s consent to an extension of the time of payment may be given either before or after the extension is made. Central-Penn National Bank of Philadelphia v. Tinkler, 351 Pa. 123, 40 A.2d 389 (1945). The correspondence between Rexnord and Travelers clearly indicates that Travelers approved of, and in fact, encouraged, Rexnord’s dealing with Victoria and its attempt to make arrangements concerning the recovery of the monies due it.
Travelers would also have us decide that the action is barred by the statute of limitations set forth in Section 7 of the Public Works Contractors’ Bond Law of 1967, Act of December 20, 1967, P.L. 869, 8 P.S. §197.
Accordingly, we affirm.
Order
And Now, this 26th day of July, 1978, the order of the Court of Common Pleas of Westmoreland County, dated April 15, 1977, is hereby affirmed.
This case is not unlike Valley Forge Industries, Inc. v. Armand Construction, Inc., 248 Pa. Superior Ct. 53, 374 A.2d 1312 (1977). There, the Superior Court transferred the proceedings to this Court, holding that jurisdiction over the appeal properly lay with us. We note that Valley Forge has not yet been decided by our Court and is, in fact, scheduled for oral argument in September. However, for the sake of expediency and fairness to the litigants in this case, we will reach and decide the merits.
The lower court found that a tee-rail which had been ordered was subsequently cancelled and not delivered. Victoria’s officer was not aware of this cancellation when the agreement was entered into. The order of the lower court reflects an adjustment in the amount owing Rexnord due to the non-delivery of this item.
We note that each letter from Travelers to Kexnord contained an express reservation of rights. This reservation, however, conflicts with the other language encouraging an amicable resolution of the problem.
Rexnord, relying on Commonwealth v. Transamerican Insurance Co., 462 Pa. 268, 341 A.2d 74 (1975), argues that the correspondence between it and Travelers amounted to a waiver of the time limitation provision entirely. We disagree. The facts in Transamerioa are much stronger than in the present ease. There, the course of conduct between the parties clearly demonstrated that the terms of the policy were waived by the acts of the insurer. Here, we cannot say that the exchange of letters rose to that level. While it may be that mere correspondence may constitute a waiver in some situations, the contents of these letters do not so indicate.
It is provided therein, inter alia:
(b) No such action may be commenced after the expiration of one year from the day on which the last of the labor was performed or material was supplied for the payment of which such action is brought by the claimant.