h Travelers Casualty and Surety Company of America (Travelers) and Tycor Industries LLC (Tycor) appeal the circuit court’s order for Tycor to pay Cummins Mid-South LLC (Cummins) $59,115.14 plus costs, interest, and attorney’s fees on the grounds that (1) the language of the lien release was ambiguous, (2) Cummins did not waive its right to recover on the bond, and (3) Tycor was unjustly enriched. This appeal follows.
On appeal, Tycor asserts that the terms of the release were unambiguous, and that Cummins waived its right to payment under the bond by signing the release. Additionally, Tycor asserts that Cummins is not entitled to recover under the doctrine of unjust enrichment because the existence of a contract bars such recovery. We agree, and we reverse the circuit court’s order.
|⅞1. Facts
Tycor, a general contractor, bonded by Travelers, subcontracted with ARC Electrical (ARC) for installation and electrical work on the Armed Forces Reserve Center project (project). ARC purchased a generator from Cummins. ARC began to have problems performing, and Tycor fired ARC before the job was completed. On August 3, 2011, John Virden
Three more times in January 2012, the generator required repair, which Cummins provided. ■ The total bill for the three service calls was $6,794.64, which Tycor paid. However, for these repairs, Cummins prepared its own lien release, specifically noting that the generator itself had not been paid for. On March 28, 2012, Cummins submitted a notice of subcontractors claim against the contractor’s bond for the amount of the generator, transfer switch, and start-up materials. Travelers denied the claim based on the execution of the lien release. On July 2, 2012, Cummins filed a complaint against Tycor and Travelers, asking for payment for the generator, interest, and attorney’s fees. Tycor filed a motion to dismiss with its answer, which the circuit court denied.
II. The Circuit Court’s Order
On March 7, 2014, the circuit court entered an order finding that Cummins did not waive its bond claim on the grounds that the language of the first release was ambiguous and did not indicate it was payment for anything other than the service call. The circuit court found that the language was ambiguous, considering extrinsic evidence, and construed the |4terms of the lien release in favor of Cummins:
[Tjhere was nothing in the proof, circumstantial or otherwise, to indicate that Cummins knew that by accepting the check for $2,748.16 that it was releasing its right to be paid for the generator. The definition of waiver requires full knowledge of material facts and an action which is inconsistent with the right or intention to rely upon the right.
A waiver requires consideration.... There was nothing [in the lien release] to indicate that it [the check] was consideration for payment of the generator purchased by ARC.
The circuit court found that “Cummins provided the generator and was never paid for it” and hence, Tycor was unjustly enriched. Specifically, the circuit court found Tycor was unjustly enriched in the amount of $59,115.14 by its “retention of the generator at the work site ... for the project owner, and the failure of the bonding company to pay for it.”
The circuit court also found that Cum-mins could recover under the bond based on Tycor’s unjust enrichment:
The purpose of the bond under A.C.A. section 18-44-501, et seq. was to provide for unforeseen eventualities. Tycor was obligated to provide the generator under the overall set of contracts, and for Ty-cor to not pay for it is a windfall benefit to Tyeor[.]
The circuit court denied Tycor’s defensive claims of detrimental reliance, estop-pel, and payment on the ground that Tycor did not meet its burden to assert the defenses. In its final finding, the circuit court found that the bond should have covered the generator: “The purpose of the statute requiring a bond for public works projects is to provide for payment of subcontractors of materialmen in cases such as this.” The circuit court awarded Cummins $59,115.14 plus costs, 12% penalty, prejudgment and postjudgment interest, and attorney’s fees.
IJIL The Lien Release
The release at issue in this appeal is a type of contract between the
Our supreme court has set forth the function of the court when there is a question concerning the clarity of the terms of a contract:
[W]here there is a dispute as to the meaning of a contract term or provision, be it an insurance or other contract, the trial court must initially perform the role of gatekeeper, determining first whether the dispute may be resolved by looking solely to the contract or whether the parties rely on disputed extrinsic evidence to support their proposed interpretation. As Justice George Rose Smith explained, “[t]he construction and legal effect of written contracts are matters to be determined by the court, not by the jury, except when the meaning of the language depends upon disputed extrinsic evidence.” Thus, where the issue of ambiguity may be resolved by reviewing the language of the contract itself, it is the trial court’s duty to make such a determination as a | f,matter of law.
Elam,
After careful examination of the lien release written by Tycor and signed by Cummins, we hold that the trial court erred in finding its language ambiguous, and we reverse.
We cannot say that the language of the lien release is ambiguous, looking only on the face of the document. The release is entitled at the top of the document: “SUBCONTRACTOR/MATERIALMAN UNCONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT.” It contains the statements that the release “covers the full and final payment of the contract amount for labor, services and equipment, or material furnished on the job of Armed Forces Reserve Center.” The release clearly sets forth that the person who signs the document waives any bond right he or she may have: “[T]he undersigned hereby releases and waives any mechanics’ lien, stop notice, or bond right he/she/it has on the said job.” The language is clear that Cummins releases any bond right it may have against Tycor concerning the Armed Forces Reserve Center job. There is no ambiguity, and therefore no call to look beyond the plain language of the contract.
We hold that the circuit court erred in finding the language of the release ambiguous, and on this point, we reverse.
IV. Waiver and Unilateral Mistake
Waiver is the voluntary abandonment or surrender by a capable person of a right known by him to exist, with the intent that he shall forever be deprived of its benefits, and it, may occur when one,
A contractual stipulation can only be withdrawn on grounds for nullifying a contract, meaning fraud or misrepresentation. Bishop v. Bishop,
In Fitzwater v. Lambert and Barr, Inc.,
The evidence is undisputed that the plaintiffs read the release. It is beyond question that plaintiffs knew the character of the release and understood the consequences of executing it. The release is clear, plain, simple, and unambiguous in all respects. It may indeed be true that plaintiffs failed to appreciate the seriousness of the injury, but startlingly clear hindsight will not render the acts of one laboring under erroneous foresight void ab initio. That plaintiffs’ signing of the release was perhaps unwise, and in retrospect unfortunate, is not sufficient to avoid it.
Id. at 291 (internal citations omitted). The facts in the present case are analogous. The terms of the release are unambiguous, as discussed above. The document is signed by Whitehead, who holds a master’s of business administration from Kellogg University, and at the time of trial had been the CFO at Cummins Mid-South for fourteen years where he specialized in
Furthermore, Cummins put on no evidence that Tycor defrauded Cummins into .signing the release, and in its order the circuit court did not make any finding of fraud on Tycor’s part necessary to assert unilateral mistake as a defense. Instead, the circuit court erroneously relied upon its finding of ambiguity in the language of the release and construed the language of the release based on extrinsic evidence. The circuit court’s construction of the lien led to its erroneous finding that waiver did not occur.
The unambiguous language of the release informed Whitehead that the right to recover on the bond, a right known to him to exist, was waived upon signing, and unilateral mistake without a showing of fraud on the part of Tycor does not allow Cummins to rescind the release. Thus, we hold that the circuit court erred in finding that Cummins did not waive its right to recover on the bond, and on this point we reverse.
V. Unjust Enrichment
Tycor asserts on appeal that the circuit court erred in finding that Cum-mins was able to recover under the doctrine of unjust enrichment. We agree, and we reverse. In the present case, the issue of whether the doctrine of unjust enrichment applies is a question of law. Generally, the standard of review on appeal from a bench trial is whether the trial court’s findings were clearly erroneous or clearly against the preponderance of the evidence. Hall v. Bias,
Unjust enrichment is.an equitable doctrine. First Nat’l Bank of DeWitt v. Cruthis,
In Servewell Plumbing, LLC v. Summit Contractors, Inc.,
Reversed.
Notes
. John Virden is not related to Judge Bart F. Virden.
