Opinion for the Court by Circuit Judge ROGERS.
Various municipalities
I.
The court has recently summarized much of the pertinent background in Sacramento Municipal Utility District v. FERC,
According to the CAISO, the “most important objective” of its proposal was to “protect CAISO ratepayers from unjust and unreasonable prices that may result in
[[Image here]]
The IBAA Proposal focuses on SMUD and Turlock, two independent but interconnected “balancing authority areas,” see Sacramento Mun.,
The CAISO’s proposed solution in the IBAA Proposal was two-fold. It first combined SMUD and Turlock into a single IBAA for purposes of the full network model. And, second, to rectify concerns regarding market manipulation and to model the IBAA connection points more accurately, the IBAA Proposal used a “sin
The CAISO explained that the elements of its single hub, default pricing point proposal were justified by and “result[ed] directly from the limited type and amount of information the CAISO expects to receive from the IBAA [ejntities.” IBAA Proposal at 5. The Commission agreed, concluding that “by using a more accurate representation of the locations of external resources used to implement interchange transactions in the CAISO’s full network model the IBAA [Pjroposal will help to ensure that interchange transactions from the SMUD and Turlock balancing authority areas are appropriately valued for purposes of managing congestion on the CAISO-controlled grid, and reduce the likelihood of significant differences between scheduled flows and actual flows.” Order ¶ 5. Accordingly, the Commission found the CAISO tariff, as amended by the IBAA Proposal, was “just and reasonable” under the Federal Power Act (“FPA”), 16 U.S.C. § 824d, but conditioned its approval on the modification of the IBAA Proposal in several ways, including that the CAISO address potential over-collection for charges based upon losses of energy during transmission due to the modeling of parallel flows, specify in its tariff the information to be provided for establishing MEEAs, and treat such information as confidential. See Order ¶¶6 & n.6, 8. The CAISO satisfied the conditions in additional filings and the Commission denied rehearing, rejecting various challenges, some of which are renewed in the pending petitions. See Rehearing Order ¶ 1.
II.
Petitioners challenge the Commission’s jurisdiction to review and approve a tariff amendment governing the pricing of electricity in the CAISO market, and also contend that the Commission’s acceptance of the IBAA Proposal amending the CAISO tariff was neither a reasonable exercise of its discretion under the FPA nor supported by substantial evidence of record.
The court “review[s] [the Commission’s] orders under the arbitrary and capricious standard and uphold[s] [the Commission’s] factual findings if supported by substantial evidence.” Am. Gas Ass’n v. FERC,
A.
Jurisdiction. FPA Section 201(f) provides that “[n]o provision in ... subchapter [II regulating electric utility companies engaged in interstate commerce] shall apply to, or be deemed to include ... any political subdivision of a State ... or any agency, authority, or instrumentality of ... the foregoing ... unless such provision makes specific reference thereto.” 16 U.S.C. § 824(f). Section 205 requires the Commission to ensure that the rates and charges “made, demanded, or received by any public utility” are “just and reasonable.” Id. § 824d(a). Section 201(e), in turn, defines “public utility” to be “any person who owns or operates facilities subject to the jurisdiction of the Commission.” Id. § 824(e). The court has concluded that by these provisions “Congress has ... specifically exempted governmental entities from subchapter II of the FPA.” TANC,
Petitioners, joined by intervenor Municipals, contend that the Commission exceeded its jurisdiction in approving the IBAA Proposal because FPA Section 201(f) “unequivocally exempts” governmental entities from the Commission’s rate-setting authority under FPA Sections 205 and 206, id., and their voluntary participation in such markets does not give the Commission authority to regulate their rates, Bonneville Power Admin, v. FERC,
Although the jurisdictional line was more easily drawn when the electricity world was “neatly divided into spheres of retail versus wholesale sales, and local distribution versus transmission facilities,” the “unbundling” of services and the general restructuring of electricity markets in the last two decades has made line-drawing more complex. Transmission Access Policy Study Group v. FERC,
In Sacramento Municipal,
Far from compelling Imperial [Irrigation District] to become a participating transmission owner of California ISO, [the Commission] merely permitted the ISO to charge Imperial for the costs incurred by the ISO when Imperial conducts transactions that cause transmission losses on the ISO’s grid. The Commission’s proper exercise of its power to regulate California ISO’s rates was not transformed into a violation of its statutory jurisdiction by dint of its incidental effect on Imperial.
Id. The Commission was not charging Imperial to use its own facilities; rather, the charges stemmed solely from Imperial’s use of CAISO-controlled facilities and attendant services. Id. at 537. The court noted a similar distinction had been drawn in Michigan Public Power Agency v. FERC,
The same reasoning controls here. In denying rehearing, the Commission emphasized that “[t]he IBAA Proposal is ... limited, only applying to scheduled transactions that impact the CAISO-controlled grid.” Rehearing Order ¶ 21. And “since the IBAA Proposal only applies to scheduled transactions that impact the CAISOcontrolled grid, only a party that chooses to use the CAISO-controlled grid is affected.” Id. ¶ 23. In short, “the IBAA Pro
Contrary to petitioners’ position, neither the Ninth Circuit’s opinion in Bonneville nor this court’s opinion in TANC preclude the Commission from asserting jurisdiction over the IBAA Proposal. Bonneville simply holds that the Commission may not order a non-jurisdictional entity to issue a refund,
Petitioners and Municipals also miss the mark in faulting the Commission for justifying its assertion of jurisdiction on non-jurisdictional entities’ voluntary participation in the CAISO market. In denying rehearing the Commission was not suggesting that it was asserting jurisdiction by agreement; rather, the Commission was illustrating that governmental entities are affected by the IBAA Proposal only insofar as they choose to transact within the CAISO-controlled grid. See Rehearing Order ¶ 22. Thus, petitioners’ and Municipals’ reliance on Columbia Gas Transmission Corp. v. FERC,
Municipals fare no better in responding that the IBAA Proposal is not limited to the CAISO-controlled grid because it incorporates prices at Captain Jack outside of the grid and makes reference to modeling “external” resources. Although the CAISO’s full network model uses proxies and data from outside the CAISO-controlled grid, the IBAA Proposal sets rates only for transactions on the CAISO-controlled grid. Moreover, the Commission may properly “analyze and consider the rates of non-jurisdictional utilities to the extent that those rates affect jurisdictional transactions.” TANC,
B.
Existing Contracts. The Amended Owners Coordinated Operation Agreement (“Agreement”) between Pacific Gas and Electric Company (“PG & E”), participants in the California-Oregon Transmis
A variation of the two-step Chevron analysis frames the arbitrary and capricious review. See Entergy Servs., Inc. v. FERC,
Section 5 of the Agreement provides:
This Agreement governs the coordinated operation of the PACI and COTP. It is the intent of the Parties to maintain the System as coordinated facilities to benefit its Transfer Capability. Except as to the use of the Tesla ByPass provided under this Agreement and as necessary to perform curtailment sharing obligations under Section 11 of this Agreement, no Party provides or shall be required to provide any transmission or other electric service to another Party under this Agreement.
Section 8.4 provides, in pertinent part, that
[t]he System shall be operated as a coordinated three-line transmission system. No Party shall be charged any rate and PG & E shall not be charged any transmission loss for any power, which flows over the System or over the Tesla ByPass .... Except to the extent necessary for sharing Curtailments, no Party shall have a right under this Agreement to have any of its power delivered on or otherwise have the use of transmission facilities owned by another Party.
Petitioners contend that section 8.4 unambiguously precludes the CAISO from “charg[ing] any rate ... for any power, which flows over the System.” As they see it, section 8.4 “reflects the Parties’ intent to shield one another from charges that might otherwise be imposed as a result of their coordinated operations, even where the power flows through the CAI-SO-eontrolled grid.” Reply Br. 8. But section 8.4 must be read in conjunction with section 5, as they are both part of a single agreement. See Consol. Gas Transmission,
Seeking to avoid the effect of section 5, petitioners maintain that the Commission has erroneously presumed a conflict between the two sections. But the Commission simply read one section in light of the other. See Order ¶ 248. In addition, the Commission’s interpretation is consistent with the Agreement’s general purpose, see Consol. Gas Transmission,
Petitioners relatedly contend that the Commission’s adjustment of the IBAA Proposal to prevent potential overcollection of losses, see Order ¶¶ 106, 252, shows that the Commission is permitting losses to be charged for parallel flows in violation of the Agreement. The Commission directed the CAISO to remove these charges, however, in order to avoid having COTP customers that transact in the CAI-SO market pay the cost due to losses of energy during transmission reflected in the Captain Jack locational marginal price in addition to the same cost reflected in the existing COTP tariff. See Order ¶ 106. Such action has no relation to whether the parties to the Agreement may charge one another for parallel flows on the California-Oregon Intertie. The Commission acknowledged that section 8.4 of the Agreement “provides that parties cannot charge a rate for these [parallel] flows.” Order ¶ 252. But its decision to direct the CAI-SO “to revise the IBAA proposal to address any potential overcollection of losses,” id., does not indicate that a failure to remove these loss charges would have violated the Agreement. The Commission explained that “the IBAA proposal will not charge any rate for these flows over and
Because section 5 defines the scope of the Agreement to govern only the joint operation of the three power lines comprising the California-Oregon Intertie, and section 8.4 is properly read in light of section 5, the Commission reasonably concluded that the Agreement only prohibits the parties to the Agreement from charging each other for unscheduled use of another’s lines associated with parallel flows and does not reach the IBAA Proposal, which concerns the CAISO’s ability to set rates within its own market.
C.
Discrimination. FPA Section 205, in addition to requiring that all rates and charges be “just and reasonable,” provides:
No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.
16 U.S.C. § 824d(b). To this end, upon finding that a rate is “unjust, unreasonable, unduly discriminatory or preferential,” the Commission is required to “determine the just and reasonable rate, charge, classification, rule, regulation, practice, or contract to be thereafter observed and in force, and shall fix the same by order.” Id. § 824e(a). “A rate is not ‘unduly’ preferential or ‘unreasonably’ discriminatory if the utility can justify the disparate effect.” Ark. Elec. Energy Consumers v. FERC,
In filing a revision to a tariff, the public utility bears the ultimate burden of demonstrating that the rate is not unduly discriminatory. See Elec. Consumers,
On the merits, petitioners contend that combining SMUD and Turlock into an IBAA constituted unreasonable and undue discrimination, in violation of FPA Section 205, 16 U.S.C. § 824d. Rejecting this view, the Commission credited the CAI-SO’s identification of six factors distinguishing SMUD and Turlock from other balancing authority areas, finding that “unique circumstances” justified the consolidation for purposes of the CAISO’s market redesign. See Order ¶¶ 208-216; Rehearing Order ¶¶ 216-226. Petitioners now complain that the Commission failed to provide a reasoned response to evidence and objections advanced by parties, see NorAm,
In response to petitioners’ objection to placing weight on the number, rather than the size, of the connections between two parallel systems, the Commission noted that the proposed “IBAA does, in fact, have several large interconnection points, including Tracy,” making the SMUD-Turlock IBAA “highly interconnected with the CAISO with respect to the number, size, and distance between its interconnections with the CAISO-eontrolled grid.” Order ¶ 212; see also Rehearing Order ¶ 218. Additional statements defeat petitioners’ claim that the Commission did not conclude SMUD and Turlock connections were more significant than other areas. The Commission noted that the “sheer number of interconnections and the extent of the parallel flows combined with its imbedded position within the CAISO grid” make the SMUD-Turlock IBAA the “most highly integrated interface with the CAI-SO.” Order ¶ 212. The Commission also contrasted the IBAA’s twelve interconnection points with the next largest balancing authority area, the Los Angeles Department of Water and Power, which has only four points. See id. Moreover, with respect to the degree of impact on the CAI-SO system, the Commission found that unscheduled flow data for SMUD and Turlock distinguished these entities from neighboring balancing authority areas. See Rehearing Order ¶ 220. The Commission also responded to petitioners’ objection that the former integration of SMUD and Turlock with the CAISO was irrelevant, pointing out that this “detailed knowledge” helped inform the CAISO’s understanding of challenges that might arise. Order ¶ 214. In sum, petitioners fail to show that the Commission did not examine the relevant data or articulate a rational connection between the facts found and the choice made, bearing in mind that the court’s review is highly deferential. See Alcoa,
Petitioners persist, however, contending that the Commission failed to respond to comments raising the arbitrariness of “lumping” SMUD and Turlock together. This contention also fails. The Commission, citing evidence of two experts presented by the CAISO, explained that the high degree of integration between SMUD and Turlock justified the IBAA Proposal. See Order ¶ 210. On rehearing, the Commission pointed out that the CAISO had presented “compelling data that illustrates the significance of unscheduled flows between the SMUD and Turlock balancing authority areas and the CAISO-controlled grid.” Rehearing Order ¶ 220 (emphasis added). This data compared SMUD and Turlock with other neighboring balancing
Petitioners’ remaining arguments fare no better. First, contrary to their suggestion, the Commission did not unreasonably reject evidence relating to flow rates. Rather, the Commission discussed in detail the parties’ respective positions regarding the accuracy of the data and the difference between frequency, magnitude, and peak flow data. See Order ¶¶ 37-39. On rehearing the Commission noted that “SMUD’s assertion that we ignored evidence it provided suggesting that flow reversals were ‘grossly exaggerated’ is incorrect. The Commission considered all submitted evidence in the record in making determinations regarding the IBAA Proposal.” Rehearing Order ¶ 69. As the Commission points out, the fact that the CAISO’s experts and data were credited over petitioners’ is no reason to grant the petition because the court, acknowledging the Commission’s expertise, “defers to the Commission’s resolution of factual disputes between expert witnesses.” Elec. Consumers Res. Council v. FERC,
Second, while petitioners correctly point out that future approval of other IBAAs does not justify undue discrimination against SMUD and Turlock, and that the availability of MEEAs — an agreement between the CAISO and an IBAA entity to share information — does not cure discrimination these considerations are of no aid to them here. The Commission identified no other entities suitable for IBAA treatment at the time of the challenged orders, and thus the Commission cannot be said to be treating similarly situated entities differently. See Sacramento Mun.,
Third, petitioners incorrectly suggest that the Commission impermissibly relied on a “totality of circumstances” approach. Unlike in LeMoyne-Owen College v. NLRB,
Fourth, the Commission did not, as petitioners note, directly address some of the evidence regarding parallel flows or explain why certain experts’ testimony was unpersuasive. But the overall explanation the Commission provided sufficed because it provided reasonable responses to petitioners’ objections that were neither summary nor dismissive. See NorAm,
D.
Proxy Prices. The Commission accepted the IBAA Proposal to use default import and export proxy pricing points to model the IBAA. See Order ¶¶ 82-92; Rehearing Order ¶¶ 58-70. Imports into the CAISO, i.e., sales from the IBAA entities to the CAISO, are given a locational marginal price as if they originated at the Captain Jack substation in Oregon; exports from the CAISO, i.e., sales from the CAISO to the IBAA entities, are given a locational marginal price at a hypothetical “SMUD hub,” a composite point representing the average location of exports. See Order ¶ 64. As an alternative to these default locational marginal prices, the IBAA Proposal provided for MEEAs.
The Commission found this model and the underlying assumptions of the IBAA Proposal to be reasonable “given the available information on interchange transactions,” Order ¶ 82, and “the absence of additional information ... verifying an interchange transaction’s source or sink,” id. ¶ 83. It noted that the CAISO “has appropriately chosen to make an assumption that imports are likely to flow through Captain Jack and exports are likely to flow through the SMUD hub.” Id. ¶ 82. It further agreed that the CAISO’s experience from which it “anticipates that its proposal is needed to address unscheduled flows and effectively manage congestion,” as applied here, reasonably supported the use of default proxy prices. Id. The Commission noted as well that IBAA entities could avoid the proxy price by providing confidential proprietary information on actual power sources through MEEAs. See id. ¶ 83.
In rejecting comments that the IBAA Proposal’s use of the Captain Jack default proxy prices was unreasonable because it erroneously assumed Captain Jack to be the import source, the Commission explained that the CAISO “does not assert
Petitioners challenge as arbitrary and capricious the Commission’s determination that the default proxy prices for the IBAA were just and reasonable. They offer four grounds, none of which ultimately is persuasive. First, petitioners challenge the reasonableness of the assumption that IBAA entities use inexpensive Pacific Northwest power to schedule imports into the CAISO, but do not challenge the use of the proxy system itself. Their principal objection is that the Commission failed to address uncontradicted evidence demonstrating the IBAA entities use power from the Pacific Northwest to serve their own loads, rather than re-selling that power to the CAISO.
Petitioners’ complaint about the different assumptions that underlie the default prices charged for imports and for exports is misdirected; the Commission did not mistakenly treat those assumptions as established facts. Rather, as the Commission explained, the default prices were based on flow data used to accomplish the CAISO’s purpose of eliminating arbitrage opportunities. See Order ¶ 83. The use of proxy pricing, as the CAISO explains in its brief, focused not on the intended ultimate use of energy purchased by the IBAA entities but on the power flow, and the CAISO studies showed that 15% or less of energy passing through Captain Jack flowed through Tracy and “[m]ost of the remainder, 66% of the power flows, entered the ISO system through the Pacific AC Intertie.” Intervenor CAISO Br. 25.
The Commission adopted this analysis in rejecting petitioners’ evidence and contrary views. See Order ¶¶ 90-92. The Commission concluded that absent more detailed information from IBAA entities about generation sources, imports into the CAISO are likely to flow through the Captain Jack substation, supported by resources from the Pacific Northwest. The CAISO flow studies support this finding. Moreover, the Commission noted, petitioners may avoid default prices by providing accurate information to the CAISO, either through MEEAs or otherwise.
Second, petitioners object that the Commission’s failure to remedy duplicative congestion charges is irreconcilable with its recognition that default IBAA prices account for parallel flows. The Commission ordered the CAISO to prevent double-charging for losses flowing over the COTP, one of the three California-Oregon Inter-tie lines, and explained why there is no comparable congestion duplication to be eliminated:
[T]he congestion will not arise due to capacity limitations on the California-Oregon Intertie. Rather, the congestion will arise due to the capacity limitations*326 of other elements of the CAISO-controlled grid which, under normal operations, will be the limiting factors for scheduling interchange transactions that also use the California-Oregon Intertie. Said another way, any congestion that is reflected in [locational marginal prices] applicable to interchange transactions that use the California-Oregon Intertie will be attributable to binding constraints, not on the intertie, but on the other elements of the CAISO-controlled grid.
Order ¶ 105; see also Rehearing Order ¶ 82. Petitioners maintain that the Commission failed to address record evidence demonstrating that their congestion charges will increase under the IBAA Proposal, creating an “overcollection.” But such evidence does not undermine the Commission’s point that the CAISO charges are not for congestion on the California-Oregon Intertie. The Commission, noting evidence submitted by the CAISO, explained that the charges are for congestion on the CAISO’s own underlying 230 kilovolt line and “other elements of the CAISO-controlled grid,” not for congestion on the California-Oregon Intertie. See Order ¶ 105 & n.97 (citing IBAA Proposal Ex. ISO-1, at 88-89). Thus, a customer transacting in the CAISO market will pay one charge for using the California-Oregon Intertie and another charge for any congestion created on the CAISO-controlled grid.
Third, petitioners object that the Commission’s approval of the default price for imports was inconsistent with its finding that such a rate design “may, in limited circumstances, create an artificially low price” for energy. Order ¶ 120. Quoting Federal Power Comm’n v. Texaco Inc.,
Finally, the Commission gave a reasoned explanation for rejecting petitioners’ suggestion that the Captain Jack price could lead to substantially reduced imports creating instability on the CAISO-controlled grid. Essentially, the Commission concluded that the proxy prices generate benefits to all entities using the CAISOcontrolled grid because SMUD and Turlock cannot cause inaccurate market prices and infeasible scheduling. In the Commission’s view, the use of locational marginal pricing would strengthen the market by accurately reflecting market demand across the power grid and facilitating energy transactions. As the Commission stat
Accordingly, we deny the petitions for review. ,
Notes
. Petitioners are the Sacramento Municipal Utility District, the Turlock Irrigation District, the Modesto Irrigation District, the City of Redding, the City of Santa Clara d/b/a Silicon
. "An [Independent System Operator ("ISO”) ] is an independent company that has operational control, but not ownership, of the transmission facilities owned by member utilities. ISOs provide open access to the regional transmission system to all electricity generators at rates established in a single, unbundled, grid-wide tariff----" NRG Power Mktg., LLC v. Maine Pub. Utils. Comm’n, - U.S. -,
. Under a locational marginal price rate design, energy prices vary by location and time in order to reflect the cost of energy, including the cost of transmission losses and congestion, at each location on the CAISO-controlled grid. Sacramento Mun.,
. See United Gas Pipe Line Co. v. Mobile Gas Serv. Corp.,
