659 F.2d 1228 | D.C. Cir. | 1981
Opinion for the Court filed by Chief Judge SPOTTSWOOD W. ROBINSON, III.
The challenge here is to orders of the Federal Power Commission
I. THE TWO STATUTES
Natural gas companies must, under Section 4(a) of the Natural Gas Act, charge just and reasonable rates for the transportation and sale of their product.
The regulatory impact of a second statute — the Economic Stabilization Act of 1970
II. THE RATE INCREASE
Transco, an interstate gas pipeline company subject to the Natural Gas Act,
Subsequently, Transco and protestants against the proposed rates settled their differences, agreeing to an increase of approximately $35 million. Of particular importance here is that the agreement, in Article IV, addressed the 43-day period from July 1 through August 12 during which the new rates had been frozen by presidential decree, and provided that Transco would be permitted to recoup its foregone revenues.
Despite objections to Article IV,
The status of Article IV was thrown into additional confusion when the Cost of Living Council balked at endorsement of the recoupment feature of the agreement. The Council refused to expressly approve or disapprove Article IV but left little doubt as to its position, declaring that “the [Commission] should not approve any rate increase which is specifically based upon the principle of retroactive recovery of revenues ...”
Again fate intervened. The Economic Stabilization Act had expired on April 30, 1974;
Transco then returned to the Commission, requesting unqualified approval of Article IV. Pending resolution of the problem, the Commission allowed Transco to collect, subject to refund, the new charges from the date of expiration of the Commission’s suspension, including the 43-day period during which they were frozen by presidential order.
III. THE SETTLEMENT AGREEMENT
At the threshold, we face a comparatively straightforward question: whether the settlement agreement and the Commission’s 1974 order accepting it validly entitled Transco to retain the revenues generated while its rate' increase was frozen. If so, the inquiry need proceed no further, for parties undoubtedly are bound by settlement contracts into which they enter.
We believe, however, that the issue is settled by the fundamental maxim of contract law that “failure to occur of a condition upon which the bargain has been expressly or impliedly predicated excuses all parties to the contract from performing.”
Our conclusion is not changed by the obviously ambiguous language of the order accepting the settlement agreement. What the Commission there said was that “[t]o the extent the Cost of Living Council retains jurisdiction to approve the provisions of Article IV of the settlement, we defer to that jurisdiction. To the extent jurisdiction rests with this Commission, we find that Article IV is reasonable, and should be approved.”
We shall require Transco, as a condition to approval of the proposed settlement, to make application to the Cost of Living Council for approval of . . . Article IV .... At such time as Transco applies to this Commission for authorization to track these deferred amounts, it shall submit a statement outlining its efforts to obtain Cost of Living Council approval, and the results of such efforts. We shall consider such representations by Transco in determining the action to be taken.51
That, in sharp contrast to the language of the clause purporting to rule “[t]o the extent jurisdiction rests with [the] Commission”
Much earlier the Commission, by regulation, had pledged to maintain consistency with the Economic Stabilization Act when promulgating just and reasonable rates under the Natural Gas Act.
That indubitably was the Commission’s reading of the 1974 order when in 1978 it made its ultimate ruling on Article IV. The earlier order, the Commission stated, “left for future decision questions pertaining to Transco’s possible failure to obtain Cost of Living Council approval of . . . Article IV.
IV. THE STATUTORY RELATIONSHIP
The propriety of the Commission’s final order, however, is not assured by our determination that Article IV is non-binding. The Commission acknowledged that were it to apply traditional ratemaking criteria, it would approve operation of the rate increase from the moment its five-month suspension expired;
A. The Statute Utilized
At the outset, our analysis hinges on which body of legislation the Commission acted under when it ruled against Transco. This is more than a semantic issue, for orders issued under the Economic Stabilization Act may be challenged only in the District Court, with appeals to the Temporary Emergency Court of Appeals exclusively.
Unfortunately, the statutory basis of the Commission’s decision is'somewhat less than clear. As we have noted, the Commission found Article IV invalid “only insofar . . . as it [was] inconsistent with the Economic Stabilization Program.”
Here again, however, we believe the Commission’s current interpretation of the meaning of its 1974 order — that it was simply importing Stabilization Act principles into the Gas Act
The idea that the Commission can look to policies undergirding other federal statutes when interpreting the Gas and Power Acts is hardly novel or controversial. For example, the Supreme Court has flatly declared that the Commission must consider the “fundamental national economic policy expressed in the antitrust laws” as part of the “public interest” standard of the Power Act;
exercise of authority conferred by the Natural Gas Act, may, and in some instances must, take account of policies set forth in another Federal statute, without undercutting the quality of its action as one taken under the Natural Gas Act and reviewable in accordance with its procedures. It could also be said that in a certain sense the [Commission’s] action-— of making a determination of consistency with the Economic Stabilization Act of 1970 — must necessarily reflect an authority granted by at least the general framework of the Natural Gas Act. . . .75
The Stabilization Act, no less than numerous other pieces of legislation, embodies broad national policies designed to affect economic behavior at every level. Given the latitude traditionally accorded the Commission in interpreting the Gas Act’s mandates,
B. Jurisdiction
Our authority to resolve cases featuring the interplay between the Natural Gas and Economic Stabilization Acts has not hereto
On close inspection, however, it becomes clear that none of these decisions robs us of power to decide the instant controversy. In each, the critical question was whether Commission action resting indisputably upon the Stabilization Act was proper. The Temporary Emergency Court of Appeals has jurisdiction in cases “arising under [that Act] or under regulations or orders issued thereunder.”
As we have already said, the order before us was promulgated under the Gas Act.
C. The Merits
At long last we are in position to consider the merits of Transco’s argument, which in essence reduces to a single chain of reasoning. The Commission, Transco says, disallowed operation of the rate increase during the price-freeze period to avoid conflict with the Economic Stabilization Act. That legislation expired on April 30, 1974,
We find this argument seriously flawed. The Commission’s order, we repeat, effectuates a decision made under the Gas Act, not the Stabilization Act.
Surely it was within the Commission’s purview to determine whether a regulated entity should be permitted retrospectively to charge higher gas rates than could have been legally demanded when the gas was supplied.
Affirmed.
.Pursuant to the Department of Energy Organization Act. Pub.L.No. 95-91, § 402(a), 91 Stat. 565 (1977), 42 U.S.C. § 7172(a) (Supp. Ill 1979), most of the functions of the Federal Power Commission were transferred to the Federal Energy Regulatory Commission, the respondent-appellee herein. To preserve the present-tense style of this opinion as far as possible, we use the word “Commission” to refer to the Federal Power Commission in connection with events preceding October 1, 1977, the effective date of the Act, and to the Federal Energy Regulatory Commission in connection with those occurring thereafter.
. See note 42 infra. On the orders under review, see text infra at notes 39-41.
. 15 U.S.C. § 717c(a) (1976).
. Id. § 717c(d).
. Id. § 717c(e).
. See generally 18 C.F.R. §§ 154.38 to 154.41, 154.63 (1980).
. Economic Stabilization Act of 1970, Pub.L.No. 91-379, 84 Stat. 799 (1970), reprinted as amended following 12 U.S.C. § 1904 (1976).
. See Economic Stabilization Act of 1970, § 218, reprinted as amended following 12 U.S.C. § 1904 (1976).
. Id. § 203(a), reprinted as amended following 12 U.S.C. § 1904 (1976).
. 18 C.F.R. § 2.90(b) (1980).
. See 15 U.S.C. § 717(b) (1976).
. Exec. Order No. 11723, 38 Fed.Reg. 15765 (June 13, 1973).
. Joint Appendix (J.App.) 1-3.
. J.App. 2.
. J.App. 3.
. See Transcontinental Gas Pipe Line Corp., Docket No. RP 73-69, 51 F.P.C. 1243, 1245 (1974), J.App. 6.
. Id., 51 F.P.C. at 1246, J.App. 7.
. Id.
. Id.
. Id.
. See Appendix to Brief of Respondent-Appellee (A.App.) 4a. See also A.App. at 6a.
. A.App. 15a.
. Transcontinental Gas Pipe Line Corp. v. Department of the Treasury, Civ.No. 74-1389 (D.D.C.1974).
. See Economic Stabilization Act of 1970, § 218, reprinted as amended following 12 U.S.C. § 1904 (1976).
. Economic Stabilization Act of 1970, § 211(b), reprinted as amended following 12 U.S.C. § 1904 (1976).
. United States v. State of California, 504 F.2d 750 (Temp.Emer.Ct.App.1974), cert. denied, 421 U.S. 1015, 95 S.Ct. 2423, 44 L.Ed.2d 864 (1975).
. State of California dealt with a California law, effective on July 1, 1973, providing salary increases for state employees. On August 29, 1973, the Cost of Living Council declared some of those increases excessive and issued a limiting order. The employees sought a writ of mandamus to compel California officials to obey the statute in full, and a state court rendered judgment for the employees, effective on May 19, 1974. On May 8, however, the United States sought injunctive relief in a federal district court to prevent California from implementing the pay increases in contravention of the Council’s order. See id. at 752. On review of a preliminary injunction in favor of the Government, the Temporary Emergency Court of Appeals concluded that “by the explicit terms of Section 218 [of the Economic Stabilization Act], the [Council] and the courts . . . lost their authority ... on April 30, 1974. . . .” id. at 753. The two statutory exceptions to § 218 — for “pending proceedings” and for proceedings “based upon any act committed prior to May 1, 1974,” see Economic Stabilization Act of 1970, § 218, reprinted as amended following 12 U.S.C. § 1904 (1976) — did not help the Government: the exemption for “pending proceedings” was held to be limited to enforcement proceedings, and that for “acts committed” prior to the statute’s expiration was relevant only if they were "violations of the Act . . . that . . . could be the basis for a civil or criminal enforcement proceeding” — that is, an actual payout. United States v. State of California, supra note 26, 504 F.2d at 755 (emphasis in original).
. J.App. 16.
. J.App. 17.
. See FERC Order Disapproving Retroactive Increase in Frozen Rates, and Directing Refunds (Order), Docket Nos. RP 73-3, RP 73-69 and RP 72-99 (Jan. 18, 1978) at 8, J.App. 25.
. See text supra at note 18.
. See Order, supra note 30, J.App. 18-37.
. Id. at 13, J.App. 30.
. Id. at 15, J.App. 32.
. Id. at 16, J.App. 33.
. Id. at 18, J.App. 35.
. Id. at 13, J.App. 30.
. See text supra at notes 19-20.
. Order, supra note 30, at 13, J.App. 30.
. Id. at 20, J.App. 37.
. FERC Order Denying Rehearing and Granting a Stay, Docket Nos. RP 73 — 3, RP 73-69, RP 72-99 (May 16, 1978), J.App. 55-57. The Commission did, however, issue a stay pending Transco’s appeal. Id. at 3, J.App. 57.
. Transco also sought relief in the District Court for the District of Columbia pursuant to §§ 210 and 211 of the Economic Stabilization Act. Transcontinental Gas Pipe Line Corp. v. FERC, Civ. No. 78-1241 (D.D.C. Sept. 28, 1978). That court dismissed Transco’s complaint for lack of jurisdiction, holding that the Commission’s order had been issued pursuant to the Natural Gas Act and that accordingly this court was the proper forum for judicial review. Id. Doubting which legislation provided the basis for the order, Transco appealed to this court, No. 78-2193, and as well to the Temporary Emergency Court of Appeals, which stayed its hand pending resolution here. Transcontinental Gas Pipe Line Corp. v. FERC, No. D.C.-51 (Temp.Emer.Ct.App.1978). No. 78-2193, meanwhile, was consolidated with Transco’s petition for direct review, No. 78-1632. Transcontinental Gas Pipe Line Corp. v. FERC, Nos. 78-1632 & 78-2193 (D.C.Cir. Dec. 22, 1978). In light of our conclusion that the Commission’s order was promulgated under the Natural Gas Act, Part IV A infra, in No. 78-2193 we affirm the District Court’s judgment.
. See Mobil Oil Corp. v. FPC, 187 U.S.App. D.C. 112, 117, 570 F.2d 1021, 1026 (1978); Tennessee Gas Pipeline Co. v. FPC, 164 U.S.App.D.C. 130, 133, 504 F.2d 199, 202 (1974).
. Riley v. General Mills, Inc., 346 F.2d 68, 70 (3d Cir. 1965). Accord, Cole v. Benavides, 481 F.2d 559 (5th Cir. 1973); United States v. Schaeffer, 319 F.2d 907, 911 (9th Cir. 1963), cert. denied, 376 U.S. 943, 84 S.Ct. 798, 11 L.Ed.2d 767 (1964); Enerdyne Corp. v. Wm. Lyon Dev. Co., Inc., 488 F.2d 1237 (10th Cir. 1973).
. Approval by a third party is certainly a condition precedent. See, e. g., Los Angeles Raws Football Club v. Cannon, 185 F.Supp. 717 (S.D.Calif.1960).
. J.App. 2.
. J.App. 3.
. See text supra at notes 21-22.
. See text supra at note 28.
. Transcontinental Gas Pipe Line Corp., supra note 16, 51 F.P.C. at 1246, J.App. 7.
. Id.
. See text supra at note 50.
. See text supra at note 10.
. Transcontinental Gas Pipe Line Corp., supra note 16, 51 F.P.C. at 1246, J.App. 7.
. Id. at 1245, J.App. 6.
. See text supra at note 18.
. Order, supra note 30, at 15, J.App. 32. See also id. at 18, J.App. 35.
. Belco Petroleum v. FERC, 191 U.S.App.D.C. 157, 162-163, 589 F.2d 680, 685-686 (1978); Gillring Oil Co. v. FERC, 566 F.2d 1323, 1325 (5th Cir.), cert. denied, 439 U.S. 823, 99 S.Ct. 91, 58 L.Ed.2d 115 (1978). Cf. Chesapeake & O. Ry. Co. v. United States, 187 U.S.App.D.C. 241, 245, 571 F.2d 1190, 1194 (1977).
. Belco Petroleum v. FERC, supra note 58, 191 U.S.App.D.C. at 163, 589 F.2d at 686.
. Order, supra note 30, at 19, J.App. 36.
. Id. See also text supra at note 55.
. Economic Stabilization Act of 1970, § 211, supra note 7, reprinted as amended following 12 U.S.C. § 1904 (1976).
. See 15 U.S.C. § 717r(b) (1976).
. See text supra at note 61.
. Order, supra note 30, at 14, J.App. 31.
. Order, supra note 41, at 2-3, J.App. 56-57.
. See Brief for Appellees at 30-31.
. Order, supra note 16, at 16-17, J.App. 32-33.
. Id. at 16, J.App. 33.
. FPC Order No. R-437B (June 19, 1973), reprinted at A.App. 25a, 26a-27a.
. Gulf States Utils. Co. v. FPC, 411 U.S. 747, 759, 93 S.Ct. 1870, 1878, 36 L.Ed.2d 635, 644 (1973). Cf. McLean Trucking Co. v. United States, 321 U.S. 67, 64 S.Ct. 370, 88 L.Ed. 544 (1944).
. NAACP v. FPC, 425 U.S. 662, 666-669, 96 S.Ct. 1806, 1809-1811, 48 L.Ed.2d 284, 289-291 (1976).
. Northern Natural Gas Co. v. FPC, 130 U.S.App.D.C. 220, 226, 399 F.2d 953, 959 (1968).
. Calvert Cliffs’ Coordinating Comm., Inc. v. United States Atomic Energy Comm’n, 146 U.S.App.D.C. 33, 36, 449 F.2d 1109, 1112 (1971) (“every federal agency and department” must consider the environmental impact of its actions).
. Municipal Intervenors Group v. FPC, 153 U.S.App.D.C. 373, 376-379, 473 F.2d 84, 89-90 (1972) (citation omitted).
. See Permian Basin Area Rate Cases, 390 U.S. 747, 767, 88 S.Ct. 1344, 1360, 20 L.Ed.2d 312, 336 (1968); Montana-Dakota Utils. Co. v. Northwestern Pub. Serv. Co., 341 U.S. 246, 71 S.Ct. 692, 95 L.Ed. 912 (1951); Colorado Interstate Gas Co. v. FPC, 324 U.S. 581, 65 S.Ct. 829, 89 L.Ed. 1206 (1945); FPC v. Hope Natural Gas Co., 320 U.S. 591, 601, 64 S.Ct. 281, 287, 88 L.Ed. 333, 344 (1944); FPC v. Natural Gas Pipeline Co., 315 U.S. 575, 62 S.Ct. 736, 86 L.Ed. 1037 (1942).
. Permian Basin Area Rate Cases, supra note 76, 390 U.S. at 767, 88 S.Ct. at 1360, 20 L.Ed.2d at 336.
. Order, supra note 30, at 13, J.App. 30.
. Permian Basin Area Rate Cases, supra note 76, 390 U.S. at 767, 88 S.Ct. at 1360, 20 L.Ed.2d at 336, quoting FPC v. Hope Natural Gas Co., supra note 76, 320 U.S. at 602, 64 S.Ct. at 288, 88 L.Ed. at 345.
. 200 U.S.App.D.C. 156, 626 F.2d 1020 (1980).
. Supra note 75.
. Connecticut Mun. Group v. FPC, 162 U.S.App.D.C. 260, 265, 498 F.2d 993, 998 (1974). See also Municipal Elec. Utils. Ass’n v. FPC, 158 U.S.App.D.C. 188, 191-192, 485 F.2d 967, 970-971 (1973).
. Economic Stabilizaton Act of 1970, § 211(b)(2), reprinted as amended following 12 U.S.C. § 1904 (1976).
. Tennessee Gas Pipeline Co. v. FERC, supra note 80, 200 U.S.App.D.C. at 157, 626 F.2d at 1021.
. Municipal Intervenors Group v. FPC, supra note 75, 153 U.S.App.D.C. at 377, 473 F.2d at 88.
. Id. at 378, 473 F.2d at 89.
. See Part IV A supra.
. See text supra at notes 67-70.
. See text supra at notes 67-70.
. 15 U.S.C. § 717r(b) (1976).
. See Economic Stabilization Act of 1970, § 218, reprinted as amended following 12 U.S.C. § 1904 (1976).
. These exceptions are not relevant here. Consideration of Transco’s rate request was not an enforcement proceeding; and to be actionable the acts committed prior to expiration
. Brief for Petitioner at 13-16.
. See Part IV A supra.
. Economic Stabilization Act of 1970, § 218, reprinted as amended following 12 U.S.C. § 1904 (1976).
. See note 27 supra.
. Thus State of California, on which Transco relies extensively, see Brief for Petitioner at 13-16, is completely inapposite. There the Temporary Emergency Court of Appeals simply gave effect to the plain language of the Economic Stabilization Act specifying when authority to issue orders thereunder lapsed. See note 27 supra. That hardly means that the anti-inflation program reflected by the Stabilization Act must be ignored when rates are set under another statute. Transco has pointed to nothing in the language or the legislative history of the Act — let alone in State of California —that commands such a broad result.
. It should be noted that the proper construction of the Economic Stabilizaton Act is not at issue here. If the outcome of the case turned on an issue of that sort, it is at least arguable that we would have to find jurisdiction in the Temporary Emergency Court of Appeals. See Connecticut Mun. Group v. FERC, supra note 82, 162 U.S.App.D.C. at 265, 498 F.2d at 998. But Transco does not challenge the Commission’s understanding of the Act’s anti-inflation program, or claim that the increased rate would not have contravened it. Transco argues instead that the Commission could not look to the Act or its policies at all.
. See NAACP v. FPC, supra note 72, 425 U.S. at 668, 96 S.Ct. at 1810-1811, 48 L.Ed.2d at 290-291.
. 6 C.F.R. § 150.1(d) (1974).