History
  • No items yet
midpage
Transamerica Insurance Co. v. Housing Authority of Victoria
669 S.W.2d 818
Tex. App.
1984
Check Treatment

*1 dictment Cause No. so as to

aggregate the amounts so as to create one degree felony, third under TEX.PENAL § (Vernon 1974). CODE ANN. 31.09 Appellant plea guilty entered a to each judicial indictment and executed a confes- punishment sion. The trial court assessed at confinement for a of three in each the two three terms to concurrently. run charge appellant The two indictments general with the offense of theft under the statute, theft TEX.PENAL ANN. CODE § (Vernon Supp.1984). Appellant 31.03

contends the convictions are void for reason that the indictments should have

charged the under offenses TEX.HUM. § 1980). ANN. 33.011 RES.CODE urged by appellant The contention now rejected by our Court of Criminal Appeals Mangrum, in Ex Parte 564 S.W.2d (Tex.Cr.App.1978). Op.Tex. also (1982).

Atty.Gen. No. MW-582 of charged by fenses indictments properly chargeable case at bar are the offense of theft as set out TEX.PE § (Vernon Supp. NAL CODE ANN. 31.03 1984). in each case is affirmed.

TRANSAMERICA INSURANCE

COMPANY, Appellant, AUTHORITY OF CITY HOUSING Texas, VICTORIA, Appellee. OF No. 13-82-385-CV. Appeals of Court of Corpus Christi. March 1984. Rehearing April Denied *2 Jones, III, Victoria, Douglas

O. F. M. Brin, Kennedy, Christi, Brin Corpus & for Campbell Construction Co. Antonio, Shaddox, for San R. Charles appellee. BISSETT, and GON- KENNEDY

Before ZALEZ, JJ.

OPINION

BISSETT, Justice. arising This is a suit out of construction contract. The Au- thority City Victoria, here- Housing Authority,” after “the peti- 30,1979, sought damages tion filed on from Transamerica Insurance Co., Campbell Bruce & Son Construction Inc., others, alleged arising out of a contract for the public housing renovation of Victoria, Texas. The case was submitted jury special to the issues. an- Certain jury, swers do not we discuss opinion, disregarded by in this were immaterial, being trial court as but based jury’s remaining on the answers to the issues, judgment rendered that jointly recover and sev- erally from Bruce & Son Con- Co., (the Inc. contractor for the construction), allegedly defective hereafter “Campbell,” and Insurance Transamerica (the Company surety on the given by Campbell), hereafter “Trans- america,” damages actual in the amount of $384,323.00, $66,000.00 attorney’s fees $20,- case, through trial of the attorney’s further fees” after 000.00 “for attorney’s the trial. The additional fees remittitur, total, subject part were appeals depending on whether there were appellate from the to the courts. addition, judgment In was rendered that Campbell the Transamerica recover from Dayton Wiley, Walker, G. Cornel W. Wi- $384,323.00, damages, sum of “for actual Garwood, ley, Simmons, Stolhandske & San $39,000.00 and the further sum of for attor- Antonio, for Transamerica Insurance Co. through ney’s fees for services rendered Sharber, Law Kenneth Office of Windle sum the trial of this and the further P.C., Dallas, Turley, for Victoria attorneys’ fees for further Authority. cause,” incurred after trial of this re-nail, Campbell agreed necessary,

provisions for remittitur staples in the construction of the appeal Campbell has used judgment. re-nailing, per- that needed and authorized appealed. Only roofs Transamerica Housing Authority to retain an addi- appeal judg- fected an from the trial court’s staples however, tional until the were Campbell, has filed a brief ment. nailed, pos- upon conditioned the latter’s imme- in this Court wherein it assumes *3 payment previ- of the Trans- diate to the former appellee response to ture of an $44,574.00, ously agreed upon sum of less twenty-seventh and twenty-sixth, america’s $1,000.00 After the additional retention. twenty-eighth points of error. We do not re-nailed, staples Housing the appeal. the had been points of error in this reach those Authority paid agreed upon the sum of 1, 1974, Authority, Housing the On $44,574.00 Thereafter, Campbell. owner, general Campbell, and as the as the Housing Authority paid an additional contractor, con- entered into a construction $5,200.00 the sum Campbell but retained repair for the and modernization tract $5,000.00. payment The final under the Hous- housing projects by owned three $5,000.00 in the amount of was contract for the construction of a ing and Campbell of its made to because never building, was also a community new which de- remedy certain construction failure to price building. original The contract public provisions in in accordance with the fects $871,300.00. Transamerica issued was required it contract which Housing in favor of the performance bond occurring one after the within as “LHA” Authority, sometime referred to occupancy Housing Authority’s documents, in amount of the contract project. original price. contract third, fourth, Transamerica, second, in its Housing Authori- August On error, sixth, eighth points of and seventh projects, and a “Certificate ty occupied the failing the trial court erred contends that Campbell by executed and Release” was failing verdict and grant it a directed Also, the same Housing Authority. jury the case from to withdraw Completion” was day, a “Certificate of favor, in its because render Authority’s archi- signed by Housing by it brought against Buck, Housing Au- tect, by the Robert V. one-year stat- by the Authority was barred by Campbell, which stated thority and provided by TEX. as ute of August completed as of the work art. 5160 G REV.CIV.STAT.ANN. “punch exception of certain 1971). $10,200.00. in the amount of list” items brief, subsequently paid all sums Authority, in its ar- except owing the contract gues:

$5,000.00. “1) executed performance (Transamerica) provided Appellant dirt consisted of punch list items expira- instituted before must be $1,000.00, paving work work of (2) date on years from the tion $4,400.00, $4,600.00, paneling of exterior This limi- fell due. payment final At the time shelving of $200.00. (2) contained period of two tation executed, the Completionwas Certificate of over controls performance bond withheld, as retain- Authority had period provid- (1) year limitation one $54,774.00 for in as called age, the sum ed in Article Housing Au- documents. the contract (Transamerica) failed 2) Appellant agreed thority, the architect seeking a fact jury issue to the an submit should be sum of that the comple- ‘final to when com- determination Housing Authority until by the tained occurred. Under contract items, tion’ of the and that punch list pletion of such (1) limitation one should remaining amount comple- upon ‘final begins run period August Campbell. On paid to tion of the contract. any Even the limita- We have found case which dealt period provided in Article 5160 where, is with the situation in a con- held to control over the terms of the project, there was a conflict be- bond, absent fact determination period tween the limitation under Article jury as to ‘final completion’ when of the peri- 5160 G and the contractual limitation occurred, contract it impossible to now od set forth in bond. How- (1) determine if the year statutory ever, Supreme Court of Texas ad- expired had before suit was filed. problem dressed a somewhat similar 3) Company Sherwin-Williams v. American The issuance the architect of the Indemnity Company, 504 S.W.2d 400 Completion not, Certificate of (Tex.1974), payment where bond in a a conclusive ‘fi- determination that private project presented completion’ nal oc- contractual limitation curred.” was in conflict with the peri- limitation *4 Article part, provides: 5160 relevant There, od. a clause identical the two- suit “G.... No shall instituted on year period limitation in the contained bond performance expira- bond after the by upheld furnished by Transamerica was (1) year tion of one after the date of final Supreme However, Court. in that completion of such contract ...” the facts were different from those There, case. 1971), granted 5160 A the trial Article court which bonding company was when a subject summary judgment effect on executed, required ground was any person period that that limitation of who any governmental provided contracted with fourteen by or months Article 5472d quasi-governmental (the Act) authority for the con Hardeman barred the suit public improvements struction of surety furnish as a matter of law. Court performance a bond where the of Appeals construction Civil affirmed the of $2,000.00. costs exceeded court, In the Supreme instant trial but the Court re- case, the costs were greatly excess of versed judgments of the lower courts $2,000.00; therefore, performance a Supreme bond and remanded the case. The required by the statute since the Hous Court held that since the bond ing is a quasi-governmental qualify statutory bond, au as a it error thority. claim, The bond stated suit must be insti hold that the filed expiration tuted before the the statutory period expired but within from the date when payment final the two-year became limitation provided for due. bond, was barred as a matter of law. Supreme Court further that “the held performance bond furnished two-year contractual controls.” limitation required A, Transamerica is Article 5160 Supreme particularly Court noted that is in compliance provisions of that compliance “elective,” with Article 5472dis statute, a statutory Any and is bond. suit while Article statute subject on the one-year bond is to the limi quired person who was sheriff elected period provided by tations Article 5160 G. furnish a in a bond certain amount of mon- provisions statutory “The [of 5160] ey, statutory “required” is a bond which is governing recovery mandatory are as well persons taking of all office as sheriff. provide only procedure as exclusive and courts, presenting for a claim The federal where federal con- City involved, bond.” San v. Argo projects gener- Antonio are have naut ally peri- Insurance 644 S.W.2d 90 held that the limitation (Tex.App. prevails provisions Antonio writ od conflicting ref’d over bond —San n.r.e.). also, Fidelity Deposit covering filing & Co. v. the time for on the Co., Big Welding Equip. Three 151 pp Tex. bond. See 52 Tex.L.Rev. 1459 (1974). (1952). 249 183 S.W.2d 822 pletion

Care not to of the contract’ is now the deter- must be taken confuse applicable pri mining the statute factor.” construction statute vate contracts surety It is well settled that a on applicable public of limitations construc performance rely is bond entitled to on is tion contracts. A contractor re Completion Certificate as architect’s performance for quired to furnish a discharge duty of its the bond final is, however, private He re construction. agent repre because the architect performance to furnish bond for a quired owner, representa sentative of the and his where, project, representation tion is of the owner. exceeded the construction costs Waller, 430 473 Midland v. S.W.2d (now $25,000.00). Tendick, (Tex.1968); Tex. Boettler v. 73 We hold that the instant ease falls within (1889). equally 497 well S.W. It is purview of Article which re- settled if the owner the construc quired that a bond be fur- (or per an other designates architect nished connection with the construction son) supervise approve the work public improvements the Hous- here, performed, is the case his decision as Authority. Consequently one-year ing owner, fraud or binding upon absent provided Article period of Library Carnegie bad Ass’n faith. Public controls, two-year than the rather (Tex. Harris, 97 S.W. Brownwood provided for in the bond. ref’d); Civ.App.1906, writ First- See also Wood, 632 Bank v. Wichita National Having determined *5 1982, (Tex.App. S.W.2d 210 Worth provided by of year statute —Port writ); Cook, 592 no Hooks v. 345 S.W.2d is in this we applicable Article 5160 1961, ref’d (Tex.Civ.App. writ that limita must now determine when time —Houston n.r.e.); Bank Tensha v. Col First State year expired. Under the one of linsworth, (Tex.Civ.App.— 111 S.W.2d 309 period, on a suits dism’d). 1937, or writ Fraud Beaumont one brought year must be within of present not in this case. bad faith is completion date of the final of the the contract, final payment not the date that in provision extension of time fact, due, was, actually paid. or in became only frame the time the contract relates may frame extended This time remedy agreed to for which the contractor remedy de agreement of an existence ever, time, point to a in defects and not workmanship that arise fects in within repairs actually made that the contractor acceptance. the final time after defects, fully and complained of or was Constructors, Inc. v. Bayshore Southern Normally, finally contract would paid. Municipal Utility County Montgomery certifi completed have on the date the been District, (Tex.Civ.App.— 543 898 S.W.2d which, completion accepted, in cate of 1976, n.r.e.). Here, ref’d Beaumont writ August have been 1975. this case would any agreed remedy Waller, 430 v. S.W.2d City Midland workmanship faulty materials due (Tex.1968). However, if the com 473 even year appeared one from the within an additional pletion was extended for date Authority’s occupancy date of the Camp for which year to cover construing In project. of the or use defects, agreed discovered bell Court, in provision, Bayshore, similar finally com have the contract would been stated: 4, August and limitations pleted on to mean that a 5160 “We construe art. run from that would have commenced to of the in position in the District person date. file year has a case full this ex Housing Authority’s own elapsed ‘remedy’ period one _ long- pert that construction date no testified The ‘final settlement’ provi criteria, improvements in accordance important but the ‘com- is the

er 823 substantially sions of the contract have should been rendered. Transameri- complete third, on August second, fourth, sixth, It has ca’s seventh uniformly held comple eighth that “substantial points of are and error sustained. regard tion” of is case, it In view of our decision in this is ed, legal parlance, in perform as “full dispose necessary not that we of Trans- Martin, Corporation ance.” Del Monte v. remaining points of america’s error. (Tex.Civ.App. S.W.2d 597 Antonio —San judgment of the trial court insofar n.r.e.); v. Telles Vasconce writ ref’d recovery damages as it awarded and los, (Tex.Civ.App. 417 S.W.2d 491 Paso —El attorney’s Housing Authority fees to n.r.e.); Weissberger ref’d writ Victoria, Texas, plaintiff City of Brown-Bellows-Smith, Inc., 289 S.W.2d Court, appellee court trial this (Tex.Civ.App. writ —Galveston against Transamerica Insurance Beckham, n.r.e.); Ditmar v. ref’d one of defendants the trial court and 801 (Tex.Civ.App. S.W.2d Worth —Fort Court, appellant is REVERSED dism’d). conclusively It writ here RENDERED that by the that shown record “the date of final Victoria, Housing Authority completion of the contract” more than nothing take its prior date Company. Transamerica Insurance We do Authority Therefore, filed this suit. remaining portions disturb date did have to be determined All judgment. appeal costs of this are jury. Housing Authority taxed That certain monies retained were Victoria, City of Texas. retain- age provisions of the contract and subse J., GONZALEZ, opinion with concurs quent agreements between the KENNEDY, J., joins. paid was not the final are immaterial deter GONZALEZ, Justice, concurring. mining the date when the contract was However, I concur the result. completed. represents item *6 law, disagree I that as matter Article only slightly more than one-half of one (Vernon 1971) parties controls. The (.0058) G percent price, contract right extend pay failure to money amount they contracted for a two limita Campbell should construed a man Nonetheless, period. tions even under the ner will suspend the determination year period appellee’s complet the date when the suit still for the barred reasons stated ed. majority opinion. Since the Authority not file against perform- Transamerica on 30, 1979, ance bond until and as there J., KENNEDY, concurs. nothing in the record which shows that running tolled, of the statute was

cause of action asserted Transamerica accrued more than the contract was completed and the occu- pied premises. The barred one-year statute of limitations under G. Transamerica’s motion for grant- verdict directed should have

ed, that the Author- ity nothing Transamerica take

Case Details

Case Name: Transamerica Insurance Co. v. Housing Authority of Victoria
Court Name: Court of Appeals of Texas
Date Published: Mar 29, 1984
Citation: 669 S.W.2d 818
Docket Number: 13-82-385-CV
Court Abbreviation: Tex. App.
AI-generated responses must be verified and are not legal advice.
Log In