Lead Opinion
{¶ 2} On May 21, 2004, Trans Rail applied to the Trumbull County Health Department ("Health Department") for a license to establish a construction and demolition *2
debris facility in Hubbard, Ohio.1 In a July 16, 2004 letter, the Commissioner stated that the Health Department could not consider Trans Rail's application because it was incomplete. To assist Trans Rail in the application process, the Commissioner identified the parts of the application that did not comply with Ohio Adm. Code
{¶ 3} Representatives of CT Consultants, Inc. ("CT Consultants"), an engineering firm that Trans Rail hired to oversee the application process, met with the Commissioner to discuss the application. On December 16, 2005, CT Consultants delivered to the Commissioner written responses and additional documents to resolve the deficiencies in Trans Rail's application. In a letter dated February 15, 2006, the Commissioner acknowledged receipt of the additional information, but he again found that the application was incomplete and refused to consider it. The Commissioner attached to the February 15, 2006 letter a report generated by Bennett Williams Environmental Consultants, Inc. ("Bennett Williams"), a firm that the Health Department hired to evaluate Trans Rail's application. The Commissioner directed Trans Rail to address those areas of the application that the report found were lacking the necessary information.
{¶ 4} In two letters dated March 30, 2006, CT Consultants replied to the comments in Bennett Williams' report and submitted further information regarding the proposed construction and demolition debris facility. In a response letter dated May 31, *3
2006, the Commissioner concluded that Trans Rail's application still failed to comply with Ohio Adm. Code
{¶ 5} On June 30, 2006, Trans Rail filed an appeal before the ERAC asserting one assignment of error:
The Health Department erred in determining that Trans Rail's [Construction Demolition and Debris] License Application was incomplete and could not be considered under the requirements of Ohio Administrative Code ("O.A.C.") Rule 3745-37-02(A)(2).
Trans Rail asked the ERAC to find that its application was complete and to order the Health Department to consider it. The Commissioner moved to dismiss Trans Rail's appeal for lack of subject matter jurisdiction. The Commissioner argued that the May 31, 2006 letter was not an appealable action under R.C.
{¶ 6} Trans Rail now appeals from the March 8, 2007 final order and assigns the following errors:
1. THE ENVIRONMENTAL REVIEW APPEALS COMMISSION ERRED IN FINDING THAT IT LACKED *4 SUBJECT MATTER JURISDICTION TO HEAR THE APPEAL ON THE GROUNDS THAT THE APPELLEE HEALTH DEPARTMENT'S DETERMINATION OF INCOMPLETENESS OF APPELLANT'S LICENSE APPLICATION WAS NOT A FINAL APPEALABLE ACT OR ACTION.
2. THE ENVIRONMENTAL REVIEW APPEALS COMMISSION ERRED IN FINDING THE APPELLEE HEALTH DEPARTMENT'S DETERMINATION OF INCOMPLETENESS TO BE REASONABLE DESPITE THE COMMISSION'S FINDING THAT IT LACKED JURISDICTION TO HEAR THE APPEAL.
{¶ 7} By its first assignment of error, Trans Rail argues that the ERAC erred in dismissing its appeal for lack of subject matter jurisdiction. We agree.
{¶ 8} An administrative agency has only those powers that the General Assembly expressly confers upon it. Shell v. Ohio Veterinary Med.Licensing Bd.,
{¶ 9} The parameters of the ERAC's jurisdiction are set forth in R.C.
Any person who was a party to a proceeding before the director of environmental protection may participate in an appeal to the environmental review appeals commission for an order vacating or modifying the action of the director or a local board of health, or ordering the director or board of health to perform an act.
We have previously found that this provision allows the appeal of "actions" to the ERAC. Dayton Power and Light Co. v. Schregardus (1997),
{¶ 10} In the case at bar, Trans Rail's appeal requests that the ERAC order the Health Department to either issue or deny it a license to establish a construction and demolition debris facility. R.C.
{¶ 11} Our analysis does not require consideration of whether the Commissioner's May 31, 2006 letter constitutes a "final" action. The ERAC and, if necessary, this court *6
must determine whether an action is final only if the aggrieved party requests that the ERAC vacate or modify the action. See US TechnologyCorp. v. Korleski, Franklin App. No. 07AP-383,
{¶ 12} Having concluded that the ERAC has jurisdiction over Trans Rail's appeal, we sustain Trans Rail's first assignment of error.
{¶ 13} By Trans Rail's second assignment of error, it argues that the ERAC prematurely determined the merits of its appeal. We agree.
{¶ 14} If neither the Director of the Ohio Environmental Protection Agency nor a board of health conducts an adjudicatory hearing, then the ERAC must conduct a hearing de novo on the appeal. R.C.
{¶ 15} For the foregoing reasons, we sustain Trans Rail's first and second assignments of error. Further, we reverse the March 8, 2007 final order of the Environmental Review Appeals Commission, and we remand this matter to that commission for further proceedings in accordance with law and this opinion.
Order reversed and matter remanded.
TYACK, J., concurs. FRENCH, J., dissents.
Notes
Dissenting Opinion
{¶ 16} In its opinion, the majority concludes that the Environmental Review Appeals Commission ("ERAC") has jurisdiction over an appeal from a letter finding a license application incomplete. The majority reaches this conclusion based solely on ERAC's authority under R.C.
{¶ 17} The specific question in this case is whether ERAC has jurisdiction over an appeal by appellant, Trans Rail America, Inc. ("appellant"), from a finding by appellee, James J. Enyeart, M.D., Health Commissioner, Trumbull County Health Department ("appellee"), that appellant's application for a license to establish a construction and demolition debris ("C DD") facility was incomplete. As detailed in the majority opinion, appellant first applied for the license in May 2004. Over the next two years, appellee twice found the application to be incomplete, despite appellant's submissions of additional information. Finally deciding that it had no remedy but to appeal to ERAC, appellant filed an appeal from appellee's May 31, 2006 letter, which indicated for the third time that appellant's application was incomplete.
{¶ 18} On appeal, ERAC analyzed whether the May 31, 2006 letter was a final action appealable under R.C.
{¶ 19} Before this court, appellant's first assignment of error asserts that ERAC erred in finding that it had no jurisdiction. In support, appellant asserts that the letter constituted a final action appealable under R.C.
{¶ 20} R.C.
Any person who was a party to a proceeding before the director of environmental protection may participate in an appeal to [ERAC] for an order vacating or modifying the action of the director or a local board of health, or ordering the director or board of health to perform an act. [ERAC] has exclusive original jurisdiction over any matter that may, under this section, be brought before it.
{¶ 21} Clearly, R.C.
{¶ 22} For example, R.C.
{¶ 23} R.C.
* * * "[A]ction" or "act" includes the adoption, modification, or repeal of a rule or standard, the issuance, modification, or revocation of any lawful order other than an emergency order, and the issuance, denial, modification, or revocation of a license, permit, lease, variance, or certificate, or the approval or disapproval of plans and specifications pursuant to law or rules adopted thereunder.
{¶ 24} For decades, this court has recognized that the terms "act" and "action" include, but are not limited to, the actions enumerated in R.C.
The General Assembly * * * in drafting R.C.
3745.04 chose to illustrate rather than define an appealable action, thereby vesting [ERAC's predecessor, the Environmental Board of Review] with jurisdiction over acts of the director beyond the adoption, modification or repeal of a rule. Past decisions of this court illustrate that the broad definition of appealable acts contained in the statute is to be liberally construed in favor of appeals to [ERAC]. See, e.g., Cain Park Apts. v. Nied (June 25, 1981), Franklin App. No. 80AP-817 et seq., unreported.
{¶ 25} When faced with an action not enumerated in R.C.
{¶ 26} This court recently distinguished Dayton Power Light inUS Technology Corp. v. Korleski, Franklin App. No. 07AP-383,
{¶ 27} In contrast, here, the majority does not analyze whether ERAC properly determined that it lacked jurisdiction over appellee's May 31, 2006 letter because it was not a final action appealable under R.C.
{¶ 28} R.C.
{¶ 29} R.C.
{¶ 30} Nowhere in these statutes authorizing the issuance and denial of licenses generally, or even C DD facility licenses specifically, is there authority for an appeal to ERAC before a final action by Ohio EPA or the board of health, and allowing a premature appeal, i.e., an appeal prior to a final action that adjudicates the rights of the applicant, interferes with this legislative scheme. Rather than requiring an applicant to complete the statutory process, the majority opinion allows an applicant to circumvent the process by prematurely appealing an agency's request for additional information or finding that an application is incomplete.
{¶ 31} Here, ERAC clarified that it did "not intend to imply that repeated, unreasonable requests for additional information by a licensing authority could never" *12
give rise to a final appealable action under R.C.
{¶ 32} In my view, the better reading of R.C.
{¶ 33} In the end, I would find that ERAC properly identified the factors it must consider in determining whether it has jurisdiction over the appeal. Specifically, having concluded that the May 31, 2006 letter did not reflect an "act" or "action" enumerated in R.C.
{¶ 34} ERAC also recognized correctly that the May 31, 2006 letter still could constitute a final action if it met certain substantive criteria, as follows:
Even if a document does not, in form, constitute a final action it may still be a final action if the substance of the document adjudicates with finality any legal right or privilege of the appealing party. Conversely, if the document represents an intermediate step in a continuing process, or if the contents of the document indicate that it is only a segment of an evaluation that will ultimately lead to a final action, then, at that juncture, no final appealable action has occurred. Thus, the final inquiry [ERAC] must make is whether [appellee's] May 31, 2006 letter adjudicates with finality any legal right or privilege of [appellant]. * * *
(Final Order at 14, ¶ 8.)
{¶ 35} I concur in ERAC's articulation of the test for determining whether the letter was appealable under R.C.
{¶ 36} In contrast to the case before us, however, in CECOS, neither ERAC nor this court had to determine whether the director's finding that the application was incomplete was a final action appealable under R.C.
{¶ 37} Here, ERAC correctly stated that, in order to determine whether it has jurisdiction over appellant's appeal, ERAC must first determine whether the May 31, 2006 letter "adjudicates with finality any legal right or privilege" of appellant. Only after finding jurisdiction proper may ERAC proceed to the merits, i.e., deciding whether the application is complete.
{¶ 38} Admittedly, ERAC concluded that the May 31, 2006 letter "was not a final appealable action, but rather, represents an intermediate step in a continuing process." (Final Order at 19, ¶ 15.) However, ERAC reached that conclusion without analyzing the factors it had identified previously. Therefore, while I would overrule the substance of appellant's first assignment of error, I would remand this case for further consideration in accordance with the appropriate jurisdictional test, as articulated by ERAC and this court.
{¶ 39} In its second assignment of error, appellant asserts that ERAC erred by finding the May 31, 2006 incompleteness determination to be reasonable without an *15 evidentiary hearing. Having concluded that ERAC must consider the jurisdictional question further, I would conclude that appellant's second assignment of error is moot.
{¶ 40} In conclusion, the majority having determined that ERAC has jurisdiction under the express terms of R.C.
