OPINION
The principal issue on appeal is whether the trial court or an arbitrator determines arbitrability of the plaintiffs claims. The challenged order was signed by the trial court, which determined that the claims at issue are not arbitrable. Because an arbitration agreement existed between the parties, and because that agreement assigns arbitrability determinations to the arbitrator, we conclude the trial court erred by making the determination. Accordingly, we reverse and remand to the trial court for proceedings consistent with this opinion.
Background
Appellant Trafigura Pte. Ltd. contracted in January 2013 to buy 70,000 metric tons of iron ore from appellee CNA Metals Limited (the “First Contract”). This contract included a broad-form arbitration agreement submitting all disputes to arbitration in England under the United Kingdom’s arbitration rules.
According to CNA, a smaller scrap-metal trading company called Jace Metals and Minerals, L.L.C. acted as CNA’s agent in connection with the First Contract. CNA allegedly advanced funds to Jace with the expectation that Jace would use them to purchase the iron ore promised to Trafigu-ra in the First Contract.
Because of Jace’s alleged failure to secure sufficient iron ore, CNA delivered only 40,989.13 of the 70,000 contracted-for metric tons of iron ore. CNA admitted in its live petition below that it breached the First Contract by delivering only a portion of the contracted-for ore, but contended that Trafigura accepted the lesser amount in late March 2013 and paid CNA $4,302,211.60 for the ore in April 2013.
.Jace allegedly approached Trafigura in June 2013 without CNA’s knowledge and proposed to sell Trafigura 80,000, additional tons of iron ore. Jace and Trafigura allegedly entered into a new contract (the “Second Contract”), and Jace allegedly sold Trafigura the iron ore in exchange-for approximately $4 million, Jace is alleged to have kept this amount for itself. CNA alleged that at least a portion of the iron ore Jace sold to Trafigura under the Second Contract was purchased using funds CNA had advanced to Jace to purchase ore under the First Contract.
CNA sued Jace and its principals in November 2013, and added Trafigura as a defendant in November 2015.
Trafigura moved to stay proceedings and compel arbitration pursuant to the arbitration clause in the First Contract. After hearing arguments from the parties, the trial court denied Trafigura’s motion to compel arbitration on June 16, 2016. The trial court made the following findings in its order:
1. On January 22nd, 2013 Plaintiff CNA entered into a purchase contract (hereinafter referred to as the “contract”) with Defendant Trafigura PTE that contained a broad form arbitration agreement.
2. That while the relationship between the parties may have begun in this contract, or bear some evidentiary relationship to this contract, that the subject matter of the causes of action do not fall within ..the scope of the arbitration agreement, and can be maintained without reliance/reference to the contract.
Trafigura timely filed this interlocutory appeal. See Tex. Civ. Prac. & Rem. Code Ann. § 51.016 (Vernon 2015) (in a matter subject to the Federal Arbitration Act, an appeal may be taken from an interlocutory order of a district court under the same circumstances that an appeal from a federal district court’s order or decision would be permitted by 9 U.S.C. § 16); 9 U.S.C.A. § 16(a)(1)(C) (West 2009) (under FAA, appeal may be taken from order denying application to compel arbitration); In re Helix Energy Sols. Grp., Inc.,
Analysis
Trafigura contends that the trial court erred by denying its motion to compel arbitration for three reasons. First, Trafi-gura contends that the trial court, erred at the outset by determining arbitrability because the arbitration clause, in the First Contract between CNA and Trafigura expressly reserved this determination for the arbitrator to make. Second, Trafigura contends that the trial court erred when it concluded that CNA’s claims arose independently of the First Contract and therefore fell outside the scope of the First Contract’s arbitration clause. Third, Trafi-gura contends that, even if CNA’s claims fell outside the scope of the First Contract’s arbitration agreement, CNA never
Because our resolution of Trafigura’s first reason is dispositive, we do not reach Trafigura’s remaining issues.
I. Standard of Review
It is undisputed that the First Contract between CNA and Trafigura contained an arbitration agreement. At issue is whether the trial court was the proper authority to make the determination regarding whether. CNA’s claims in this suit fall within the scope of. that arbitration agreement. This determination depends on an interpretation of the parties’ contracts, which we review de novo. Schlumberger Tech. Corp. v. Baker Hughes Inc.,
II. Determining the Arbitrability of CNA’s Claims
Trafigura contends in its first issue that the trial court erred at the outset by determining the arbitrability of CNA’s claims— whether the claims fell within the scope of the arbitration agreement in the First Contract. Trafigura maintains that the arbitration clause in the First Contract expressly reserved the determination of arbi-trability of any claims to the arbitrator.
The question of arbitrability addresses which claims must be arbitrated-Southwinds Express Constr., LLC v. D.H. Griffin of Tex., Inc.,
Assuming a valid arbitration agreement exists, that agreement affects whether the trial court or the arbitrator has primary authority to determine arbitrability. See Seven Hills Commercial, LLC v. Mirabal Custom Homes, Inc.,
The parties dispute whether the First Contract’s arbitration agreement encompasses CNA’s claims against Trafigura. We first must determine whether this decision as to scope was the trial court’s to make, or if instead the parties agreed to
The arbitration agreement in the First Contract specified, in relevant part, that
all claims, disputes or differences whatsoever between the parties arising out of or in connection with this contract, including without limitation to any question regarding its existence, validity or termination, (a “Dispute”) shall be referred to arbitration in London, England, in accordance with the Arbitration Act 1996 (or any subsequent amendment or re-enactment thereof) (the “Act”).
Several of our sister courts have held that similar language evidenced a clear intent to submit arbitrability questions to the arbitrator. See Emp. Sols. McKinney, LLC v. Wilkerson, No. 05-16-00283-CV,
Here, the First Contract requires arbitration of “all claims, disputes or differences” between CNA and Trafigura that arise “out of or in connection with” that contract. The First Contract further states that “any question regarding [the contract’s] existence, validity or tenni-nation ... shall be referred to arbitration.”
One of CNA’s principal contentions is that the First Contract “was fully performed and is now over and done with;” therefore, it appears CNA is arguing (at least in part) that the First Contract has terminated. Because questions concerning the First Contract’s termination are explicitly identified as arbitrable matters, we are persuaded that the First Contract’s broad arbitration clause delegates this gateway issue to the arbitrator for determination.
The First Contract’s express incorporation of the United Kingdom’s Arbitration Act of 1996 further demonstrates the parties’ intent to place responsibility for arbi-trability determinations with the arbitrator.
A number of our sister courts have adopted a general rule that when a broad arbitration agreement exists between the parties, and when that agreement incorporates arbitration rules that specifically empower the arbitrator to decide issues of arbitrability, then the incorporation of those rules constitutes clear and unmistakable evidence of the parties’ intent to delegate arbitrability to the arbitrator. See Gilbert v. Rain & Hail Ins., No. 02-16-00277-CV,
The Fifth Circuit and other federal appellate courts have reached the same conclusion. See Petrofac, Inc. v. DynMcDermott Petroleum Operations Co.,
Although the First Contract did not incorporate the AAA rules, it did incorporate the United Kingdom’s Arbitration Act 1996. Chapter 30 of the Arbitration Act 1996, titled “Competence of tribunal to rule on its own jurisdiction,” empowers the arbitrator to decide questions of arbitrability:
(1) Unless otherwise agreed by the parties, the arbitral tribunal may rule on its own substantive jurisdiction, that is, as to—
(a) whether there is a valid arbitration agreement,
(b) ' whether the tribunal is properly
constituted, and
(c) what matters have been submitted to arbitration in accordance with the arbitration agreement.
Arbitration Act 1996, § 30 (Eng.).
CNA argues that incorporation of the Arbitration Act 1996’s rules is distinguishable from incorporation of the AAA rules, and that the majority rule discussed above should not apply. Under Rule 7(a) of the AAA Commercial Arbitration Rules, “The arbitrator shall have the power to rule on his or her own jurisdiction, including any objections with respect to the existence, scope, or validity of the arbitration agreement or to the arbitrability of any claim or counterclaim.” See Am. Arbitration Ass’n, Commercial Arbitration Rules & Mediation Procedures, R-7: Jurisdiction (eff. Oct. 1, 2013), available at https://www.adr. org/sites/defaulVfiles/Commercial% 20Rules.pdf. CNA contends that Rule 7(a)’s use of “shall” arguably “requires questions of arbitrability to be decided by an arbitrator.” On the other hand, CNA contends that the Arbitration Act 1996 “merely states that arbitrators in any given, proceeding may rule on their own jurisdiction.”
We find persuasive the above-cited Tex-as and federal cases holding that express incorporation of the AAA rules constitutes clear and unmistakable evidence of the parties’ intent to delegate issues of arbitra-bility to the arbitrator. Applying the reasoning of those cases here, we .conclude that there is clear and unmistakable evidence that the parties intended for the arbitrator to decide arbitrability based on (1) the parties’ express incorporation of the Arbitration Act 1996, in combination with (2) a broad arbitration- agreement sending to the arbitrator “all claims, disputes or • differences whatsoever between the parties arising out of or in connection with this contract, including without limitation to any question regarding its existence, validity or termination.”
Finally, CNA argues that the majority rule should not apply because the arbitration agreement provides for certain non-arbitration remedies. Specifically, the agreement provides:
Notwithstanding the provisions of this [arbitration] clause, [Trafigura] shall have the right to commence and pursue proceedings for interim or conservatory relief against [CNA] in any court in any jurisdiction and the commencement and pursuit of such proceedings in any one court or jurisdiction shall not preclude [Trafigura] commencing . or pursuing proceedings in any other court or jurisdiction (whether concurrently or not) if and to the extent permitted by the applicable law.
Notwithstanding the foregoing arbitration provisions, [Trafigura] shall have the option of referring any Dispute to the High Court of Justice in London, England, or any other court having jurisdiction over the Dispute (the “Court”).
In support of this proposition, CNA relies on an opinion from the Delaware Supreme Court. See James & Jackson, LLC v. Willie Gary, LLC,
Conclusion
We conclude that the trial court erred by determining whether CNA’s claims fell within the scope of the First Contract’s arbitration agreement—a determination the parties had reserved for the arbitrator. Accordingly, we reverse the trial court’s order denying Trafigura’s motion to compel'arbitration, and we remand this case for proceedings consistent with this opinion.
Notes
, CNA obtáined a default judgment against Jace on May 25, 2015, for approximately $3.2 million.
. According to the First Contract and CNA’s pleadings, the iron ore was loaded onto a vessel in Mexico and offloaded in China.
. In other cases, our court and several sister courts have recognized the majority rule, but found that it did not apply in the appeals before them because there was other evidence suggesting that the parties did not intend to refer all disputes to arbitration. See, e.g., Lucchese Boot Co. v. Solano,
