MEMORANDUM OPINION
Denying the Defendant’s Motion to Dismiss for Failure to State a Claim for Which Relief Can be Granted; Denying the Plaintiff’s Motion for a Preliminary Injunction; Denying as Moot the Plaintiff’s Motion for Leave to File Supplemental Information
I. INTRODUCTION
The plaintiff, Toxco Inc., operates a waste disposal facility in Tennessee. It has brought this action pursuant to the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 553
et seq.,
and the due process clause of the Fifth Amendment, challenging the Department of Energy’s (“DOE”) withdrawal of its consent to a subcontract entered into by the plaintiff. This matter is now before the court on the plaintiffs motion for a preliminary injunction and the defendant’s motion to dismiss for failure to state a claim. The plaintiff seeks a preliminary injunction requiring the DOE to reinstate its consent to the plaintiff serving as a subcontractor on a DOE environmental clean-up project in Niskayuna, New York. The defendant opposes the entry of a preliminary injunction and has filed a Rule 12(b)(6) motion to dismiss. Because the plaintiff has failed to demonstrate that it will suffer irreparable harm
II. BACKGROUND
A. Factual Background
Until 2000, the DOE operated a research facility known as the Separation Process Research Unit (“SPRU”) in Niskayuna, New York, which was used for research on the separation of atomic isotopes. Pl.’s Mot. for a Prelim. Inj. (“Pl.’s Mot.”) at 3. Although the SPRU facility has been largely unused since 2000, the research performed there resulted in radioactive contamination of the facilities and the surrounding soil. Id. In October 2004, the DOE engaged Accelerated Remediation Company (“ARC”) to return the site to a usable condition. Id.; Def.’s Consolidated Opp’n to Pl.’s Prelim. Inj. Mot. & Mot. to Dismiss for Failure to State a Claim (“Def.’s Mot.”) at 3. The work performed by ARC was to include the removal of contaminated soils, building debris and other waste materials containing low levels of radioactive contamination and disposing of these materials at qualified locations. Pl.’s Mot. at 3.
In September 2007, the DOE issued a task order to ARC for the rehabilitation of the lower level railbed area and the lower level parking lot of the SPRU facility (“the SP-15 Task Order”). Def.’s Mot. at 3. The SP-15 Task Order made ARC responsible for disposing of any waste generated by the remediation project and authorized ARC to use “existing contractual instruments between the Federal Government and waste disposal facilities ... when disposing of waste unless [ARC could] obtain more favorable cost arrangements.” Id., Decl. of Marilyn Long (“Long Decl.”), Ex. 1 at C-12.
In February 2009, the American Recovery and Reinvestment Act provided $37 million of funding to DOE to accelerate the rehabilitation of the SPRU site. Pl.’s Mot. at 4. As a result, in May 2009, ARC issued a request for subcontractors to submit proposals for the disposal of waste generated through work on the SP-15 Task Order containing low levels of radioactive contamination. Id. The plaintiff submitted a proposal in June 2009, and ARC determined that the plaintiff was the lowest-cost, qualifying bidder. Id.
The federal acquisition regulations in force at the time required agency consent for certain subcontracts entered into by a contractor without an approved purchasing system. Def.’s Mot. at 12-13. Furthermore, DOE Order 435.1 required a contractor to obtain an exemption from the DOE before disposing of radioactive waste
On August 11, 2009, the DOE provided its formal consent to the subcontract in a letter from Marilyn Long, a DOE contracting officer. See id., Aff. of David Eaker (“Eaker Aff.”), Ex. 9. The same day, the plaintiff and ARC executed a subcontract for the disposal of low-level radioactive material pursuant to the SP-15 Task Order. See generally Eaker Aff., Ex. 10 (“Toxco Purchase Order”). The subcontract expressly incorporated several contractual provisions set forth in federal acquisition regulations, including Federal Acquisition Regulation (“FAR”) § 52.249-2. See id. at 3. That regulation contained a contractual provision entitled “Termination for Convenience of the Government,” which provided, in relevant part, that “[t]he Government may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government’s interest.” 48 C.F.R. § 52.249-2(a). The provision further specified that upon the delivery of the government’s notice of termination to the prime contractor, the prime contractor shall, “[w]ith approval or ratification to the extent required by the Contracting Officer, settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts; the approval or ratification will be final for purposes of this clause.” Id. § 52.249-2(b)(5).
After executing the subcontract, the plaintiff began to undertake its processing and disposal duties as set forth in the agreement. Pl.’s Mot. at 6. Yet on August 19, 2009, eight days after providing written consent to the plaintiffs subcontract, the DOE issued a notice to ARC that it had rescinded its consent to the plaintiffs subcontract. Eaker Aff., Ex. 13 at 1. The notice contained no explanation for the DOE’s withdrawal of consent. See id. The withdrawal forced ARC to terminate its subcontract with the plaintiff. Pl.’s Mot. at 6-7.
B. Procedural History
The plaintiff commenced this action in October 2009, asserting that the DOE’s withdrawal of consent constituted an arbitrary and capricious agency action in violation of the APA, and deprived it of property without due process of law in violation of the Fifth Amendment. See generally Compl. The plaintiff also moved for a preliminary injunction requiring the DOE to rescind its withdrawal and reinstate its consent to the plaintiffs subcontract with ARC. See generally Pl.’s Mot.
The defendant responded by filing a consolidated opposition to the plaintiffs motion for a preliminary injunction and a Rule 12(b)(6) motion to dismiss for failure to state a claim. See generally Def.’s Mot. In its motion to dismiss, the defendant argues that the plaintiffs APA claims must be dismissed because the DOE’s decision to withdraw its consent was a matter committed to agency discretion by law and because the plaintiff has an alternative adequate remedy to APA review in the form of a breach of contract action against ARC. Id. at 12-14. Furthermore, the defendant argues that the plaintiffs due process claim must be dismissed because the subcontract did not give rise to a protectable property interest for Fifth Amendment purposes. Id. at 14-15.
On November 9, 2009, the plaintiff filed a document entitled “Reply Memorandum in Support of Toxco’s Motion for Preliminary Injunction.”
See generally
Pl.’s Reply. The reply memorandum made no
The plaintiff responded to the show cause order on December 4, 2009. See generally Pl.’s Response to Dec. 1, 2009 Order (“Pl.’s Resp.”). In its response, the plaintiff asserted that its reply memorandum in support of its motion for a preliminary injunction had “addressed the Defendants’ arguments, including substantively the arguments underlying the motion to dismiss.” 2 Id. at 2. The plaintiff proceeded to “summarize” its responses to the arguments made by the defendant in its motion to dismiss. Id. As noted below, the “summary” provided responses to certain arguments raised in the defendant’s motion that were not addressed in the plaintiffs reply memorandum. See generally id.
On December 7, 2009, the court advised the parties that it would treat the plaintiffs response to the order to show cause and its reply memorandum in support of its motion for a preliminary injunction as its opposition to the defendant’s motion to dismiss. Order (Dec. 7, 2009). The defendant subsequently filed a reply in support of its motion to dismiss. See generally Def.’s Reply. As the defendant’s motion to dismiss and the plaintiffs motion for a preliminary injunction are now ripe for disposition, the court turns to the applicabie legal standards and the parties’ arguments.
III. ANALYSIS
A. The Court Denies the Defendant’s Rule 12(b)(6) Motion to Dismiss
1. Legal Standard for Rule 12(b)(6) Motion to Dismiss
A Rule 12(b)(6) motion to dismiss tests the legal sufficiency of a complaint.
Browning v. Clinton,
Yet, “[t]o survive a motion to dismiss, a complaint must contain sufficient factual
In resolving a Rule 12(b)(6) motion, the court must treat the complaint’s factual allegations — including mixed questions of law and fact — as true and draw all reasonable inferences therefrom in the plaintiffs favor.
Holy Land Found, for Relief & Dev. v. Ashcroft,
2. The Court Denies the Defendant’s Motion to Dismiss the Plaintiffs APA Claim
a. The Defendant Has Not Demonstrated that the DOE’s Withdrawal of Consent Was a Matter Committed to Agency Discretion by Law
The defendant contends that the DOE’s decision to withdraw consent to the plaintiffs subcontract is unreviewable under the APA because it was a matter committed to agency discretion by law. Def.’s Mot. at 12-13; Def.’s Reply at 2-4. According to the defendant, the regulations governing ARC’s request for consent to the plaintiffs subcontract provide the DOE unfettered discretion to grant, withhold or withdraw consent to subcontracts like the one at issue here. Def.’s Mot. at 12-13; Def.’s Reply at 2-3. Because the APA does not apply to agency actions “committed to agency discretion by law,” 5 U.S.C. § 701(a)(2), the defendant contends that the plaintiffs APA claim should be dismissed, Def.’s Mot. at 12-13; Def.’s Reply at 2-3.
The plaintiff does not address the defendant’s § 701(a)(2) argument in its reply in support of its motion for a preliminary injunction. See generally Pl.’s Reply. Although the plaintiff does acknowledge the argument in its response to the order to show cause, it responds merely by stating that “discretion does not equal fickleness, but must reflect appropriate, non-arbitrary decision-making.” PL’s Resp. at 4.
The APA “embodies the basic presumption of judicial review to one ‘suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute.’ ”
Abbott Labs. v. Gardner,
Statutory standards need not be drawn with a high degree of specificity to fall outside the narrow bounds of § 701(a)(2).
See Robbins v. Reagan,
[e]ven where there are no clear statutory guidelines, courts often are still able to discern from the statutory scheme a congressional intention to pursue a general goal. If the agency action is found not to be reasonably consistent with this goal, then the courts must invalidate it. The mere fact that a statute grants broad discretion to an agency does not render the agency’s decisions completely nonreviewable under the “committed to agency discretion by law” exception unless the statutory scheme, taken together with other relevant materials, provides absolutely no guidance as to how that discretion is to be exercised.
Id. (internal citations omitted).
These authorities make clear that when assessing whether a matter is committed to agency discretion for purposes of § 701(a)(2), the court must undertake an examination of the statutory scheme governing the agency’s exercise of authority.
See Webster v. Doe,
Although the defendant argues that its own regulations and guidelines place no limitations on its discretion to grant, withhold or withdraw consent to subcontracts like the one at issue, it has not identified— much less carefully examined — the legislative enactments pursuant to which the DOE granted, and then rescinded, its consent to the plaintiffs subcontract.
See
Def.’s Mot. at 12-13; Def.’s Reply at 2-4. Accordingly, the defendant has not demonstrated that “the
statutory
scheme, taken together with other relevant materials, provides absolutely no guidance as to how that discretion is to be exercised.”
3
Robbins,
b. The Defendant Has Not Demonstrated That the Plaintiff Possesses an Alternative Adequate Remedy to Judicial Review
The defendant contends that the plaintiffs APA claim must be dismissed because the APA does not provide for judicial review of agency action unless there is no other adequate remedy available to the aggrieved party. Def.’s Mot. at 13. The defendant asserts that because the plaintiff can pursue a breach of contract claim against ARC or seek relief from ARC through the “termination for
“Review under the APA is ... limited to ‘final agency action for which there is no other adequate remedy in a court.’ ”
Fund for Animals, Inc. v. U.S. Bureau of Land Mgmt.,
It is not clear, at least at this stage of the litigation, that the “termination for convenience” provision of the subcontract provides the plaintiff an alternative adequate remedy so as to preclude review under the APA. As an initial matter, there remains some question as to the applicability of the “termination for convenience”
The court reaches a similar conclusion with respect to the availability of a breach of contract action against ARC.
6
According to the defendant, the plaintiff “offers no explanation for why it would not be able to assert a claim against ARC for damages arising out of the termination of the contract, leaving ARC to in turn seek redress from the Government if ARC should so determine necessary.” Def.’s Reply at 5. The defendant appears to be suggesting that the plaintiff could obtain adequate relief through a “pass-through” suit, in which “a prime contractor ... assert[s] against the government a claim for harm caused by the government to a subcontractor where the subcontractor could hold the prime contractor liable for that harm.”
Int'l Tech. Corp. v. Winter,
In its cursory discussion of the matter, however, the defendant fails to demonstrate that the plaintiff could obtain an alternative adequate remedy through a claim against ARC, or even that such a claim is available to the plaintiff.
See
Def.’s Mot. at 14; Def.’s Reply at 4-5. Indeed, the defendant offers no response to the plaintiffs assertion that “ARC cannot be sued under a breach of contract claim because ARC is not responsible for DOE’s withdrawal of consent to the Toxco subcontract.”
7
Pl.’s Resp. at 5;
see
Def.’s Reply at 4-5. Because it is the defendant has not met its burden of showing by clear and convincing evidence that § 704 bars the plaintiffs APA claim,
see Garcia,
3. The Court Denies the Defendant’s Motion to Dismiss the Plaintiffs Due Process Claim
The defendant asserts that the plaintiffs due process claim must be dismissed because the alleged property inter
To state a claim for deprivation of property without due process of law, the plaintiff must possess a property interest that triggers the Fifth Amendment’s due process protections.
C & E Sens., Inc. of Wash. v. D.C. Water & Sewer Auth.,
As noted, the defendant suggests that the plaintiff did not have a protectable property interest for Fifth Amendment purposes because the defendant was not a party to the subcontract between ARC and the plaintiff.
See
Def.’s Mot. at 15. The defendant, however, points to no authority indicating that only government contracts are entitled to due process protections.
See id.;
Def.’s Reply at 6-8. To the contrary, numerous courts have held that contracts between private parties may give rise to property interests sufficient to trigger Fifth Amendment due process protections.
See Greene v. McElroy,
It is, of course, not the case that every contract triggers due process protections.
See, e.g., Unger v. Nat’l Residents Matching Program,
1. Legal Standard for a Preliminary Injunction
This court may issue interim injunctive relief only when the movant demonstrates “[1] that he is likely to succeed on the merits, [2] that he is likely to suffer irreparable harm in the absence of preliminary relief, [3] that the balance of equities tips in his favor, and [4] that an injunction is in the public interest.”
Winter v. Natural Res. Def. Council, Inc.,
The other critical factor in the injunctive relief analysis is irreparable injury. A movant must “demonstrate that irreparable injury is
likely
in the absence of an injunction.”
Winter,
consider the effect on each party of the granting or withholding of the requested relief.”
Amoco Prod. Co. v. Gambell,
As an extraordinary remedy, courts should grant such relief sparingly.
Mazurek v. Armstrong,
2. The Plaintiff Has Failed to Demonstrate That It Will Suffer Irreparable Harm Absent Interim Injunctive Relief
The plaintiff contends that in the small, specialized field of hazardous materials disposal, the DOE’s withdrawal of consent “immediately raises questions within the industry — and most importantly, among Toxco’s customers — about the continued ability of Toxco to store and dispose of wastes.” Pl.’s Mot. at 12. The plaintiff asserts that the industry will assume that safety or responsibility concerns must have led to the cancellation of the subcontract, particularly given the DOE’s
The defendant counters that the plaintiffs complaints of reputational harm are too speculative to establish irreparable harm. Def.’s Mot. at 23. Furthermore, the defendant argues that the plaintiff has neither demonstrated that the withdrawal of consent from one project would bar the plaintiff from working on the North Field or any other project, nor established that the reversal of the DOE’s withdrawal of consent would result in the plaintiffs selection for the North Field" project. Id at 21-22. Finally, the defendant asserts that the plaintiffs complaints of lost business are unaccompanied by a claim of any imminent threat to the survival of its business, as necessary to give rise to irreparable harm. Id at 22.
Turning first to the plaintiffs claims of reputational harm, it is well-established that “reputational injury can be used to establish irreparable harm in certain circumstances.”
Trudeau v. Fed. Trade Comm’n,
The plaintiffs claims of reputational harm are based solely on the uncorroborated and speculative assertions made in an affidavit of David Eaker, one of the plaintiffs vice-presidents. See Eaker Aff. ¶¶ 33-38. Although Eaker asserts that “it is the logical and inevitable assumption” that the DOE’s withdrawal of consent will raise concerns about the plaintiffs operations, id. ¶ 34, and that the absence of an explanation for the DOE’s action will lead to “the assumption, within the industry, that DOE knows something they aren’t telling about Toxco,” id. ¶ 35, he offers nothing to substantiate his conjecture about what the industry will assume, see generally id. Likewise, although Eaker states that “[i]ndications of such [reputational] damage have already come to Toxco’s attention,” id. ¶ 35, he fails to specify what these “indications” are or the manner in which they indicate that the plaintiffs reputation has been harmed, see generally id.
Given the numerous factors that could have resulted in the DOE’s withdrawal of consent, the plaintiff has simply not established that the industry will inevitably assume that the withdrawal of consent reflects some deficiency in the plaintiffs operations. The plaintiff does not assert that it has lost or will lose any potential or existing clients because of the withdrawal of consent and, in fact, does not
As for the plaintiffs assertions of economic harm, the court notes that plaintiff has offered little to support its claim that the DOE’s withdrawal of the consent threatens its participation in any other projects. See PL’s Mot. at 12-13; PL’s Reply at 12. Like the plaintiffs allegations of reputational injury, the plaintiffs contention that the DOE’s withdrawal of consent precluded it from obtaining work on the North Field project is based solely on unsupported and conclusory assertions contained in the Eaker affidavit. See Eaker Aff. ¶ 36 (stating, “I understand that ARC will continue [to] use [another company] as a waste disposal subcontractor [on the North Field project], because DOE had withdrawn consent to use Toxco”); id. ¶ 37 (stating, “Toxco is informed and believes that ARC would select it to act as subcontractor for the North Field, if DOE will permit it to do so”). Indeed, the plaintiff itself acknowledges that it “has not been debarred from all government or DOE contracting,” PL’s Mot. at 9 n. 3 (emphasis removed), and that the DOE continues to allow the plaintiff to serve its disposal needs on other projects, id. at 8.
Moreover, even if the DOE’s withdrawal did cause the plaintiff to lose the North Field project, the plaintiff has not shown that this economic loss, even if irretrievable and even when coupled with the losses resulting from the termination of the subcontract itself, is sufficiently severe so as to constitute irreparable harm. “To demonstrate irreparable injury, a plaintiff must show that it will suffer harm that is ‘more than simply irretrievable; it must also be serious in terms of its effect on the plaintiff.’ ”
Hi-Tech Pharmacal Co. v. U.S. Food & Drug Admin.,
In this case, the plaintiff has offered no indication of the magnitude of economic harm it has suffered or will suffer as a result of the DOE’s withdrawal of consent. See Pl.’s Mot. at 12-14; Pl.’s Reply at 12. The plaintiff has not provided the court with any measure of the income it has lost or will lose as a result of the termination of the subcontract or the denial of the North Field project. See Pl.’s Mot. at 12-14; Pl.’s Reply at 12. Nor has the plaintiff offered any indication of what effect these losses have had or will have on its business operations. See Pl.’s Mot. at 12-14; Pl.’s Reply at 12. Accordingly, the plaintiff has not established that its economic losses are sufficiently severe to constitute irreparable harm.
In sum, the plaintiffs claims of reputational and economic harm are insufficient to support a finding of irreparable harm. This failure, standing alone, is sufficient to warrant denial of the plaintiffs motion for a preliminary injunction.
See Chaplaincy of Full Gospel Churches v. England,
3. The Remaining Factors Do Not Warrant Awarding Preliminary Injunctive Relief
Because the plaintiff has not demonstrated that it would suffer irreparable harm absent a preliminary injunction, the court will not undertake an extensive analysis of the remaining factors relevant to this analysis.
See Chaplaincy of Full Gospel Churches,
The court notes, however, that the plaintiff has also failed to demonstrate a substantial likelihood of success on the merits. Although, as previously discussed, the court cannot conclude at this juncture that § 701(a)(2) and § 704 bar the plaintiffs APA claims,
see supra
Part III.A.2, there remains significant uncertainty as to whether the plaintiff is entitled to judicial review under the APA, given the potential availability of alternative adequate remedies and the absence of any judicially manageable standards for reviewing the DOE’s withdrawal of consent,
9
see RCM Techs.,
The court has also considered the remaining factors of the preliminary injunction analysis and concludes that neither factor weighs strongly in favor of granting such relief. As for the balance of the equities, the defendant has credibly asserted that both it and the public will be harmed by the entry of a preliminary injunction because such relief would disrupt the DOE’s ongoing efforts to decontaminate the SPRU facility. See Def.’s Mot. at 24. Thus, the court concludes that the plaintiff has failed to establish its entitlement to preliminary injunctive relief and denies the plaintiffs motion for a preliminary injunction.
IV. CONCLUSION
For the foregoing reasons, the court denies the defendant’s motion to dismiss and denies the plaintiffs motion for a preliminary injunction. An Order consistent with this Memorandum Opinion is separately and contemporaneously issued this 20th day of July, 2010.
Notes
. The plaintiff has also filed a motion for leave to file supplemental information in opposition to the defendant’s motion to dismiss. Because, as discussed below, the court denies the defendant’s motion to dismiss without consideration of this supplemental information, the court denies as moot the plaintiff's motion for leave to file.
See Nat’l Credit Counseling Servs., Inc. v. United States,
. The plaintiff asserted that “its Reply Memorandum was styled as a reply to the motion to dismiss and to the opposition to the preliminary injunction,” Pl.'s Resp. at 2 n. 1, despite the fact that the reply memorandum was ti-lied “Reply Memorandum in Support of Toxco's Motion for Preliminary Injunction” and made no explicit reference to the defendant's motion to dismiss, see generally Pl.’s Reply.
. The court also notes that the plaintiff's APA claim "does not fall into one of the narrow categories that usually satisfies the strictures of subsection 701(a)(2).”
Cody v. Cox,
. As noted, the "termination for convenience” clause incorporated into the subcontract requires ARC to "settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts; the approval or ratification will be final for purposes of this clause.” See Toxco Purchase Order at 3 (incorporating by reference 48 C.F.R. § 52.249-2).
. Although a plaintiff must satisfy the requirements of 5 U.S.C. § 704 to have a valid cause of action under the APA, the court’s jurisdiction does not hinge on the section.
Trudeau v. Fed. Trade Comm’n,
. It is undisputed that the plaintiff cannot pursue a breach of contract action directly against the defendant because it is not in contractual privity with the defendant. See Def.'s Reply at 5; Pl.’s Resp. at 6.
. It should be noted, however, that the plaintiff points to no legal authority or provisions in the subcontract substantiating its assertion that it has no contractual claim against ARC. See Pl.’s Resp. at 5-6.
.
Lockheed Martin Corp. v. United States,
.
For instance, although the defendant failed to address the statutory framework as required to demonstrate that the DOE's action was committed to agency discretion by law, the applicable regulations indicate that the DOE’s consent was merely permissive rather than mandatory.
See
DOE Order 435.1 (providing that exemptions authorizing the use of
