MEMORANDUM OPINION
Granting the Defendants’ Motion to Dismiss or, In the Alternative, for Summary Judgment; Granting the Defendants’ Motion to Strike the Plaintiff’s Sur-Reply
I. INTRODUCTION
This case is before the court on the defendants’ motion to dismiss as moot or, in the alternative, for summary judgment. The plaintiff, Toxco, Inc., commenced this action against the Department of Energy and the Secretary of the Department of Energy, alleging that the defendants’ actions violated the Administrative Procedure Act (“APA”) and the Due Process Clause of the Fifth Amendment. The defendants move to dismiss these claims pursuant to Federal Rule of Civil Procedure 12(b)(1), alleging that the court lacks jurisdiction because the plaintiffs claims are moot. In the alternative, the defendants move for summary judgment under Rule 56. Because the plaintiffs APA claim is moot, the court grants the defendants’ motion to dismiss as to that claim. With respect to the plaintiffs remaining Due Process claim, the court grants the defendant’s motion for summary judgment.
II. BACKGROUND
A. Factual Background
The Department of Energy (“DOE”) oversees the disposal of radioactive waste at nuclear waste facilities across the country. See 42 U.S.C. § 7133(a)(8)(A)-(E). One such facility is the Separations Process Research Unit (“SPRU”), which operated from 1950 to 1953 as a pilot plant to research the chemical extraction of uranium and plutonium from irradiated uranium. A.R. at 69. 1 These operations contaminated the SPRU facility and the surrounding environment with radioactive material, resulting in the need to remediate the site. Id.
In October 2004, the DOE awarded a contract for several waste disposal operations to Accelerated Remediation Company (“ARC”), with individual projects to be specified in task orders. See id. at 1-62. The contract permitted ARC to subcontract with other entities, provided that the DOE formally consented to each individual subcontract. Id. at 47 (incorporating by reference 48 C.F.R. § 52.244-2, which requires an agency’s Contracting Officer to consent before a contractor may enter into a subcontract). In September 2007, the DOE issued Task Order No. DE-AT3007CC60013, SP15 (“Task Order SP15”), requiring ARC to engage in environmental remediation of approximately fifteen acres in the SPRU land areas. See generally A.R. at 63-105. Specifically, Task Order SP15 required the cleanup of radioactively and chemically contaminated soil from two areas at SPRU: the Lower Level Railbed and the Lower Level Parking Lot. Id. at 69.
In keeping with the terms of the DOE-ARC contract, in the summer of 2008 ARC subcontracted with EnergySolutions, a Utah company, to complete the waste disposal work under Task Order SP15. See generally id. at 346-48. Later that summer, ARC sought and received the DOE’s permission to exit its subcontract with En eYgySolutions as part of a cost-savings *4 initiative. See generally id. at 349-51, 401-05; see Defs.’ Mot. to Dismiss or, in the Alternative, for Summ. J. (“Defs.’ Mot.”) at 8-9. ARC then solicited bids from other subcontractors that wished to engage in the Task Order SP15 remediation work at SPRU. A.R. at 402. In June 2009, Toxco, Inc. (“Toxco” or “the plaintiff’), a Tennessee company, submitted a bid to perform the Task Order SP15 work. See generally id. at 397-411. Pursuant to federal acquisition regulations and DOE guidelines, ARC required the DOE’s consent before it could enter into a subcontract with Toxco. Id. at 47. On August 11, 2009, the DOE issued a letter giving its formal consent to the subcontract. Id. at 450 (“Consent Order”). The Consent Order included the following provision:
This consent shall in no way relieve the prime contractor of any obligations or responsibilities it may otherwise have under the contract or under law, shall neither create any obligation of the Government to, nor privity of contract with, the subcontractor or vendors, and shall be without prejudice to any right or claim of the Government under the prime contract. This consent does not constitute a determination as to the acceptability of the subcontract or the allowability of costs.
Id.
On August 12, 2009, having received the DOE’s formal consent, ARC entered into a Purchase Order subcontract for the Task Order SP15 remediation work with Toxco. See generally id. at 451-63. The period of performance for the subcontract ran through December 31, 2009. Id. at 452. The subcontract also incorporated by reference a federal regulation titled “Termination for Convenience of the Government,” which allowed the government to “terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government’s interest.” See id. at 454.
A week later, on August 19, 2009, the DOE reversed course and withdrew its consent for the ARC-Toxco subcontract. See id. at 498-500. Swiftly thereafter, ARC cancelled its subcontract with Toxco. Id. at 501-03. ARC subsequently re-eontracted with EnergySolutions for completion of the remainder of Task Order SP15’s remediation project at SPRU. Def.’s Mot. at 12. By June 12, 2010, Ener gySolutions had completed the work contemplated by Task Order SP15. Id.
B. Procedural History
The plaintiff commenced this action in October 2009, asserting that the DOE’s withdrawal of consent to the ARC-Toxco subcontract was both an arbitrary and capricious agency action in violation of the APA and a deprivation of property in violation of the Due Process Clause of the Fifth Amendment.
See generally
Compl. Upon filing its complaint, the plaintiff also moved for a preliminary injunction requiring the DOE to reinstate its consent to the subcontract so that it could continue with work on the subcontract.
See generally
PL’s Mot. for Preliminary Injunction. The defendants moved to dismiss the complaint.
See generally
Defs.’ Mot. to Dismiss. In July 2010, the court issued a memorandum opinion denying the defendants’ motion to dismiss and denying the plaintiffs motion for a preliminary injunction.
See generally
Mem. Op.,
In September 2010, the defendants filed a second motion to dismiss under Rule 12(b)(1), asserting that the plaintiffs claims are moot. See Defs.’ Mot. at 15-20. In the alternative, the defendants move for summary judgment on all of the plaintiffs claims. Id. at 20-30. With the defendants’ motion now ripe for review, the *5 court turns to the applicable legal standards and the parties’ arguments. 2
III. ANALYSIS
A. The Court Grants the Defendants’ Rule 12(b)(1) Motion to Dismiss the Plaintiffs APA Claim for Mootness
1. Legal Standard for a Motion to Dismiss for Mootness
Under Rule 12(b)(1), a party may move to dismiss a case on grounds of mootness.
Comm, in Solidarity with People of El Sal. v. Sessions,
Courts must evaluate mootness “through all stages” of the litigation in order to ensure that a live controversy remains.
21st Century Telesis Joint Venture v. F.C.C.,
A case is moot when “the issues presented are no longer live or the parties lack a legally cognizable interest in the outcome.”
City of Erie,
2. The Plaintiffs APA Claim Is Moot Because the Work Contemplated by the ARC-Toxco Subcontract Has Been Completed
The defendants argue that the plaintiffs claim is moot because the remediation work contemplated by the ARC-Toxco subcontract has now been fully performed by a different subcontractor. Defs.’ Mot. at 17-18. The plaintiff does not contest the fact that the subcontract has been completed, but rather asks the court to require that the defendants hire the plaintiff as a contractor for future remediation work at the SPRU site. See PL’s Opp’n at 4-5. More specifically, the plaintiff argues that there may be additional opportunities for Toxco to obtain work at the SPRU site, as cleanup work is not expected to conclude until the end of 2011. Id. In addition, the plaintiff responds that this court could still grant meaningful relief by rendering a declaratory judgment against the defendants. Id. at 4. 3
This Circuit has held that a claim seeking specific performance of a contract is moot if the services contemplated by the contract have already been rendered.
Columbian Rope Co. v. West,
Because the subcontract work has been completed, the court cannot order specific performance of the ARC-Toxco subcontract. 4 Id. at 1316-17. Because time has mooted the underlying action, moreover, declaratory relief is similarly unavailable. Id. at 1317 n. 3.
3. The Plaintiffs Claims Are Not Capable of Repetition, Yet Evading Review
The plaintiff argues that its action is reviewable because its claims are capable of repetition and evade judicial review. Pl.’s Opp’n at 5. More specifically, the plaintiff argues that the challenged action was too short in its duration to be fully litigated, and that there is a reasonable expectation that Toxco could be subject to the same action in the future. Id. The plaintiff contends that waste disposal continues at the SPRU facility, and it is therefore reasonable that Toxco would submit a future bid for an additional waste disposal contract. Id. at 6. The defendants reply that these speculative assertions fail to establish a reasonable expectation that the same type of controversy will arise again. Defs.’ Reply at 5.
An action that is otherwise moot may be reviewed if it is “capable of repetition, yet evading review.”
S. Pae. Terminal Co. v. Interstate Commerce Comm’n,
Although the plaintiff contends it is reasonable that it will submit a bid for future waste disposal work at the SPRU facility and that it might suffer the same injury, the plaintiffs allegation rests upon a precarious stack of contingencies. In order for a “recurrent identical agency action[ ]” to occur,
Pub. Utils. Comm’n of Cal.,
B. The Court Grants Summary Judgment for the Defendants on the Plaintiffs Due Process Claims
1. Legal Standard for Summary Judgment
Summary judgment is appropriate when the pleadings and evidence show “that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a);
see also Celotex Corp. v. Catrett,
In ruling on a motion for summary judgment, the court must draw all justifiable inferences in the nonmoving party’s favor and accept the nonmoving party’s evidence as true.
Anderson,
The nonmoving party may defeat summary judgment through factual representations made in a sworn affidavit if he “supports] his allegations ... with facts in the record,”
Greene v. Dalton,
2. The Plaintiff Holds No Property Interest Under the Due Process Clause
The defendants contend that the plaintiff’s subcontract does not trigger any property interest under the Due Process Clause. Defs.’ Mot. at 28. The defendants argue that the ARC-Toxco subcontract did not obligate, guarantee or imply that any services would be purchased. Id. They further note that the subcontract “expressly reserved the ability of the Government to terminate performance of work in whole or in part.” Id. The plaintiff *9 counters that the ARC-Toxeo subcontract created a valid property interest that the government abrogated without affording it any due process, thus violating the Fifth Amendment. 5 Pl.’s Opp’n at 15.
The Due Process Clause of the Fifth Amendment prevents the federal government from depriving any person of property without due process of law. U.S. Const, amend. V. To state a claim for deprivation of property without due process of law, the plaintiff must possess a property interest that triggers the Fifth Amendment’s due process protections.
C & E Servs., Inc. of Wash. v. D.C. Water & Sewer Auth.,
In due process cases that arise out of contracts with the government, courts require that a claimant show a “legitimate claim of entitlement” to some benefit that is protected by independent state-law rules, relevant contractual language and applicable federal regulations.
C & E,
Here, the government’s Consent Order emphasized that the defendant had not committed itself to any contractual obligations towards Toxco, stating that its consent “shall neither create any obligation of the Government to, nor privity of contract with, the subcontractor or vendors.” A.R. at 450. The language of the Consent Order expressly disclaims any notion that the government committed itself to purchasing any services under the subcontract. The Consent Order, therefore, did not create an “understanding[ ]” between the parties that “secure[d] certain benefits and that supported] claims of entitlement to those benefits.”
Roth,
Moreover, the ARC-Toxco subcontract did not impose any limitations on the defendant’s ability to withdraw its consent to the subcontract. The subcontract incorporated by reference a federal regulation titled “Termination for Convenience of the Government,” which permitted the defendant to “terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government’s interest.”
See
A.R. at 454 (incorporating 48 C.F.R. § 52.249-2). This federal regulation in no way limits the circumstances in which the government may withdraw its consent to the subcontract. Rather, the applicable federal regulations vested the government with the unfettered discretion to withdraw its consent for the subcontract.
See
48 C.F.R. § 52.249-2(b)(5). These facts strongly support the conclusion that the defendant was not constitutionally bound to preserve any benefits created by the ARC-Toxco subcontract.
See Roth,
IY. CONCLUSION
For the foregoing reasons, the court grants the defendants’ motion. An Order consistent with this Memorandum Opinion *11 is separately and contemporaneously issued this 11th day of August, 2011.
Notes
. Citations to "A.R.'' refer to the Administrative Record.
. The plaintiff filed a sur-reply without first seeking leave of the court.
See generally
PL's Reply Memorandum. The defendants moved to strike the sur-reply.
See generally
Defs.’ Mot. to Strike. In response, the plaintiff sought leave of the court to file its sur-reply.
See generally
Pl.’s Opp’n to Defs.’ Mot. to Strike. There is no automatic right to file a sur-reply in the Federal Rules of Civil Procedure or in the Local Rules of this Court.
Amobi v. D.C. Dep’t of Corr.,
. The plaintiff also requests a "financial award[] to cure the contractual deficiency” as relief for the alleged APA violation. PL’s Opp'n at 4. The APA, however, only allows courts to grant equitable or declaratory relief.
See
5 U.S.C. § 702;
Hubbard v. Adm’r, Envtl. Prot. Agency.,
. The plaintiff also asks the court to order performance of future remediation work at the SPRU site. PL's Opp’n at 4. Enjoining performance of an existing contract is an extraordinary remedy that is granted only in exceptional circumstances. See, e.g., Kakaes v. George Washington Univ., 790 A.2d 581, 584 (D.C.2002). Here, the plaintiff asks the court to fashion an entirely new contract out of whole cloth. See Pl.’s Opp'n at 4. Enjoining performance of a contract that does not yet exist is, to the court’s knowledge, unheard of. Because the court is unwilling to fashion such unprecedented relief, the court denies the plaintiff’s request.
. This issue is appropriate for resolution on summary judgment because it turns on questions that are legal, not factual, in nature.
See Empresa Cubana Exportadora de Alimentos y Productos Varios v. U.S. Dep't of Treasury,
. Courts have analyzed due process claims that arise from contracts for the provision of public services within the framework developed in cases involving contracts for personal employment with the government.
See, e.g., C & E Servs.,
