The plaintiff, a locomotive engineer upon a passenger train of the defendant at the time of his injury, brought suit in the Monroe circuit court to recover damages for such injury occasioned by the derailment and wrecking of his train. The court below directed a verdict for the defendant.
The accident .was caused by a misplaced switch, and happened on the evening of Sunday, April 29, 1883, in the township of La Salle, in Monroe county, at about 8:30 o’clock. At this place the line of the Lake Shore & Michigan Southern Eailway Company runs parallel with, and a few rods west of, the line of the Michigan Central Eailroad Company. Some years prior to this time there
In the morning before the accident, plaintiff had run his engine and train, consisting of two cars and a smoker, from Toledo to Detroit, as he was accustomed to do, and was returning to Toledo in the evening. His train was behind time, and ha was running at the rate of 45 to 50 miles an hour. This was no faster than he was permitted to run, and there seems to be no claim that he was running faster than he ought, if there had been no switch in use there. The switch had been partly opened from some cause, and the rails so moved that the flange of the locomotive wheel struck the end of the easterly movable rail about in the middle. The engine was thrown into
The plaintiff testified, as did also the conductor of his train, that after the switch was abandoned they received notice that the lights from that switch would be taken down, that the agent was removed, and the station shut up. There had been before this "a station there, called “ Otter Creek,” where there was an operator and switch-tender. The conductor testified that he had notice from Sutherland, as he supposed, through one J. B. Morford, of the condition of this station, and that it was to be thereafter nothing more than any other piece of track between stations; that he received this information from an officer of the company. The conductor notified the
There can be no dispute from the record that at first there was a switch at this point, with target and lights and switch-tender as long as it was used. When the transferring of cars ceased, this switch was practically abandoned, and the section master securely spiked and closed it about a year before the accident. The target, lights, and tender were removed. The section master knew of its second use, but the target and lights were not restored until after the accident, and the plaintiff was not notified of its use again. It is disputed that he ever received any notice from any officer of • the defendant of the abandonment and closing of the switch, or that he was authorized to treat the track there as if in fact no switch were in existence. It is also claimed that cars were standing on this cross-over track every day for two weeks, and the switch was being used daily for three weeks, before the accident, and he must have known of it. No other notice, however, was shown to him. These disputed questions of fact were matters for a jury.
I think the plaintiff was entitled to go to the jury upon his theory of the case, and the testimony that he produced to support it. It is shown by the rules of the company that an existing switch which is in daily use is recognized as a place of danger, and engineers on passenger trains are required to slow up, and not run faster than 15 miles an hour, in passing one. It is also shown that the lights upon the switch stand are so arranged that, if the switch is out of place and therefore dangerous, the color of the light will at once, and certainly, show the danger. Therefore the closing of this switch, and removing these lights, with notice to plaintiff that
There was testimony tending to show that, if there had been lights upon the switch, such lights could have been seen in time, and the train stopped, so as to have prevented any accident. There was also testimony tending to show that the lights could not have been seen in time to prevent the derailment of the train. This dispute was for the jury.
It is contended that the plaintiff cannot recover because the absence of the lights was not the proximate cause of the accident; that, if the switch had been locked, the train would have passed safely by as it was, without any lights; and that the opening or unlocking of the switch was caused either by the intermeddling of some stranger or trespasser, or by the negligence of fellow-servants of the plaintiff; that he could not recover in either event. But I do not so understand it. If the plaintiff’s theory be true, the lights would have prevented any accident in the condition in which the switch was, as they would have warned the plaintiff in time to avoid the danger; so the negligence of the defendant in opening this closed switch for use, without any lights to warn plaintiff of the presence of the switch or its danger, was just as much the proximate cause of the injury as was the turning of the switch rails. And it certainly was a concurrent cause, and the injury in any event, under the plaintiff’s theory and evidence, was occasioned partly through the negligence of' the defendant as to the switch lights, and partly by the condition of the switch rails, in which
It is also contended by defendant’s counsel that the negligence, if any, in not restoring the switch lights was the negligence of the section master, who was a fellow-servant of the plaintiff, and therefore the plaintiff cannot recover for his injury. But this negligence in using the switch again without notice to the plaintiff, and in not restoring the lights, was not the negligence of the section master. The defendant company abandoned the switch, and shut up the station, and removed the lights in the first place. It was the division superintendent, and not the section master, who directed or authorized the removal of the spikes and the second use of the switch; and in doing this he was the agent of the company. It then became the duty of the defendant, not of the section master, except as he acted under the direction of the company, either to notify the plaintiff that there was a switch in use there, or to restore the lights, if .not to do both, and the negligence in not doing so would be the negligence of the defendant rather than of the section master.
The judgment of the court below is reversed, with costs, and a new tidal granted.