ON WRIT OF CERTIORARI TO THE COURT OF APPEALS
We granted certiorari in this case to review the judgment of the Court of Appeals in
Town of Winnsboro v. Specialty Constructors, Inc.,
FACTS
The Town of Winnsboro (“Winnsboro”) hired WiedemanSingleton (“Engineers”) to design a wastewater treatment facility (“sewer”). Turner-Murphy Company was hired as the general contractor to construct the sewer. Specialty Constructors was hired by Turner-Murphy and approved by Winnsboro to manufacture and install the filter system for the sewer.
Winnsboro experienced numerous problems with the new sewer. Ultimately, Winnsboro brought suit against the Engineers and the general contractor, Turner-Murphy. After discovery began, it became apparent that many of the problems experienced by Winnsboro were a result of the malfunction of the filter system which was manufactured and installed by Specialty Constructors.
Turner-Murphy filed a motion to implead Specialty Constructors. The motion was denied. Thereafter, Winnsboro amended its complaint to add Specialty Constructors as a party defendant. Turner-Murphy amended its answer and asserted a cross-claim against Specialty Constructors for any *130 judgment Winnsboro might receive against it and for attorney fees and costs.
At trial, the judge sent the case to the jury, reserving the cross-claim issues until the jury decided the issues in the complaint. The jury returned a verdict in favor of Winnsboro against Specialty Constructors in the amount of $85,000.00 on a negligence theory. Further, the jury found Specialty Constructors guilty of willful and wanton conduct and awarded punitive damages to Winnsboro. Turner-Murphy was found not liable to Winnsboro by the jury.
The trial judge directed a verdict in favor of Turner-Murphy on its cross-claim for attorney fees and costs against Specialty Constructors. Specialty Constructors appealed. The Court of Appeals affirmed in
Town of Winnsboro v. Specialty Constructors, Inc.,
ISSUES
1. Did the Court of Appeals err in affirming a directed verdict on the cross-claim for equitable indemnity?
2. Did the Court of Appeals err in overturning JKT Co. v. Hardwick because the complaint should determine the status of “joint tort-feasor” as a bar to equitable indemnity?
3. Did the Court of Appeals err in affirming the directed verdict in favor of Turner-Murphy, when Turner-Murphy’s cross-claim did not allege breach of contract?
ANALYSIS
This Court has long recognized the principle of equitable indemnification.
See e.g. Stuck v. Pioneer Loggins Machinery, Inc.,
The general rule is that costs and expenses of litigation, other than the usual and ordinary court costs, are not recoverable in an action for damages, nor are such costs even recoverable in a subsequent action; but, where the wrongful acts of the defendant have involved the plaintiff in litigation with others, or placed him in such relations with others as make it necessary to incur expenses to protect his interest, such costs and expenses should be treated as the legal consequences of the original act.
McGaw v. Acker, Merrall & Condit Co.,
In
Addy v. Bolton,
The relationship between Bolton, the owner, and Thompson, the contractor, was sufficient in that case to allow Bolton to recover his attorney fees and costs for defending the negligence of Thompson. Thompson negligently burned Bolton’s building. Because of Thompson’s negligence toward Bolton, Bolton was forced to defend in an action brought by Addy. We think the relationship here between Turner-Murphy, the contractor, and Specialty Constructors, the subcontractor, sufficiently analogous to the relationship in
Addy v. Bolton,
*132
In affirming the trial court, the Court of Appeals reversed its earlier decision in
JKT Co. v. Hardwick,
Specialty Constructor’s last issue on appeal is without merit. The very nature of equitable indemnification is that a contract for indemnity is unnecessary. Recovery is allowed when as a result of the defendant’s breach of contract or tortious activity the plaintiff is required to either defend itself or bring an action against a third party. 22 Am. Jur. (2d) Damages, § 618 (1988). The attorney fees and costs must be the natural and necessary consequence of the defendant’s act. Id.; see also Restatement (Second) of Torts, § 914(2). In the case at bar, Specialty should have foreseen that its willful and wanton negligence in the design and construction of the lift station would cause the general contractor, Turner-Murphy, to defend the wrongful actions of Specialty. Thus, Turner-Murphy’s attorney fees and costs were the natural and necessary consequences of Specialty’s negligence.
Accordingly, the judgment of the Court of Appeals is
Affirmed.
