Town of Wilson v. Town of NewfaneTown of Wilson v. Town of Newfane
— Order unanimously affirmed without costs. Memorandum: In this dispute over closure of a landfill, the court did not err in denying defendant’s motion for summary judgment. There are factual questions whether defendant, by virtue of its August, 1980 agreement with plaintiff, may be held liable for costs incurred by plaintiff in closing the landfill. Whether the term "maintenance”, as used in the agreement, encompasses closure presents an ambiguity to be resolved by the trier of fact. Generally, courts are responsible for interpreting written instruments (see, Hartford Acc. & Indem. Co. v Wesolowski,
Moreover, whether defendant terminated its contract with plaintiff without cause (see, Abcon Assocs. v Apollo Theatre Investor Group,
To the extent that plaintiff’s second cause of action purports to state a claim for contribution and/or indemnification predicated upon defendant’s violation of certain regulatory provisions, such claim cannot be maintained. Because the Environmental Conservation Law specifically authorizes the Attorney-General to enforce "any rule or regulation promulgated pursuant” to ECL article 27 (ECL 71-2727 [2]), we conclude that the statute does not confer a private cause of action. Furthermore, because there is insufficient proof to show that plaintiff was under a legal obligation to pay for closure of the landfill, plaintiff may not assert a common-law right to contribution (see, Yawger v American Sur. Co.,