206 Conn. 65 | Conn. | 1988
In this declaratory judgment action, the plaintiff municipalities
The parties presented a written stipulation of the pertinent facts to the state referee. In 1975, the town of Trumbull and the city of Bridgeport began to plan a joint sewer treatment system, known as the Bridgeport-Trumbull Interceptor Sewer Project, in order to extend underground sanitary sewer lines from Trumbull through Bridgeport. An application for funding of the project was submitted to the federal environmental protection agency (EPA) through the appropriate state agency, the DEP. Under the Federal Water Pollution Control Act of 1972; Pub. L. No. 92-500, 33 U.S.C. § 1281 et seq. (1976); a grant of federal funds for the project equal to 75 percent of allowable project costs was available and the EPA approved the grant application in June, 1977. Under General Statutes § 22a-439, the DEP may grant to a municipality for a sewer construction project eligible for federal funding an additional 15 percent of the cost of the project from state funds, leaving the municipality to bear the remaining 10 percent. On October 20, 1980, the DEP agreed to provide 15 percent of the cost of the Bridgeport-Trumbull Interceptor Sewer Project to be constructed in accordance with plans and specifications which the DEP had approved on August 22, 1977.
Construction of the sewer project began after the EPA had approved the grant application in June, 1977.
After the PUCA had issued its order prohibiting relocations without reimbursement by the municipalities, a dispute arose over the formula to be used in determining the amount to be paid to the utility companies. The municipalities proposed to use a formula approved by the DEP while the companies insisted upon a formula devised by the department of transportation (DOT) that had been used for many years in calculating the reimbursement of utility companies pursuant to General Statutes § 13a-126 for relocating their facilities as a result of highway construction projects. On October 20, 1981, the DPUC issued a decision ordering the companies to proceed with the relocations as ordered by the city of Bridgeport on the basis of an agreement of the municipalities to reimburse them in accordance with the DEP formula and also to pay any additional amounts that might be required by the ruling
I
When the plaintiff municipalities filed the original complaint in this action on May 15, 1981, the prayer for relief sought a declaratory judgment only with respect to the proper formula to be used in determining the “equitable share” of the relocation costs to be reimbursed to the utility companies. Not until January 30, 1985, when a motion to amend the complaint for the third time was filed, did the plaintiffs seek a determination of whether the statute relied upon to support the defendants’ claims for reimbursement, § 22a-470, effective on June 19, 1979, was applicable to the Bridgeport-Trumbull Interceptor Sewer Project, for which a federal grant application had been approved in June, 1977. The state referee concluded that, because the federal grant application for the project had been approved in June, 1977, prior to the enactment of § 22a-470, the statute could not be applied retroactively to allow reimbursement to the utility companies even for work performed after the statute had become effective. He found, nevertheless, that the municipalities had contracted to reimburse the utility companies pursuant to the statute and thus had waived its retroactive application. In attacking this conclusion on appeal, the plaintiffs maintain (1) that any such waiver was inoperative for lack of consideration, (2) that a municipality cannot effectively waive its immunity from liability for the performance of governmental acts, and (3) that it is contrary to public policy to uphold such a waiver.
The utility companies have presented several alternative grounds to support the determination that they are entitled to be reimbursed pursuant to § 22a-470 for relocations occurring after its enactment, including an
In five written agreements with individual utility company defendants during the period June 10, 1982, to March 30, 1985, the municipalities agreed to reimburse them for relocations pursuant to § 22a-470, subject to the ultimate determination of the appropriate formula in this litigation. On October 8, 1980, the city engineer of Bridgeport sent letters to three utility companies concerning a meeting to discuss relocation eligibility for federal funding in which he indicated that payment by the municipalities would be made pursuant to the DEP formula. When the DPUC, on October 20, 1981, revised its previous order to allow utility relocations to proceed, subject to the determination of the appropriate formula for reimbursement in this action, it expressly relied upon the agreement of the municipalities “to reimburse the companies on an ongoing basis according to the DEP formula and to pay any additional sums if required by the ruling of the Superior Court.” There is ample evidence to support the finding of the referee, adopted by the trial court, that the municipalities had “entered into contracts wherein they agreed the utilities were entitled to reimbursement” under § 22a-470 for relocation work performed after its effective date.
Although the term “waiver” has been used by the referee as well as the utility companies in characteriz
The municipalities contend that there was no consideration given for the interim agreements for performance of the work containing their promise of reimbursement under the statute or for the agreement pursuant to which the DPUC order prohibiting the utility companies from proceeding with relocations was modified. The mutual promises contained in these agreements, from which the municipalities have obtained the benefit of proceeding with their sewer project without the delay that otherwise would have attended the resolution of their dispute, adequately satisfied the consideration requirement. “An exchange of promises is sufficient consideration to support a contract.” Osborne v. Locke Steel Chain Co., 153 Conn. 527, 531, 218 A.2d 526 (1966).
The case relied upon by the plaintiffs in arguing that a municipality cannot waive its immunity from liability for the performance of governmental acts; Gauvin v. New Haven, 187 Conn. 180, 445 A.2d 1 (1982); does not support that proposition. Furthermore, the doctrine
The claim that it is contrary to public policy to infer a waiver of the municipalities’ belated claim that the statute should not be applied to their sewer project, which had commenced before its effective date, is similarly without merit. There is no public policy against the settlement of a disputed claim by any party, whether or not a municipality, on terms deemed advantageous at the time, even though the compromise may later, with the benefit of hindsight, appear improvident. Whether the resolution of the dispute accepted by the municipalities in their agreement with the utility companies was wise or foolish we need not determine.
II
Under the provisions of § 22a-470, a company ordered to relocate or remove a public service facility from a street must comply with such order, but “an equitable share of the cost of such readjustment, relocation or removal of said public service facility, including the cost of installing and constructing a facility equal in capacity in a new location, shall be borne by the municipality.” The statute further provides that “[i]n establishing the equitable share of the cost to be borne by the municipality, there shall be deducted from the cost of the readjusted, relocated or removed facilities a sum based on a consideration of the value of materials salvaged from existing installations, the cost of the original installation, the life expectancy of the original facility and the unexpired term of such useful life.” Virtually identical language is used in General Statutes § 13a-126
The DEP has refused to follow the DOT formula in deciding the amount of the “equitable share” of the cost to be reimbursed pursuant to § 22a-470, despite the use of language similar to that contained in § 13a-126. The DEP has devised a formula
The utility companies recognize that the DEP, and not the DOT, has jurisdiction to apply and interpret § 22a-470 in processing applications for sewers under General Statutes § 22a-439. See General Statutes §§ 22a-424 (l), 22a-439 (c). They maintain, nevertheless, that the DOT formula must be followed (1) because it represents a long-standing administrative interpretation of § 13a-126, a statute within the jurisdiction of the DOT, from which the legislature appears to have extracted the language used in § 22a-470 to define the “equitable share” of relocation costs to be borne by the municipalities, and (2) because the DEP injects into the calculation of “equitable share” an element, inflation, that is not mentioned in the statute.
This court has recognized the well established principle that great deference should be aceorded to the construction given a statute by the agency charged with its enforcement. Phelps Dodge Copper Products Co. v. Groppo, 204 Conn. 122, 129, 527 A.2d 672 (1987); Board
The companies also rely upon the circumstance that the legislature has made several amendments to § 13a-126 since the DOT formula has been in effect, none of which has modified the interpretation of the statute embodied in that formula. See Public Acts 1967, No. 671; Public Acts 1976, No. 76-133; Public Acts 1978, No. 78-280, § 2; Public Acts 1982, No. 82-472. These amendments, however, were unrelated to the statutory definition of “equitable share” and, in addition to technical changes necessitated by court reorganization, merely revised other portions of the statute with respect to the kinds of projects and utility installations to which it applied. It is fanciful to presume that the legislature in enacting them gave any consideration to the manner in which the DOT had been implementing the statutory definition of “equitable share.” There is no legislative history to suggest that the General Assembly was even aware of the DOT formula at the time of these amendments.
The companies rely principally on the “plain wording” of § 22a-470, which they maintain precludes consideration of inflation as an element in determining the amount of reimbursement for relocations. In specifying the method for calculating the municipality's “equitable share” of the cost of relocation, including the cost of the new installation, the statute specifies that from the total cost there shall be deducted “a sum based on a consideration of the value of materials salvaged from existing installations, the cost of the original installation, the life expectancy of the original facility and the unexpired term of such useful life.” The statute mentions the various factors that are to be considered in
It is quite apparent that to ignore the effect of inflation, as the DOT formula does, in determining a municipality’s share of the cost of relocating a facility that was installed many years ago, when the cost of such an installation was a fraction of its present cost, must inevitably result in substantial overpayments to utility companies and correspondingly excessive burdens upon municipalities. This inequity results from the failure to evaluate the additional useful life that the new facility has added to the remaining useful life of the replaced facility in accordance with the current cost of the new facility. To use historical costs of facilities installed many years ago in the same calculation with current costs of replacing those facilities results in a distortion comparable to adding apples and oranges.
The utility companies do not advance any arguments that seriously militate against the referee’s characterization of the amount of their reimbursement under the DOT formula as a windfall. They claim, neverthe
Because we have concluded that the trial court did not err in holding that the DEP formula could appropriately be applied in calculating the amounts to be reimbursed under § 22a-470, we need not consider the claim of error relating to the admission of a letter from EPA officials for the purpose of showing that they would approve the use of the DEP formula, but not the DOT formula, in calculating the costs of the project for the purpose of the federal grant to the municipalities. Whether this additional ground, upon which the referee and trial court partly relied, would provide an additional ground to affirm the judgment is a question we leave for another day.
There is no error.
In this opinion the other justices concurred.
During the trial court proceedings, the city of Norwalk intervened as a plaintiff but withdrew prior to judgment. The city of New Haven also intervened as a plaintiff and has participated in this appeal as well as in the trial court proceedings. New Haven has briefed and argued only the issue of the formula to be used in calculating the amount of reimbursement to be made to a utility company for relocating its facilities in the course of construction of a municipal sewer project.
The defendant utility companies are The Southern Connecticut Gas Company, The United Illuminating Company, Southern New England Telephone Company, Bridgeport Hydraulic Company and Connecticut Water Company. The state department of environmental protection was also a defendant in the trial court, but has not been involved in this appeal. The federal environmental protection agency was originally named as a party defendant, but the action was later withdrawn as to that defendant.
“[General Statutes] Sec. 22a-470. (Formerly Sec. 25-54yy). RELOCATION OR REMOVAL OF PUBLIC SERVICE FACILITIES AS NECESSARY FOR CONSTRUCTION OF MUNICIPAL SEWER OR POLLUTION ABATEMENT FACILITIES. Whenever a municipality obtains a grant under this chapter for the construction, rebuilding, expansion or acquisition of sewers or other pollution abatement facilities and where the carrying out of such construction, rebuilding, expansion or acquisition requires the temporary or permanent readjustment, relocation or removal of a public service facility from a street or public right-of-way, the municipality shall issue an appropriate order to the company owning or operating such facility and such company shall permanently or temporarily readjust, relocate or remove such facility promptly in accordance with such order, provided an equitable share of the cost of such readjustment, relocation or removal of said public service facility, including the cost of installing and constructing a facility equal in capacity in a new location, shall be borne by the municipality. Such equitable share shall be one
“[General Statutes] Sec. 13a-126. removal or relocation of public SERVICE FACILITIES FOR HIGHWAY CONSTRUCTION. As used in this Sec
The DOT formula determines the reimbursement for utility relocations by subtracting from the net relocation costs a “depreciated reserve,” which is calculated as follows:
[[Image here]]
The following example illustrates the application of the formula for a facility with the following data:
Total cost of replacement installation.................... $100,000
Less Salvage......................................... 10,000
Net cost............................................. $ 90,000
Original cost when installed 25 years ago with estimated useful life of 50 years....................................... $ 50,000
[[Image here]]
Reimbursement $90,000 (net cost) - $25,000 (depreciated reserve) =........................................... $ 65,000
The DEP formula is explained by the referee as follows:
“The DEP formula reads algebraically something like this: R = A - (B x C x D) - E. R is the reimbursement to utilities; A is relocation costs; B is cost of original installation; C is expired useful life divided by life expectancy of original facility; D is a factor for inflation; and E is value of salvage. The inflation factor is commonly accepted in the construction industry as the proper standard for bringing to current value the cost of construction done since 1900.”
The DEP formula also provides for a minimum reimbursement to a utility company of 20 percent of the current cost of the new installation, regard
Using the same figures as those in the example given in footnote 5, supra, and assuming an inflation faetor of 2.0 over the twenty-five year period, the calculation of the reimbursement would be as follows:
[[Image here]]
Reimbursement = $100,000 (new cost) - $10,000 (salvage) - $50,000
(BxCxD)=$40,000
A 2.0 inflation factor represents a doubling of construction costs over the twenty-five year period, corresponding to a 100 percent rate of inflation for that period or an uncompounded rate of 4 percent per year.