¶ 1. This case turns on the ever-changing location of East Shore Road, a town road that runs along Knee Deep Bay in South Hero, Vermont. Over time, Lake Champlain has eroded the shoreline, and plaintiff Town of South Hero has responded by moving the road further inland onto defendants’ land. In 2000, the Town sought a declaratory judgment as to the existence, location, and width of the road, and defendants — the four landowners on whose properties the Town claims the right-of-way for the road is located — counterclaimed for damages and injunctive relief. The trial court held that a right-of-way for the road was created by dedication and acceptance of the changes in the road’s position until a time just prior to the maintenance work the Town did in August of 2000, and that any road work by the Town outside of that right-of-way was a taking. As explained below, we affirm the trial court’s determination of the location and width of the right-of-way.
¶ 2. The roots of this dispute, now submerged in the waters of Knee Deep Bay,
¶ 3. The evidence reflects that East Shore Road, while not a heavily-trafficked thoroughfare, was regularly used as a road for decades. Charles Tourville, a seventy-two-year resident of South Hero, and John Roy, a sixty-two-year resident, both testified that they used the road since they were boys. Robert Frechette, the brother of two of the defendants, testified that he drove on the road “a couple times a year.” In addition to the trial testimony, the record includes sworn statements made by a number of residents in October 2000. Those statements demonstrate that people have driven on the road for many decades, and continued to do so up until 2000.
¶ 4. Over the years, as the north shore of the bay continuously eroded, the Town maintained the road by adding material and cutting trees as needed. The road is seasonal; over the years, the Town has plowed it sporadically during the winter, and it has been underwater and thus impassable in the spring. At trial, Mr. Tourville testified that the Town opened the road every year from 1966 to 1988 (his entire tenure as road commissioner), and Mr. Roy, who became road commissioner in 1990, testified that the Town opened the road in the years other than 1996 through 1999. 1
¶ 5. In 2000, the Town indicated that it was going to perform significant maintenance work on the road that would encroach upon, defendants’ property. On August 21, 2000, defendants’ attorney sent a letter to the Town objecting to the proposed construction. Four days later, the Town filed the declaratory judgment complaint that began this case. On August 28, 2000, three days after filing the lawsuit, the Town began the construction work, which it completed in September 2000. The construction work moved the road further inland, placing most of it between 100 and 160 feet further inland from its 1942 location, and more than twenty-five feet inland from its 1962 location.
¶ 6. In September 2000, defendants counterclaimed for damages and injunctive relief. Based on the parties’ stipulation, the trial court bifurcated the question of the road’s location from the issues of damages and attorneys’ fees. In 2003, the court held a bench trial to determine the location of the right-of-way for the road. It held that “[t]he right-of-way for the road was created by dedication and acceptance,” and described the right-of-way as “three rods wide, one and one half each side of the center line of the traveled portion as it moved slightly up to 2000.”
¶ 7. The court rejected the Town’s “shifting highway” and “rolling easement” theories and held that “[p]art of the 2000 construction by the Town is outside of the right-of-way and constitutes a wrongful taking.” It pointed out that the Town “must proceed to follow statutory procedures if parts of the new roadway are to remain as constructed in 2000” and to pay damages for property taken outside the right-of-way. The court then issued a final partial judgment defining the location and width of the right-of-way, permanently enjoining the Town from doing any further road work on defendants’ land lying outside the right-of-way, and setting for trial the parties’ remaining claims for damages, liability under 42 U.S.C. § 1983, and attorneys’ fees. Defendants appealed, and the Town cross-appealed. We address defendants’ appeal in Section I and the Town’s cross-appeal in Section II.
I.
¶ 8. Defendants argue that the court erred in concluding that the right-of-way had moved by dedication and acceptance farther inland from the 1962 location of the road. Specifically, they contend that the evidence at trial precluded the court from ruling that they intended to dedicate any land outside the 1962 roadway for public use, pointing to trial testimony describing four discrete incidents. First, Harlow Frechette, Sr., their predecessor-in-title, twice during the 1960s put up barriers to attempt to stop people from using the road, both of which the Town removed. Second, in the mid-1970s, defendant David Fifield encountered Charles Tourville, then the road commissioner of South Hero, operating a grader on East Shore Road. Mr. Fifield testified that he asked Mr. Tourville what he was doing. When asked at trial if he did anything other than ask Mr. Tourville what he was doing, Mr. Fifield responded, “No. It was quite evident that it wouldn’t make any difference. He was not the person to pursue the complaint with.” Third, Mr. Fifield testified that in 1991 he walked the beach with road commissioner John Roy and complained about the road, pointing out cut trees that had been “dumped well beyond a 50-foot right-of-way.” Fourth, the minutes of the Town selectboard reflect that the Frechettes and Fifields attended an August 5, 1991 meeting “to discuss the road being built up in front of their camps” and expressed concern about the removal of trees and about the public’s use of the beach without asking permission of the landowners.
¶ 9. In response, the Town argues that the court correctly concluded that defendants’ evidence of their unwillingness to dedicate the roadway is outweighed by the evidence showing intent to dedicate — namely, defendants’ long acquiescence in the existence of the road and acceptance of the Town’s efforts to maintain it. We agree.
¶ 10. “Dedication is the setting apart of land for public.use, either expressly
¶ 11. Because dedication may be express or implied, the offer to dedicate need not come in the form of a writing or an affirmative act by the owner.
Druke,
[l]ong acquiescence in use[] by the public, if the attending circumstances clearly indicate an intent by the owner to devote the land to public use, is evidence upon which a dedication may be predicated. The allowance by the owners of repairs at public expense is one circumstance that strongly tends to show the intent to dedicate.
Id.
at 575,
¶ 12. As described above, the court had before it some evidence that tended to disprove an intent on defendants’ part to dedicate land
beyond the 1962 location of the road, including testimony about a handful of instances where defendants expressed concern about the road
3
and one or two instances of defendants’ predecessor-in-title erecting a physical barrier across the road. The court concluded, however, that defendants made an implicit offer to dedicate the land, citing the “[l]ong acquiescence in use by the public and allowance by the owners of repairs at public expense” and the fact that “the parties acknowledge the historical existence of the road.” Each of these facts was supported by “reasonable or credible evidence.”
Mann,
¶ 14. Defendants next argue that if we uphold the trial court’s conclusion that a dedication occurred, then the resulting right-of-way’s inland boundary should be the “northerly line of the traveled portion of the road as it existed prior to the August 2000 construction.” This argument challenges the trial court’s conclusion that the “right-of-way is three rods wide, one and one half each side of the center line of the traveled portion as it moved slightly up to 2000.” Defendants’ argument would effectively characterize all of the 2000 construction as a taking, rather than only that portion of the construction that extends beyond the three-rod right-of-way fixed by the trial court.
¶ 15. When, as here, the boundaries of a road are not properly recorded,
4
the law presumes a roadway width of “one and one half rods on each side of the center of the
existing
traveled way.” 19 V.S.A. § 32 (emphasis added). This presumption applies regardless of whether the existing traveled way has wandered from its original route.
Town of Ludlow v. Watson,
¶ 16. The evidence shows instead that the land was dedicated to public use as a road. Dedication “passes an easement to use the property in a manner consistent with the dedication.”
Walker,
II.
¶ 17. In its cross-appeal, the Town argues that there can be no taking in this case because the shoreline is “the only true monument” for determining the location of the road and the Town has respected that location “for as long as the road has been there.” The Town reasons that it is entitled to a three-rod right-of-way centered at the centerline of the existing traveled way — wherever it may be — because 19 V.S.A. § 32 applies “whether or not the traveled way has changed over time.”
Watson,
¶ 18. We disagree with the Town’s analysis. A “common-law dedication ... does not pass fee simple; rather, it passes an easement to use the property in a manner consistent with the dedication.”
Walker,
¶ 19. The Town’s reliance on
Feinman v. State,
¶ 20. Finally, the Town contends that, after the August 2000 construction, the road remained completely inside the three-rod right-of-way centered on the centerline of the preconstruction traveled way created by the dedication. In so arguing, the Town refers to defendants’ trial exhibit C, a large map that depicts the location of the traveled way prior to the construction, the traveled way after the construction, and the boundaries of the three-rod right-of-way centered at the centerline of the preconstruction traveled way. While we decline to rule on whether and to what extent the August 2000 construction worked a taking, we note that, contrary to the Town’s contention, defendants’ exhibit C appears to shows several small areas where the post-construction traveled way sits outside of the three-rod right-of-way. Pursuant to the parties’ stipulation, the trial court will determine during the second phase of this bifurcated matter whether the August 2000 construction was a taking of defendants’ land and, if so, to what extent.
¶ 21. In conclusion, the trial court correctly decided that the right-of-way for East Shore Road as it existed prior to the August 2000 construction work was established by dedication and acceptance of the incremental changes in the roadway’s location up to that time. Additionally, the court applied 19 V.S.A. § 32 properly in centering the right-of-way at the centerline of the traveled way, rather than setting the inland edge of the traveled way as the right-of-way’s boundary. The court also correctly rejected the Town’s theories that would have the effect of moving the right-of-way further inland from that location. Therefore, we affirm the partial judgment and remand the matter so that the second phase of the litigation can proceed.
Affirmed and remanded for further proceedings consistent with this decision.
Notes
There was no specific testimony about the road’s status in 1989 because Mr. TourviUe’s tenure as road commissioner ended in 1988, and Roy’s began in 1990.
The partial judgment order signed by the court on August 4, 2004 confirms that the “centerline of the road is hereby declared to be the centerline of the road as it existed prior to the construction work done by the Town in 2000. The width of the road is hereby declared to be three rods wide, centered on said centerline.”
In this regard, we note that defendants’ own testimony indicates that to the extent they voiced displeasure about the road’s existence, they did not do so in a manner that could have overridden the public’s expectation, based on long-time use, that the road was and would remain a public way.
Under 19 V.S.A. § 702, “[t]he right-of-way for each highway and trail shall be three rods wide unless otherwise properly recorded.” The trial court found that “[t]here has never been any formal laying out nor formal alteration or relocation of the highway in the Knee Deep Bay area.”
The 1999 deed of James Wood states that “[t]he parcel of land herein conveyed is subject to whatever rights the Town of South Hero may have in and to Hochelaga Road, so-called, which crosses the parcel.” Similarly, the 1997 deed of Harold Woods and Stephanie Woods notes that the “conveyed land is subject to the right of way of Hochelaga Road (formerly known as East Shore Road).”
