Town of Sabattus v. L.P. Poirier & Son, Inc., Et Al.Town of Sabattus v. L.P. Poirier & Son, Inc., Et Al.
[¶1] This case involves a gravel pit in the Town of Sabattus that violated the terms upon which the Town had permitted it to operate. The owners of residential properties adjacent to the mining operation, whom we collectively refer to as the Abutters,1 appeal from a judgment of the District Court (Lewiston, Churchill, J.) approving a consent judgment between the Town and the owners of the mining operation, Raymond N. Poirier and L.P. Poirier & Son, Inc. (collectively, Poirier).2 The Abutters argue that the consent judgment
violates state and local law and that the court erred in approving it. We disagree and affirm the judgment.
I. BACKGROUND
[¶2] In 2003, the Town granted Poirier conditional approval to mine gravel from a four-acre excavation area abutting F. Sanborn Road, a private road along the shore of Sabattus Pond. The Abutters own properties along the shore and use F. Sanborn Road for access. The 2003 conditional approval required Poirier to maintain a buffer zone between F. Sanborn Road and the edge of the excavated pit and maintain a two-to-one slope ratio from the edge of the mining area. The Town also approved Poirier‘s reclamation plan.
[¶3] In November 2023, the Town received a letter from an attorney representing one of the Abutters asking the Town to assess the gravel pit‘s compliance with the conditional approval. After the Town did so and identified various concerns, Poirier agreed to cease further excavation operations.
[¶4] In December 2023, the Town issued a notice of violation to Poirier for violating the conditional approval by expanding the pit beyond four acres and into the buffer zone and not maintaining a two-to-one slope ratio from the mining area line. The Town also cited Poirier for expanding the pit into the
[¶5] Throughout 2024 and early 2025, the Town and Poirier engaged in discussions to resolve the matter. In spring 2025, the Town filed a land use citation and complaint, see
[¶6] The consent judgment requires Poirier to submit and execute a new reclamation plan, stabilize the berm on the edge of the excavation zone along F. Sanborn Road, and construct a “Reclaimed Buffer in the 30 feet east of the Berm,” i.e., between the road and the excavated zone. The judgment states that Poirier has no further mineral extraction rights and that “this Consent Judgment grants [Poirier] no right to use the Premises.” Additionally, Poirier must “cause all work at the Premises to be performed in accordance with the Reclamation Plan, Sabattus Code, Maine law, and the Maine Erosion and Sediment Control Best Management Practices.”
II. DISCUSSION
[¶8] Relying on Pike Industries, Inc. v. City of Westbrook, the Abutters argue that the consent judgment violates Maine statutes and the Town‘s own ordinances, and that, therefore, the court erred in approving the judgment. In Pike, we held that while a municipality has the right to settle lawsuits, “consent decrees that affect public rights should be subject to closer scrutiny than those that resolve purely private disputes.” 2012 ME 78, ¶ 23, 45 A.3d 707. We stated that
when a court is asked to approve a consent decree . . . that will affect the enforcement of a land use ordinance, it should ensure . . . that entering the decree is fair, adequate, and reasonable, and . . . (1) the parties have validly consented; (2) reasonable notice has been given to possible objectors and they have been afforded a reasonable opportunity to present their objections; (3) the consent decree will not violate the United States or Maine Constitutions, a statute, or other authority; (4) the consent decree is consistent with express legislative objectives and other zoning-related public policy considerations; and (5) the consent decree is reasonable and is not legally impermissible in its effects on third parties.
Id. ¶ 24. The Abutters argue that the consent judgment violates elements three, four, and five of this standard. Their primary grievance with the consent judgment is that it requires Poirier to construct a reclaimed buffer zone of thirty
[¶9] “For the purposes of our appellate review, whether a consent decree comports with legal requirements is a question of law that we review de novo.” Pike Indus., 2012 ME 78, ¶ 14, 45 A.3d 707. Because a “consent decree is primarily a means by which parties settle their disputes without having to bear the financial and other costs of litigating,” an intervenor or other third party cannot “block the decree merely by withholding consent.” Butler v. D/Wave Seafood, 2002 ME 41, ¶ 13, 791 A.2d 928 (quotation marks omitted). Therefore, “[n]otwithstanding the objection of intervenors, if the court finds that each of the five elements identified above is met, it may approve the decree.” Pike Indus., 2012 ME 78, ¶ 28, 45 A.3d 707.
A. State Law
[¶10] Maine statutes set performance standards for certain excavation operations. See
[¶11] It is not clear whether these standards apply here. The standards apply only to excavation operations where “the total excavated area on a parcel is 5 or more acres.”
[¶12] The consent judgment requires Poirier to “construct a Reclaimed Buffer in the 30 feet east of the Berm” and does not explicitly require Poirier to reestablish vegetation on the buffer. The consent judgment does not, though,
[¶13] Further, nothing in the consent judgment purports to immunize Poirier from enforcement of
B. Ordinances
[¶14] The Abutters also argue that the court erred in approving the consent judgment because it violates the Town‘s 2004 and 2015 Site Plan Review Ordinances and its Shoreland Zoning Ordinance. The Abutters contend
[¶15] “When we interpret an ordinance, we look first to the plain meaning of its language, and if the meaning of the ordinance is clear, we do not go beyond it.” Moreau v. Town of Parsonfield, 2024 ME 75, ¶ 27, 327 A.3d 48 (quotation marks omitted). “In construing the language of an ordinance, the ordinance is to be considered as a whole.” Id. (quotation marks omitted).
1. Site Plan Review Ordinances
[¶16] The Abutters argue that the Town‘s 2004 and 2015 Site Plan Review Ordinances require gravel pits to have a buffer zone of at least fifty feet and that the consent judgment violates these ordinances by requiring only a thirty-foot buffer zone. This argument, though, is based on a misunderstanding of how these ordinances operate.
[¶17] The Town‘s Site Plan Review Ordinance has varied over the years. It was first adopted in 1978. A revised version was adopted in 2004, and the Town‘s current Site Plan Review Ordinance was adopted in 2015. See Sabattus, Me., Site Plan Rev. Ord. (May 14, 2015). The essential purpose and framework
[¶19] Even if the 2004 and 2015 Site Plan Review Ordinances somehow apply to gravel pits that received site plan approval under the 1978 ordinance, Poirier is no longer operating the gravel pit. The consent judgment does not allow Poirier to use the premises or extract minerals. Instead, it sets forth the actions that Poirier must take to reclaim the area. Nothing in the 2004 or 2015 ordinances suggest that they apply to the reclamation of a previously approved project.
2. Shoreland Zoning Ordinance
[¶21] Next, the Abutters argue that the Town violated its Shoreland Zoning Ordinance by allowing an “illegal structure or use to continue.” Sabattus, Me., Shoreland Zoning Ord. § 16(I)(3) (May 30, 2009). The Abutters first cite a provision of the Shoreland Zoning Ordinance which states that
municipal officers . . . are hereby authorized to enter into administrative consent agreements for the purpose of eliminating violations of this Ordinance and recovering fines without Court action. Such agreements shall not allow an illegal structure or use to continue unless there is clear and convincing evidence that the illegal structure or use was constructed or conducted as a direct result of erroneous advice given by an authorized municipal officer.
[¶22]
C. Public Policy and Effect on Third Parties
[¶23] Finally, the Abutters argue that the consent judgment is contrary to zoning-related public policy and is impermissible because of its effects on third parties. See Pike Indus., 2012 ME 78, ¶ 24, 45 A.3d 707. “[C]ourts should uphold the public policy favoring the settlement of disputed claims by deferring to the reasonable judgments and compromises made by the settling parties.
[¶24] Here, where the thirty-foot buffer does not violate state law or town ordinances, and the consent judgment is consistent with town ordinances in all other respects, we cannot say that the judgment unreasonably interferes with the Town‘s land use scheme. The Abutters essentially argue that an inconsistency between a consent judgment and a town‘s ordinances should result in the consent judgment being rejected. As discussed above, there is no inconsistency. In any event, Abutters’ argument is neither consistent with Pike, which contemplates inconsistencies, nor public policy in favor of allowing settlements. The fifth Pike factor specifically “calls upon the court to consider, among other things, whether the extent to which a consent decree will interfere with a municipality‘s land use regulatory scheme is no greater than that reasonably needed to achieve the consent decree‘s objectives.” Pike Indus., 2012 ME 78, ¶ 25, 45 A.3d 707. The fact that the court must weigh the degree
[¶25] Finally, the consent judgment does not dispose of any independent claims the Abutters may have, see Butler, 2002 ME 41, ¶ 13, 791 A.2d 928, and their claims that the thirty-foot buffer would interfere with the F. Sanborn Road right-of-way or their adjacent properties are speculative. In the absence of a concrete and particular interference with their rights, we cannot say that the consent judgment has a legally impermissible effect on the Abutters.
The entry is:
Judgment affirmed.
Keith P. Richard, Esq., and Colin W. Hull, Esq. (orally), Archipelago, Portland, for appellants Christopher Tweedie, Jane Eden Guthro, Leslie Cook, Richard Charest, Gerald Hagerty, James Montrone, Jonna Wilson, Timothy Richard, Michael Todorsky, and Scott Fyfe
Zachary B. Brandwein, Esq., Dentons Bingham Greenebaum LLP, Portland, for appellee Kristie J. Berube
Lewiston District Court docket number CIV-2025-92
FOR CLERK REFERENCE ONLY