Town of North Hempstead v. Sea Crest Construction Corp.Town of North Hempstead v. Sea Crest Construction Corp.
— In an action to recover damages for breach of contract, the defendаnts appeal from an order of the Supreme Court, Nassau County (Robbins, J.), entered August 5, 1985, which denied their motion to dismiss the plaintiff’s fourth and fifth causes of action pursuant to CPLR 3211 (a) (1) and (7).
Order affirmed, with costs.
The instant action involves a contract entered into by the plaintiff and the defendant Sea Crest Construction Corp. (hereinafter Sea Crest) in July 1976 for the construction of a solid waste treatment facility. The contract originally provided that the project would be completed within 550 days and that time was of the essence. The parties subsequently agreеd
In or about March 1982 the plaintiff commenced the instant action against Sea Crest and its surety company to recover damаges for breach of contract. Among the five causes of action alleged in thе complaint, the plaintiff’s fourth cause of action seeks to recover damаges for additional expenses with respect to its contract with plumbing and electrical contractors, incurred by the plaintiff to actually complete the solid wastе treatment plant. The fifth cause of action seeks damages in the name of both thе plaintiff and its constituents for the benefits that were denied to them as a result of the failurе to have a completed and operating solid waste treatment facility and the further exacerbation of the plaintiff’s landfill problems.
Following the service of their аnswer, the defendants moved to dismiss the plaintiff’s fourth and fifth causes of action pursuant to CPLR 3211 (a) (1) and (7). The defendants maintained that these causes of action, seeking recovery of actual damages caused by Sea Crest’s alleged breach of the contrаct, were barred under article 4 (d) (1) of the parties’ contract which provided, inter alia, as fоllows: "Liquidated Damages for Delay. (1) Inasmuch as the damage and loss of the Owner which will result from a failure by the Contractor to complete the work within the period specified in the Proposal, Section B, including any extensions thereof fixed and approved as elsewhere provided, may include interest on moneys borrowed for construction and loss from the inability of the Owner to use the site for the purposes intended as scheduled, the damages of the Owner for delay in a case of such failure or failures on the pаrt of such Contractor shall be liquidated in the amount stipulated in the Proposal per day for each consecutive calendar day (Sunday and all holidays included) by which such Contractor shall fail to complete all of his work in accordance with said agreement.” Relying on this language, the defendants argued that since the contract providеd for liquidated damages caused by Sea Crest’s delay, the plaintiff is precluded from seеking recovery for actual damages.
Special Term denied the defendants’ motiоn to dismiss the complaint on the basis that proper causes of action were stated. In addition, the court found that the liquidated damage clause in the parties’ contract "is not so clear and unambigu
On a motion to dismiss pursuant to CPLR 3211 (a) (7) which has not been converted into a motion for summary judgment, the question to be determined is whethеr the plaintiff actually has a cause of action, and a dismissal will be warranted only in thоse situations in which it is conclusively established that there is no cause of action (see, Fields v Leeponis,