delivered the opinion of the Court.
This construction dispute requires the Court to consider two issues: 1) when a building can be considered substantially complete for purposes of calculating the ten-year period of the statute of repose, N.J.S.A. 2A: 14-1.1(a), and 2) whether the Comparative Negligence Act, N.J.S.A. 2A:15-5.2, and the Joint Tortfeasors Contribution Law, N.J.S.A. 2A:53A-2, authorize allocation of fault at trial to defendants who have obtained dismissals pursuant to the statute of repose, N.J.S.A. 2A:14-l.l(a).
Following structural failures in its public safety facility, plaintiff Town of Kearny (Town) sued the project’s architectural firm, Brandt-Kuybida Architects (Brandt-Kuybida), and three of its individual architects, alleging that Brandh-Kuybida was liable for defects in the facility that rendered it unusable. The Town and Brandt-Kuybida filed claims against the project’s soil engineering firm, Soils Engineering Services, Inc. (SESI), and one of its individual engineers, and structural engineering firm, HarrisonHamnett, P.C. (Harrison-Hamnett), and its principal. The trial court granted summary judgment motions filed by SESI and Harrison-Hamnett on the ground that the Town’s complaint was filed more than ten years after the engineers completed their work on the construction project, ruling that the claims against these defendants were barred by the statute of repose and the statute of limitations. The trial court, however, denied a similar motion filed by the defendant architect, holding that the ten-year
The Town appealed. The Appellate Division affirmed the trial court’s application of the statutes of repose and limitations to Brandt-Kuybida but reversed the trial court’s denial of the architect’s application for an apportionment of fault to the dismissed codefendants.
We affirm. We hold that the trial court properly denied Brandt-Kuybida’s motion for summary judgment on the statute of repose issue. We concur with the trial court’s finding that the ten-year period prescribed in N.J.S.A. 2A:14-l.l(a) commenced when the first Temporary Certificate of Occupancy was issued for the Town’s public safety facility. We further hold that, when the claims against a defendant are dismissed on statute of repose grounds, fault may be apportioned to the dismissed defendant under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
I.
The South Kearny Improvement Projects Corporation (SKIP) was charged by the Town with the responsibility to oversee the design and construction of a new public safety facility, including police and fire stations. In October 1989, BrandWKuybida submitted a proposal to SKIP to design and plan the new facility. SKIP selected BrandWKuybida to perform the work. A principal of the firm, Louis Brandt, was initially designated as the lead architect. The Town and Brandt-Kuybida executed a contract on April 9, 1990. After Brandt-Kuybida dissolved in 1994, Michael Kuybida became the primary architect for the project.
SKIP chose Beleor Construction (Belcor) to build the facility in accordance with Brandt-Kuybida’s design, and, on July 11, 1994, SKIP and Belcor entered into a construction contract. Among other provisions, the construction contract required Belcor to achieve substantial completion of the project within 360 days of the issuance of a Notice to Proceed. That notice was issued on September 12, 1994. The contract between SKIP and Belcor defined substantial completion to be the date upon which the project architect, Brandt-Kuybida, certified that the facility is “sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.”
Construction of the facility began in the fall of 1994. On November 15,1995, Beleor signed a document entitled “Certificate of Substantial Completion” (Certificate). On November 24, 1995, Brandt-Kuybida and SKIP signed that same document. In language similar to that of the July 11, 1994 contract, the Certificate defined the date of substantial completion as “the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.” The signatories to the Certificate, however, failed to complete it. For reasons that the record does not disclose, the “date of issuance” and the “date of completion” of the project were left blank on the form.
Structural defects in the facility surfaced shortly after the Kearny Police Department took occupancy. The building settled differentially, causing gaps between the ceiling and a wall, as well as leaks, buckled tiles and cracks in the walls. The Kearny Police Department reported leaks in various parts of the building and doors that could not close because they did not fit in their frames. Although the Town continued to use the facility, there were further complaints about structural flaws in the building. In 2003, the Town’s Construction Official received an emergency call that the ceiling in the police dispatch area of the building was about to collapse. By 2007, ceilings in the facility had fallen, pipes had separated and pulled, and glass had broken, all of which were attributed to uneven settlement. The Town never issued a final certificate of occupancy. The Town’s Construction Official ordered all occupants to evacuate the building on February 8, 2007. The building has been vacant and unused since that date.
Belcor initiated arbitration proceedings against the Town because the Town withheld final payment under the contract. Bel
II.
On April 7, 2006, the Town filed an action in the Law Division, asserting negligence and breach of contract claims against Brandt-Kuybida and two of its principals, Louis Brandt and Michael Kuybida, and another architect, Robert Strebi (the Brandt-Kuybida defendants); negligence claims against Harrison-Hamnett and its principal, John N. Harrison (the HarrisonHamnett defendants); and negligence and breach of contract claims against SESI and one of its engineers, William St. Pierre (the SESI defendants). The Brandt-Kuybida defendants pled an affirmative defense based upon their right to seek apportionment of fault to all other parties who contributed to the incident. They also asserted a cross-claim against their codefendants, premised upon common-law indemnification and contribution pursuant to the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
The Brandt-Kuybida defendants filed a motion for summary judgment. They asserted, among other theories, that the statute of repose, N.J.S.A. 2A:14-l.l(a), barred the Town’s claims.
The trial court, however, granted summary judgment motions filed by the Harrison-Hamnett defendants and the SESI defendants. It held that the ten-year period set forth in the statute of repose commenced for the SESI defendants on the date that their involvement in the project ended, July 31, 1990, and that the statutory period commenced for the Harrison-Hamnett defendants on the date that their role in the project concluded, October 30, 1995. Consequently, the trial court held that the actions against the SESI and Harrison-Hamnett defendants were barred by both the statute of repose, N.J.S.A. 2A:14-l.l(a), and the
The BrandL-Kuybida defendants filed a motion for leave to appeal the trial court’s order denying summary judgment. The Appellate Division granted the motion and summarily remanded the ease to the trial court for reconsideration in light of this Court’s decision in Daidone v. Buterick Bulkheading, 191 N.J. 557,
The case was tried before a jury for six days in October 2008. The trial court rejected the Brandt-Kuybida defendants’ argument that the date of substantial completion should be determined by the jury, and denied their motion to dismiss the Town’s claims on statute of repose grounds at the close of the Town’s case. In accordance with the trial court’s decision striking the Brandi Kuybida defendants’ apportionment defense, the jury considered only the fault of those defendants, not that of the codefendants previously dismissed on statute of repose grounds.
The Brandt-Kuybida defendants appealed. Analyzing the Comparative Negligence Act, the Joint Tortfeasor Contribution Law
We granted the Town’s petition for certification and the BrandWKuybida defendants’ cross-petition for certification. 209 N.J. 98,
III.
The parties dispute whether the trial court should have granted the Brandt-Kuybida defendants’ motion for summary judgment on the statute of repose. The Brandt-Kuybida defendants primarily rely upon the Certificate of Substantial Completion signed on November 15 and 24, 1995, contending that the latter date constitutes the operative date by which the construction was substantially complete. They contend that, if the Court does not accept Novembеr 24,1995, as the date of substantial completion, it should instead find February 1, 1996, to be the critical date, given the Town’s acknowledgement of that date in its Stipulation of Settlement with Belcor and the corresponding Town of Kearny Resolution 1999(R)-338. The Brandt-Kuybida defendants argue that in
The Town argues that the trial court properly ruled that the date of substantial completion was April 9, 1996, when the first Temporary Certificate of Occupancy was issued. Although the Town concedes that parties to a construction dispute may stipulate to a date of substantial completion, it contends that there was no such stipulation in this ease. The Town asserts that because no agreed-upon date was included in the Certificate of Substantial Completion, that document lacked a material term and has no legal effect. The Town urges the Court to defer to the factual findings of the trial court regarding the actual date upon which work on the project had progressed to the point of substantial completion. It argues that the trial court correctly denied the BrandUKuybida defendants’ motion for summary judgment, because the action was timely filed.
With respect to the issue of apportionment, the Town argues that the Appellate Division erred when it reversed the trial court’s pretrial and trial orders and permitted the Brandb-Kuybida defendants to allocate fault to the SESI and Harrison-Hamnett defendants. The Town contends that, when the claims against an individual or entity are dismissed pursuant to the statute of repose, liability should not be apportioned to that individual or entity, because the Comparativе Negligence Act, N.J.S.A 2A:15-5.2(a)(2), authorizes apportionment only to “the parties to a suit.” The Town argues that the SESI and Harrison-Hamnett defendants are distinguishable from various categories of parties to whom fault may be apportioned under our law. Instead, the Town likens the dismissed defendants in this case to an employer protected from civil liability by the workers’ compensation bar, to which fault may not be apportioned under the relevant statutes.
The Brandb-Kuybida defendants counter that allocation of fault to the SESI and Harrison-Hamnett defendants is consistent with the protective goals of the statute of repose because those defen
IV.
The first issue before the Court is whether the trial court properly denied the Brandt-Kuybida defendants’ motion for summary judgment and their motion to dismiss at the close of the Town’s case at trial based upon the statute of repose. We review de novo the grant or denial of a motion for summary judgment. Coyne v. State Dep’t of Transp., 182 N.J. 481, 491,
In 1967, “the Legislature enacted the statute [of repose] in response to the expanding application of the ‘discovery rule’ to new types of tort litigation, the abandonment of the ‘completed and accepted rule’ ... and the expansion of strict liability in tort for personal injuries caused by defects in new homes to builder/sellers of those homes.” Newark Beth Israel Med. Ctr. v. Gruzen & Partners, 124 N.J. 357, 362,
No action whether in contract, in tort, or otherwise to recover damages for any deficiency in the design, planning, supervision or cоnstruction of an improvement to real property, or for any injury to property, real or personal, or for an injury to the person, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribu*93 lion or indemnity for damages sustained on account of such injury, shall be brought against any person performing or furnishing the design, planning, supervision of construction or construction of such improvement to real property, more than 10 years after the performance or furnishing of such services and construction.
[N.J.S.A. 2A:14-l.l(a).]6
The statute of repose is construed broadly to serve its legislative objective “of providing a reasonable measure of protection against expanding liability for design and construction professionals.” Newark Beth Israel, supra, 124 N.J. at 363,
Our case law distinguishes between defendant contractors who are hired to perform limited services and defendants with supervisory responsibilities that span the entire project, in determining the date upon which the ten-year period begins for purposes of N.J.S.A. 2A:14-l.l(a). For the former, the ten-yеar period begins to run at the conclusion of the contractor’s specific task. As this Court held in Daidone, supra, 191 N.J. at 568,
For professionals such as the BrandL-Kuybida defendants, whose responsibilities for the Kearny public safety facility continued throughout its design and construction, the ten-year period set forth in N.J.S.A 2A:14-1.1(a) commences on the date of the project’s substantial completion. In Russo Farms, supra, 144 N.J. at 116-17,
[I]f liability were to be measured from the date the last retainage is released and all disputed and punch list items are completed, a contractor’s exposure to suit might be prolonged unreasonably. Disputes over workmanshiр and compensation for services can continue for years____[A] contractor would remain liable and the commencement of the statute of repose could be delayed indefinitely. Such a result is inconsistent with the statutory purpose to provide repose and allow contractors and architects to walk away from liability at a certain point in time; indeed, it would, all too often, provide “liability for life.”
[Id. at 117-18,675 A.2d 1077 .]
Deferring to the construction industry’s standard practice of deeming a project complete, the Court held that “substantial completion” had occurred for statute of repose purposes “when the certificate of occupancy was issued and the architect certified to the owner that building was substantially completed.” Id. at 117,
This Court’s holdings in Russo Farms and Daidone support the determinations of the trial court and the Appellate Division in this ease. The trial and appellate courts agreed that the ten-year period prescribed by the statute of repose commenced on April 9, 1996, when the first Temporary Certificate of Occupancy was issued for the facility. As the trial court noted, this certificate indicated that the building was sufficiently complete so that it could be occupied and used. We agree and hold that the issuance of that certificate triggered the running of the ten-year period for purposes of the statute of repose under N.J.S.A. 2A:14-l.l(a).
While this Court in Russo Farms acknowledged the importance of the date of substantial completion аs certified by a project’s lead architect, see Russo Farms, supra, 144 N.J. at 92-93, 117,
We affirm the trial court’s finding that the ten-year period of the statute of repose, N.J.S.A. 2A:14-l.l(a), commenced on April 9, 1996, when the first Temporary Certificate of Occupancy was issued. Accordingly, we hold that the Town’s action was timely filed against the BrandWEiuybida defendants. We affirm the Appellatе Division’s determination that the trial court properly denied the Brandt-Kuybida defendants’ motion for summary judgment.
V.
We review de novo the Appellate Division’s decision reversing the trial court’s ruling on the issue of whether the jury should consider the SESI and Harrison-Hamnett defendants’ fault in its apportionment calculation. See Murray v. Plainfield Rescue Squad, 210 N.J. 581, 584,
The Comparative Negligence Act and the Joint Tortfeasors Contribution Law comprise the statutory framework for the allocation of fault when multiple parties are alleged to have contributed to the plaintiff’s harm. Under the Comparative Negligence Act, in negligence and strict liability actions in which “the
(1) The amount of damages which would be recoverable by the injured party regardless of any consideration of negligence or fault, that is, the full value of the injured party’s damages.
(2) Thе extent, in the form of a percentage, of each party’s negligence or fault. The percentage of negligence or fault of each party shall be based on 100% and the total of all percentages of negligence or fault of all the parties to a suit shall be 100%.
[N.J.S.A. 2A:15-5.2(a).]
In practice, the Comparative Negligence Act requires the fact-finder to assign to each party on the verdict sheet a percentage of fault, with the percentages assigned to each party adding up to 100%. N.J.S.A. 2A: 15-5.2(a)(2). With the factfinder’s task complete, ‘Ttjhe judge shall mold the judgment from the findings of fact made by the trier of fact.” N.J.S.A. 2A:15-5.2(d). In accordance with N.J.S.A. 2A:15-5.3(a), if a defendant’s fault is assessed at sixty percent or more, the plaintiff may recover the full amount of the awarded damages from that defendant alone. If the factfinder apportions less than sixty percent of fault to that defendant, the plaintiff may recover from that defendant only the percentage of the damages assessed. N.J.S.A. 2A:15-5.3(c).
The Joint Tortfeasors Contribution Law plays a complementary role in the statutory scheme. Under that statute, a party that is liable for more than the percentage share of the damage award that is assessed by the factfinder may have contribution rights against other parties. N.J.S.A. 2A:53A-3. The statute “was enacted to promote the fair sharing of the burden of judgment by joint tortfeasors and to prevent a plaintiff from arbitrarily selecting his or her victim.” Holloway v. State, 125 N.J. 386, 400-01,
When interpreting multiple statutes governing the same subject, the Court should attempt to harmonize their provisions. Saint Peter’s Univ. Hosp. v. Lacy, 185 N.J. 1, 14-15,
We previously have not determined whether the Comparative Negligence Act and the Joint Tortfeasors Contribution Law authorize allocation of fault to a defendant who obtains a dismissal by virtue of the statute of repose. This Court and the Appellate
The Appellate Division in Ramos v. Browning Ferris Industries of South Jersey, Inc., 194 N.J.Super. 96, 106,
This Court reached a different conclusion when the defendant at issue was not protected by statutory immunity but was dismissed from the case by virtue of a settlement. In Young v. Latta, 123 N.J. 584, 585,
Thus, when a defendant ceases to participate in the case by virtue of a settlement, a non-settling defendant who meets the relevant requirements as to notice and proof may obtain an allocation of fault to the settling defendant. See Young, supra, 123 N.J. at 596-97,
We hold that the triеr of fact must determine the percentage of fault or negligence of a party dismissed from a negligence action following that party’s discharge in bankruptcy. .. That conclusion assures that defendants are not deprived of the benefits of the Comparative Negligence Act, namely their right to be held accountable only for their percentage of fault, provided that portion is less than sixty percent.
[Id. at 116,853 A.2d 940 (citing N.J.S.A. 2A:15-5.3(c)).]
Under Brodsky, a defendant against whom plaintiff had a potential claim, but who was shielded by bankruptcy law from liability for that claim, was nonetheless held to be an essential component of the jury’s assessment of fault under the Comparative Negligence Act. Ibid.
The Appellate Division has also considered the issue of apportionment in several settings. In Bencivenga v. J.J.A.M.M., Inc., 258 N.J.Super. 399, 406-08,
From the governing statutes and our case law, we can derive several guiding principles. First, the Comparative Negligence Act and the Joint Tortfeasors Contribution Law promote “the distribution of loss ‘in proportion to the respective faults of the parties causing that loss.’ ” Brodsky, supra, 181 N.J. at 114,
Second, our courts have barred apportionment where, as a matter of law, defendant could not under any circumstances be a joint tortfeasor under N.J.S.A 2A:53A-2. Brodsky, supra, 181 N.J. at 115,
Third, apportionment of fault under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law does not turn on whether the plaintiff is in a position to recover damages from the defendant at issue. Our courts have authorized a factfinder’s assessment of the fault of a defendant from whom the plaintiff is barred from recovering damages by virtue of bankruptcy, Brodsky, supra, 181 N.J. at 116,
Fourth, a claimant’s failure to conform to a statutory requirement for asserting claims against a given defendant does not necessarily bar apportionment of that defendant’s fault at trial. In Burt, supra, 339 N.J.Super. at 304,
Applied here, these principles require that we affirm the Appellate Division’s decision on the issue of apportionment. Allocation of fault to the dismissed defendants — who will, in any event, pay no damages — does not subvert the statute of repose’s purpose to
Accordingly, the Appellate Division properly reversed the trial court’s pretrial and trial orders denying the Brandt-Kuybida defendants’ applications for an allocation of fault to the SESI and Harrison-Hamnett defendants.
VI.
We affirm the judgment of the Appellate Division. We remand the matter to the trial court for a new trial on the issue of liability,
For affirmance and remandment — Chief Justice RABNER and Justices LaVECCHIA, ALBIN, HOENS, PATTERSON, Judges RODRÍGUEZ (temporarily assigned) and CUFF (temporarily assigned) — 7.
Opposed — None.
Notes
The Brandt-Kuybida defendants also asserted a defense based upon the ten-year statute of limitations that governs construction claims asserted by public entities, N.J.S.A. 2A:14-1.2. In this case, the parties stipulated that the statute of repose and statute of limitations were coextensive, and that the ten-year period for each commenced on the date of substantial completion. The Town did not assert that the discovery rule tolled the commencement of the statute of limitations in this case. See Rosenberg v. Town of N. Bergen, 61 N.J. 190, 195-98,
Although the trial court transcript reflects that the jury received a verdict sheet, the verdict sheet is not part of the record.
The Appellate Division affirmed the trial court's determination that fault could not be apportioned to the Town under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law, and that issue is not before this Court.
A motion for dismissal based on Rule 4:37-2(b) "requires essentially the same analysis” as a motion for summary judgment under Rule 4:46-2. Shelcusky v. Garjulio, 172 N.J. 185, 199,
The statute of repose does not protect parties who are "in actual possession and control [of the improvement] as owner, tenant, or otherwise” at the time that the defective and unsafe condition causes the injury or damage at issue. N.J.S.A. 2A: 14-1.1(a).
The statute was amended in May 2001, L. 2001, c. 76, § 1, but the changes as a result of that amendment are irrelevant here.
In Young, the Court emphasized the importance of timely notice to a plaintiff and any remaining defendants when a non-settling defendant seeks to prove the fault of a settling codefendant. Young, supra, 123 N.J. at 597,
The Town's awareness of construction defects during the ten-year statute of repose period distinguishes this case from Rosenberg. There, the plaintiff’s personal injury took place approximately thirty-three years after the road, that she alleged to have been negligently constructed, had been repaved. Rosenberg, supra, 61 N.J. at 193,
