delivered the opinion of the Court.
This construction dispute requires the Court to consider two issues: 1) when a building can be considered substantially complete for purposes of calculating the ten-year period of the statute of repose, N.J.S.A. 2A: 14-1.1(a), and 2) whether the Comparative Negligence Act, N.J.S.A. 2A:15-5.2, and the Joint Tortfeasors Contribution Law, N.J.S.A. 2A:53A-2, authorize allocation of fault at trial to defendants who have obtained dismissals pursuant to the statute of repose, N.J.S.A. 2A:14-l.l(a).
Following structural failures in its public safety facility, plaintiff Town of Kearny (Town) sued the project’s architectural firm, Brandt-Kuybida Architects (Brandt-Kuybida), and three of its individual architects, alleging that Brandh-Kuybida was liable for defects in the facility that rendered it unusable. The Town and Brandt-Kuybida filed claims against the project’s soil engineering firm, Soils Engineering Services, Inc. (SESI), and one of its individual engineers, and structural engineering firm, HarrisonHamnett, P.C. (Harrison-Hamnett), and its principal. The trial court granted summary judgment motions filed by SESI and Harrison-Hamnett on the ground that the Town’s complaint was filed more than ten years after the engineers completed their work on the construction project, ruling that the claims against these defendants were barred by the statute of repose and the statute of limitations. The trial court, however, denied a similar motion filed by the defendant architect, holding that the ten-year periods prescribed by the statutes of repose and limitations were triggered by the issuance of the first Temporary Certificate of Occupancy, and, accordingly, the Town’s claims against the architect were timely filed. The trial court also denied BrandtKuybida’s application for an apportionment of fault at trial to SESI and Harrison-Hamnett, pursuant to the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
The Town appealed. The Appellate Division affirmed the trial court’s application of the statutes of repose and limitations to Brandt-Kuybida but reversed the trial court’s denial of the architect’s application for an apportionment of fault to the dismissed codefendants.
We affirm. We hold that the trial court properly denied Brandt-Kuybida’s motion for summary judgment on the statute of repose issue. We concur with the trial court’s finding that the ten-year period prescribed in N.J.S.A. 2A:14-l.l(a) commenced when the first Temporary Certificate of Occupancy was issued for the Town’s public safety facility. We further hold that, when the claims against a defendant are dismissed on statute of repose grounds, fault may be apportioned to the dismissed defendant under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
I.
The South Kearny Improvement Projects Corporation (SKIP) was charged by the Town with the responsibility to oversee the design and construction of a new public safety facility, including police and fire stations. In October 1989, BrandWKuybida submitted a proposal to SKIP to design and plan the new facility. SKIP selected BrandWKuybida to perform the work. A principal of the firm, Louis Brandt, was initially designated as the lead architect. The Town and Brandt-Kuybida executed a contract on April 9, 1990. After Brandt-Kuybida dissolved in 1994, Michael Kuybida became the primary architect for the project.
SKIP chose Beleor Construction (Belcor) to build the facility in accordance with Brandt-Kuybida’s design, and, on July 11, 1994, SKIP and Belcor entered into a construction contract. Among other provisions, the construction contract required Belcor to achieve substantial completion of the project within 360 days of the issuance of a Notice to Proceed. That notice was issued on September 12, 1994. The contract between SKIP and Belcor defined substantial completion to be the date upon which the project architect, Brandt-Kuybida, certified that the facility is “sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.”
Construction of the facility began in the fall of 1994. On November 15,1995, Beleor signed a document entitled “Certificate of Substantial Completion” (Certificate). On November 24, 1995, Brandt-Kuybida and SKIP signed that same document. In language similar to that of the July 11, 1994 contract, the Certificate defined the date of substantial completion as “the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.” The signatories to the Certificate, however, failed to complete it. For reasons that the record does not disclose, the “date of issuance” and the “date of completion” of the project were left blank on the form.
According to a December 7, 1995 memorandum from Brandi Kuybida, a November 28,1995 inspection revealed that open items had to be completed and that, while municipal construction, fire and electrical approval had been obtained, approval for the facility’s plumbing was still pending. A December 4, 1995 punch list identified eleven outstanding items requiring additional work. On January 18, 1996, BrandWiuybida wrote to Belcor confirming the continued existence of open items and a pending plumbing inspection of the facility’s showers. It was not until April 5, 1996, that the Kearny Police Department requested permission to occupy its portion of the building. On April 9, 1996, the Town’s Construction Official issued the first Temporary Certificate of Occupancy, limited to the police section of the building and subject to completion of the items in a March 28, 1996 punch list. On May 23, 1996, the Construction Official issued the second Temporary Certificate of Occupancy, permitting the Kearny Fire Department to use its section of the building.
Structural defects in the facility surfaced shortly after the Kearny Police Department took occupancy. The building settled differentially, causing gaps between the ceiling and a wall, as well as leaks, buckled tiles and cracks in the walls. The Kearny Police Department reported leaks in various parts of the building and doors that could not close because they did not fit in their frames. Although the Town continued to use the facility, there were further complaints about structural flaws in the building. In 2003, the Town’s Construction Official received an emergency call that the ceiling in the police dispatch area of the building was about to collapse.
Belcor initiated arbitration proceedings against the Town because the Town withheld final payment under the contract. Belcor and the Town resolved their dispute by Stipulation of Settlement dated October 12, 1999. Both the Stipulation of Settlement and the related Town of Kearny Resolution 1999(R)-338 identified the date of substantial completion of the facility as February 1, 1996.
II.
On April 7, 2006, the Town filed an action in the Law Division, asserting negligence and breach of contract claims against Brandt-Kuybida and two of its principals, Louis Brandt and Michael Kuybida, and another architect, Robert Strebi (the Brandt-Kuybida defendants); negligence claims against Harrison-Hamnett and its principal, John N. Harrison (the HarrisonHamnett defendants); and negligence and breach of contract claims against SESI and one of its engineers, William St. Pierre (the SESI defendants). The Brandt-Kuybida defendants pled an affirmative defense based upon their right to seek apportionment of fault to all other parties who contributed to the incident. They also asserted a cross-claim against their codefendants, premised upon common-law indemnification and contribution pursuant to the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
The Brandt-Kuybida defendants filed a motion for summary judgment. They asserted, among other theories, that the statute of repose, N.J.S.A. 2A:14-l.l(a), barred the Town’s claims.
The trial court, however, granted summary judgment motions filed by the Harrison-Hamnett defendants and the SESI defendants. It held that the ten-year period set forth in the statute of repose commenced for the SESI defendants on the date that their involvement in the project ended, July 31, 1990, and that the statutory period commenced for the Harrison-Hamnett defendants on the date that their role in the project concluded, October 30, 1995. Consequently, the trial court held that the actions against the SESI and Harrison-Hamnett defendants were barred by both the statute of repose, N.J.S.A. 2A:14-l.l(a), and the statute of limitations, N.J.S.A 2A:14-1.2(a). In the wake of the trial court’s decision, the Brandt-Kuybida defendants were the only remaining defendants in the case.
The BrandL-Kuybida defendants filed a motion for leave to appeal the trial court’s order denying summary judgment. The Appellate Division granted the motion and summarily remanded the ease to the trial court for reconsideration in light of this Court’s decision in Daidone v. Buterick Bulkheading, 191 N.J. 557,
The case was tried before a jury for six days in October 2008. The trial court rejected the Brandt-Kuybida defendants’ argument that the date of substantial completion should be determined by the jury, and denied their motion to dismiss the Town’s claims on statute of repose grounds at the close of the Town’s case. In accordance with the trial court’s decision striking the Brandi Kuybida defendants’ apportionment defense, the jury considered only the fault of those defendants, not that of the codefendants previously dismissed on statute of repose grounds.
The Brandt-Kuybida defendants appealed. Analyzing the Comparative Negligence Act, the Joint Tortfeasor Contribution Law and the statute of repose, the Appellate Division reversed the trial court’s determination on the issue of apportionment. The panel held that the Legislature’s objective in promoting fair apportionment of liability under these statutes
We granted the Town’s petition for certification and the BrandWKuybida defendants’ cross-petition for certification. 209 N.J. 98,
III.
The parties dispute whether the trial court should have granted the Brandt-Kuybida defendants’ motion for summary judgment on the statute of repose. The Brandt-Kuybida defendants primarily rely upon the Certificate of Substantial Completion signed on November 15 and 24, 1995, contending that the latter date constitutes the operative date by which the construction was substantially complete. They contend that, if the Court does not accеpt November 24,1995, as the date of substantial completion, it should instead find February 1, 1996, to be the critical date, given the Town’s acknowledgement of that date in its Stipulation of Settlement with Belcor and the corresponding Town of Kearny Resolution 1999(R)-338. The Brandt-Kuybida defendants argue that in either case, the ten-year period prescribed by the statute of repose expired before the Town filed its complaint on April 7, 2006.
The Town argues that the trial court properly ruled that the date of substantial completion was April 9, 1996, when the first Temporary Certificate of Occupancy was issued. Although the Town concedes that parties to a construction dispute may stipulate to a date of substantial completion, it contends that there was no such stipulation in this ease. The Town asserts that because no agreed-upon date was included in the Certificate of Substantial Completion, that document lacked a material term and has no legal effect. The Town urges the Court to defer to the factual findings of the trial court regarding the actual date upon which work on the project had progressed to the point of substantial completion. It argues that the trial court correctly denied the BrandUKuybida defendants’ motion for summary judgment, because the action was timely filed.
With respect to the issue of apportionment, the Town argues that the Appellate Division erred when it reversed the trial court’s pretrial and trial orders and permitted the Brandb-Kuybida defendants to allocate fault to the SESI and Harrison-Hamnett defendants. The Town contends that, when the claims against an individual or entity are dismissed pursuant to the statute of repose, liability should not be apportioned to that individual or entity, because the Cоmparative Negligence Act, N.J.S.A 2A:15-5.2(a)(2), authorizes apportionment only to “the parties to a suit.” The Town argues that the SESI and Harrison-Hamnett defendants are distinguishable from various categories of parties to whom fault may be apportioned under our law. Instead, the Town likens the dismissed defendants in this case to an employer
The Brandb-Kuybida defendants counter that allocation of fault to the SESI and Harrison-Hamnett defendants is consistent with the protective goals of the statute of repose because those defendants would not be compelled to pay damages to the Town no matter what the outcome of a new liability trial. They argue, that by virtue of the trial court’s ruling, they were effectively penalized by thе Town’s failure to file a timely action against the SESI and Harrison-Hamnett defendants. The Brandb-Kuybida defendants contend that the dismissed codefendants in this case are analogous to settling defendants that cannot be sued by virtue of statutory immunity, and defendants who are dismissed because of a defect in the plaintiffs complaint, but are nonetheless considered in the allocation of fault. They urge the Court to affirm the Appellate Division’s order remanding the case for a new liability trial.
IV.
The first issue before the Court is whether the trial court properly denied the Brandt-Kuybida defendants’ motion for summary judgment and their motion to dismiss at the close of the Town’s case at trial based upon the statute of repose. We review de novo the grant or denial of a motion for summary judgment. Coyne v. State Dep’t of Transp., 182 N.J. 481, 491,
To the extent that the trial court’s ruling with respect to the statute of repose was premised upon factual findings, those findings are entitled to substantial deference on appellate review, and are not overturned if they are supported by “adequate, substantial, and credible evidence.” Pheasant Bridge Corp. v. Twp. of Warren, 169 N.J. 282, 293,
In 1967, “the Legislature enacted the statute [of repose] in response to the expanding application of the ‘discovery rule’ to new types of tort litigation, the abandonment of the ‘completed and accepted rule’ ... and the expansion of strict liability in tort for personal injuries caused by defects in new homes to builder/sellers of those homes.” Newark Beth Israel Med. Ctr. v. Gruzen & Partners, 124 N.J. 357, 362,
No action whether in contract, in tort, or otherwise to recover damages for any deficiency in the design, planning, supervision or construction оf an improvement to real property, or for any injury to property, real or personal, or for an injury to the person, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribulion or indemnity for damages sustained on account of such injury, shall be brought against any person performing or furnishing the design, planning, supervision of construction or construction of such improvement to real property, more than 10 years after the performance or furnishing of such services and construction.
[N.J.S.A. 2A:14-l.l(a).]6
The statute of repose is construed broadly to serve its legislative objective “of providing a reasonable measure of protection against expanding liability for design and construction professionals.” Newark Beth Israel, supra, 124 N.J. at 363,
Our case law distinguishes between defendant contractors who are hired to perform limited services and defendants with supervisory responsibilities that span the entire project, in determining the date upon which the ten-year period begins for purposes of N.J.S.A. 2A:14-l.l(a). For the former, the ten-year pеriod begins to run at the conclusion of the contractor’s specific task. As this Court held in Daidone, supra, 191 N.J. at 568,
For professionals such as the BrandL-Kuybida defendants, whose responsibilities for the Kearny public safety facility continued throughout its design and construction, the ten-year period set forth in N.J.S.A 2A:14-1.1(a) commences on the date of the project’s substantial completion. In Russo Farms, supra, 144 N.J. at 116-17,
[I]f liability were to be measured from the date the last retainage is released and all disputed and punch list items are completed, a contractor’s exposure to suit might be prolonged unreasonably. Disputes over workmanship and compensation for services сan continue for years____[A] contractor would remain liable and the commencement of the statute of repose could be delayed indefinitely. Such a result is inconsistent with the statutory purpose to provide repose and allow contractors and architects to walk away from liability at a certain point in time; indeed, it would, all too often, provide “liability for life.”
[Id. at 117-18,675 A.2d 1077 .]
Deferring to the construction industry’s standard practice of deeming a project complete, the Court held that “substantial completion” had occurred for statute of repose purposes “when the certificate of occupancy was issued and the architect certified to the owner that building was substantially completed.” Id. at 117,
This Court’s holdings in Russo Farms and Daidone support the determinations of the trial court and the Appellate Division in this ease. The trial and appellate courts agreed that the ten-year period prescribed by the statute of repose commenced on April 9, 1996, when the first Temporary Certificate of Occupancy was issued for the facility. As the trial court noted, this certificate indicated that the building was sufficiently complete so that it could be occupied and used. We agree and hold that the issuance of that certificate triggered the running of the ten-year period for purposes of the statute of repose under N.J.S.A. 2A:14-l.l(a).
While this Court in Russo Farms acknowledged the importance of the dаte of substantial completion as certified by a project’s lead architect, see Russo Farms, supra, 144 N.J. at 92-93, 117,
We also affirm the trial court’s finding with respect to the significance of the Stipulation аnd the Town of Kearny Resolution 1999(R) — 338 arising from the Town’s settlement with Belcor. These documents, which identify the date of substantial completion as February 1, 1996, represent neither a contemporaneous agreement between the Town and the Brandt-Kuybida defendants with respect to the operative date, nor the architect’s determination that the facility was substantially complete. The trial court’s rejection of February 1, 1996, as the date of substantial completion, for purposes of the dispute between the Town and the Brandt-Kuybida defendants, was amply supported by the evidence.
We affirm the trial court’s finding that the ten-year period of the statute of repose, N.J.S.A. 2A:14-l.l(a), commenced on April 9, 1996, when the first Temporary Certificate of Occupancy was issued. Accordingly, we hold that the Town’s action was timely filed against the BrandWEiuybida defendants. We affirm the Aрpellate Division’s determination that the trial court properly denied the Brandt-Kuybida defendants’ motion for summary judgment.
V.
We review de novo the Appellate Division’s decision reversing the trial court’s ruling on the issue of whether the jury should consider the SESI and Harrison-Hamnett defendants’ fault in its apportionment calculation. See Murray v. Plainfield Rescue Squad, 210 N.J. 581, 584,
The Comparative Negligence Act and the Joint Tortfeasors Contribution Law comprise the statutory framework for the allocation of fault when multiple parties are alleged to have contributed to the plaintiff’s harm. Under the Comparative Negligence Act, in negligence and strict liability actions in which “the question of liability is in dispute,” the trier of fact makes the following findings of fact:
(1) The amount of damages which would be recoverable by the injured party regardless of any consideration of negligence or fault, that is, the full value of the injured pаrty’s damages.
(2) The extent, in the form of a percentage, of each party’s negligence or fault. The percentage of negligence or fault of each party shall be based on 100% and the total of all percentages of negligence or fault of all the parties to a suit shall be 100%.
[N.J.S.A. 2A:15-5.2(a).]
In practice, the Comparative Negligence Act requires the fact-finder to assign to each party on the verdict sheet a percentage of fault, with the percentages assigned to each party adding up to 100%. N.J.S.A. 2A: 15-5.2(a)(2). With the factfinder’s task complete, ‘Ttjhe judge shall mold the judgment from the findings of fact made by the trier of fact.” N.J.S.A. 2A:15-5.2(d). In accordance with N.J.S.A. 2A:15-5.3(a), if a defendant’s fault is assessed at sixty percent or more, the plaintiff may recover the
The Joint Tortfeasors Contribution Law plays a complementary role in the statutory scheme. Under that statute, a party that is liable for more than the percentage share of the damage award that is assessed by the factfinder may have contribution rights against other parties. N.J.S.A. 2A:53A-3. The statute “was enacted to promote the fair sharing of the burden of judgment by joint tortfeasors and to prevent a plaintiff from arbitrarily selecting his or her victim.” Holloway v. State, 125 N.J. 386, 400-01,
This case requires us to determine whether the terms “eaсh party” and “all the parties to a suit,” as used in the Comparative Negligence Act, N.J.S.A. 2A:15-5.2(a)(2), encompass defendants who have been granted dismissals pursuant to the statute of repose, N.J.S.A. 2A:14-l.l(a). Established principles of statutory construction direct that we determine the Legislature’s intent, considering first the statute’s plain language. Brodsky v. Grinnell Haulers, Inc., 181 N.J. 102, 109-10,
When interpreting multiple statutes governing the same subject, the Court should attempt to harmonize their provisions. Saint Peter’s Univ. Hosp. v. Lacy, 185 N.J. 1, 14-15,
We previously have not determined whether the Comparative Negligence Act and the Joint Tortfeasors Contribution Law authorize allocation of fault to a defendant who obtains a dismissal by virtue of the statute of repose. This Court and the Appellate Division, however, have analyzed these comparative fault statutes in cases in which the claims against some defendants have been dismissed on other grounds, either prior to or during trial.
The Appellate Division in Ramos v. Browning Ferris Industries of South Jersey, Inc., 194 N.J.Super. 96, 106,
This Court reached a different conclusion when the defendant at issue was not protected by statutory immunity but was dismissed from the case by virtue of a settlement. In Young v. Latta, 123 N.J. 584, 585,
Thus, when a defendant ceases to participate in the case by virtue of a settlement, a non-settling defendant who meets the relevant requirements as to notice and proof may obtain an allocation of fault to the settling defendant. See Young, supra, 123 N.J. at 596-97,
This Court’s most recent exploration of the allocation issue arose from the bankruptcy of an uninsured driver alleged to have been partly responsible for the plaintiff’s injuries in a motor vehicle accident. In Brodsky, supra, 181 N.J. at 116,
We hold that the triеr of fact must determine the percentage of fault or negligence of a party dismissed from a negligence action following that party’s discharge in bankruptcy. .. That conclusion assures that defendants are not deprived of the benefits of the Comparative Negligence Act, namely their right to be held accountable only for their percentage of fault, provided that portion is less than sixty percent.
[Id. at 116,853 A.2d 940 (citing N.J.S.A. 2A:15-5.3(c)).]
Under Brodsky, a defendant against whom plaintiff had a potential claim, but who was shielded by bankruptcy law from liability for that claim, was nonetheless held to be an essential component of the jury’s assessment of fault under the Comparative Negligence Act. Ibid.
The Appellate Division has also considered the issue of apportionment in several settings. In Bencivenga v. J.J.A.M.M., Inc., 258 N.J.Super. 399, 406-08,
Second, our courts have barred apportionment where, as a matter of law, defendant could not under any circumstances be a joint tortfeasor under N.J.S.A 2A:53A-2. Brodsky, supra, 181 N.J. at 115,
Third, apportionment of fault under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law does not turn on whether the plaintiff is in a position to recover damages from the defendant at issue. Our courts have authorized a factfinder’s assessment of the fault of a defendant from whom the plaintiff is barred from recovering damages by virtue of bankruptcy, Brodsky, supra, 181 N.J. at 116,
Fourth, a claimant’s failure to conform to a statutory requirement for asserting claims against a given defendant does not necessarily bar apportionment of that defendant’s fault at trial. In Burt, supra, 339 N.J.Super. at 304,
Applied here, these principles require that we affirm the Appellate Division’s decision on the issue of apportionment. Allocation of fault to the dismissed defendants — who will, in any event, pay no damages — does not subvert the statute of repose’s purpose to give construction defendants “the right not to have to defend ancient claims or obligations.” Cyktor v. Aspen Manor Condo. Ass’n, 359 N.J.Super. 459, 470,
Accordingly, the Appellate Division properly reversed the trial court’s pretrial and trial orders denying the Brandt-Kuybida defendants’ applications for an allocation of fault to the SESI and Harrison-Hamnett defendants.
VI.
We affirm the judgment of the Appellate Division. We remand the matter to the trial court for a new trial on the issue of liability, including apportionment of fault to the BrandL-Kuybida, SESI and Harrison-Hamnett defendants.
For affirmance and remandment — Chief Justice RABNER and Justices LaVECCHIA, ALBIN, HOENS, PATTERSON, Judges RODRÍGUEZ (temporarily assigned) and CUFF (temporarily assigned) — 7.
Opposed — None.
Notes
The Brandt-Kuybida defendants also asserted a defense based upon the ten-year statute of limitations that governs construction claims asserted by public entities, N.J.S.A. 2A:14-1.2. In this case, the parties stipulated that the statute of repose and statute of limitations were coextensive, and that the ten-year period for each commenced on the date of substantial completion. The Town did not assert that the discovery rule tolled the commencement of the statute of limitations in this case. See Rosenberg v. Town of N. Bergen, 61 N.J. 190, 195-98,
Although the trial court transcript reflects that the jury received a verdict sheet, the verdict sheet is not part of the record.
The Appellate Division affirmed the trial court's determination that fault could not be apportioned to the Town under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law, and that issue is not before this Court.
A motion for dismissal based on Rule 4:37-2(b) "requires essentially the same analysis” as a motion for summary judgment under Rule 4:46-2. Shelcusky v. Garjulio, 172 N.J. 185, 199,
The statute of repose does not protect parties who are "in actual possession and control [of the improvement] as owner, tenant, or otherwise” at the time that the defective and unsafe condition causes the injury or damage at issue. N.J.S.A. 2A: 14-1.1(a).
The statute was amended in May 2001, L. 2001, c. 76, § 1, but the changes as a result of that amendment are irrelevant here.
In Young, the Court emphasized the importance of timely notice to a plaintiff and any remaining defendants when a non-settling defendant seeks to prove the fault of a settling codefendant. Young, supra, 123 N.J. at 597,
The Town's awareness of construction defects during the ten-year statute of repose period distinguishes this case from Rosenberg. There, the plaintiff’s personal injury took place approximately thirty-three years after the road, that she alleged to have been negligently constructed, had been repaved. Rosenberg, supra, 61 N.J. at 193,
