OPINION ON REHEARING
I. Introduction
After considering Appellants’ motion for rehearing, we deny the motion but withdraw our prior opinion and judgment of December 8, 2011, and substitute the following.
In this interlocutory appeal, Appellants Town of Flower Mound, Texas; Harlan Jefferson, Town Manager; and Charles
II. Background
Rembert is the developer of a residential subdivision in Flower Mound (the Property). When Rembert applied to Flower Mound for approval of its development permits, Flower Mound required Rembert to construct Auburn Drive on the property and other land Rembert did not initially own as a condition of approval. Rembert and Flower Mound thereafter entered into three separate development agreements, and Rembert constructed Auburn Drive as set forth in those agreements. Flower Mound paid Rembert fifty percent of the Auburn Drive construction cost, but Rem-bert alleges in its third amended petition that the August 4, 2008 Development Agreement (the Agreement) required Flower Mound to reimburse Rembert the full cost of constructing Auburn Drive through a combination of impact fee credits and direct reimbursement. Rembert alleges that Flower Mound’s failure to fully reimburse the Auburn Drive construction costs is a breach of the Agreement or, alternatively, constitutes a compensable taking. Rembert further seeks judicial declarations (1) that the Impact Fee Act,
Appellants answered Rembert’s petition and filed a plea to the jurisdiction that they amended on two occasions. The trial court conducted an evidentiary hearing on Appellants’ second amended plea to the jurisdiction and granted the plea in part. Appellants appeal the trial court’s partial denial of their plea to the jurisdiction, and Rembert appeals the trial court’s partial grant of Appellants’ plea.
III. Standard of Review
Whether the trial court had subject matter jurisdiction is a question of law that we review de novo. Tex. Natural Res. Conservation Comm’n v. IT-Davy,
“[Sovereign immunity deprives a trial court of subject matter jurisdiction for lawsuits in which the state or certain governmental units have been sued[,] unless the state consents to suit.”
When a governmental entity such as Flower Mound enters into a contract, it waives immunity from liability but does not waive immunity from suit unless the legislature has clearly and unambiguously waived the governmental entity’s immunity from suit. Tooke,
IV. Breach of Contract
Appellants contend in their third issue that the trial court does not have subject matter jurisdiction over Rembert’s breach of contract claim because the Agreement does not involve the provision of goods and services as required for a waiver of immunity under local government code chapter 271.
Section 271.152 of the local government code states:
A local governmental entity that is authorized by statute or the constitution to enter into a contract and that enters into a contract subject to this subchapter waives sovereign immunity to suit for the purpose of adjudicating a claim for breach of the contract, subject to the terms and conditions of this subchapter.
Tex. Loe. Gov’tCode Ann. § 271.152 (West 2005). A “[c]ontract subject to this sub-chapter” is defined, in relevant part, as “a written contract stating the essential terms of the agreement for providing goods or services to the local governmental entity.” Id. § 271.151(2) (West 2005).
Appellants argue that, even though Rembert used goods and services to construct Auburn Drive, the Agreement is not a contract for “goods or services” because it is ultimately a contract for the conveyance of improved real property.
In Ben Bolt, ninety-two governmental entities formed an insurance fund to provide casualty insurance to fund participants. See
In Kirby Lake, several developers entered into agreements with the Clear Lake Water Authority.
We agree with the court of appeals that the Agreements entail services provided directly to the [Water] Authority.The Developers contracted to construct, develop, lease, and bear all risk of loss or damage to the facilities, obligations far more concrete than those at issue in Ben Bolt. We therefore hold that the Agreements contemplate the provision of services under the statute.
Kirby Lake,
In this case, the Agreement required Rembert to “construct Auburn Drive ... together with all related appurtenances in addition to all other facilities necessary to serve the Property,” to “acquire in fee simple all rights-of-way necessary for the Right-Turn Lane,” to “design and construct the Right-Turn Lane in accordance with [Flower Mound]’s engineering standards,” and to “work with TxDOT and [Flower Mound] to determine the proper location and alignment of the Right-Turn Lane.” Clearly, the Agreement required Rembert to provide services to Flower Mound in the manner, at least, of constructing Auburn Drive; designing and constructing the Right-Turn Lane; and working with TxDOT concerning the location, alignment, design, and construction of the Right-Turn Lane. See id. at 839-40; Ben Bolt,
Appellants attempt to distinguish Ben Bolt, Kirby Lake, and other similar cases by arguing that the contracts at issue in those cases differ from the contract at issue here because the contract here is “nothing more than a restatement of independent obligations that Rembert must undertake under the Town’s development regulations as part of the land-development process.” However, Appellants’ argument requires a close examination of the merits of Rembert’s lawsuit beyond a review of Rembert’s pleadings and the jurisdictional evidence, an inquiry the supreme court has cautioned against. See Bland,
We hold, based on Rembert’s third amended petition and the parties’ plea to the jurisdiction evidence, that local government code section 271.152 waives Flower Mound’s immunity from suit with regard to the Agreement because the Agreement is a contract for the provision of services to Flower Mound within the meaning of that statute. See Tex. Loc. Gov’t Code Ann. §§ 271.151(2), .152; Kirby Lake,
V. Declaratory Judgment and Individual Defendants
Appellants contend in their first and fifth issues that the trial court did not have subject-matter jurisdiction over Rembert’s requested declarations because they are nothing more than a restatement of Rem-bert’s breach of contract claim and because Jefferson and Springer have derivative immunity. Appellants argue in part of their fourth issue that Rembert may not recover attorney’s fees for declaratory judgment claims over which the trial court did not have subject-matter jurisdiction. Because Appellants’ first, fourth, and fifth issues are related, we address them together.
A. Applicable Law
The Declaratory Judgments Act contains a waiver of immunity from suit. See Tex. Civ. Prac. & Rem.Code Ann. § 37.006(b) (West 2008); City of El Paso v. Heinrich,
Immunity from suit is waived if a party joins a governmental entity and seeks a declaration that an ordinance or statute is invalid, based on either constitutional or nonconstitutional grounds. See Heinrich,
“Private parties may seek declaratory relief against state officials who allegedly act without legal or statutory authority!,]” but “such suits are not suits against the State” because “suits to compel state officers to act within their official capacity do not attempt to subject the State to liability.” IT-Davy,
B. Discussion
In its third amended petition, Rembert requested a judicial declaration that the Impact Fee Act, the Agreement, and Flower Mound’s ordinances required Flower Mound to “reimburse Rembert for 100% of the cost to construct Auburn Drive” and that Flower Mound, “Jefferson!,] and Springer had a ministerial obligation to forward the sums owed to [Rembert], and their refusal to do so was unauthorized and illegal.” However, Rembert similarly alleged in its third amended petition that Flower Mound breached the Agreement and that Rem-bert is therefore entitled to recover the amount Flower Mound owed it under the Agreement. Rembert’s requested declarations merely recast Rembert’s claim for breach of the Agreement. See IT-Davy,
Rembert attempts to distinguish its declaratory judgment claim from its breach of contract claim by arguing that a judicial interpretation of the Impact Fee Act and Flower Mound ordinances is required to determine whether Flower Mound is required to reimburse Rembert fifty or one hundred percent of the cost of constructing Auburn Drive. “But in every suit against a governmental entity for money damages, a court must first determine the parties’ contract or statutory rights; if the sole purpose of such a declaration is to obtain a money judgment, immunity is not waived.” Williams,
Rembert also contends that Flower Mound’s immunity has been waived because governmental entities must be joined in suits to construe their legislative pronouncements. But as previously discussed, the construction of the ordinances will occur as part of and is arguably dis-positive of Rembert’s breach of contract claim against Flower Mound, and Flower Mound is already a party to the case for that purpose. Furthermore, Rembert’s reliance on City of Crowley v. Ray is misplaced because that case involved a claim for liability against a third-party engineer rather than the city; the city was a party only because the construction of city documents was at issue and pertained to the engineer’s potential liability. See No. 02-09-00290-CV,
Appellants further contend that because the trial court lacked subject-matter jurisdiction over Rembert’s claim for declaratory relief against it, the trial court also lacked subject-matter jurisdiction over the claims against Jefferson and Springer. Rembert, citing Heinrich,
Because we have held that the trial court did not have subject-matter jurisdiction over Rembert’s declaratory judgment claims, we also sustain the portion of Appellants’ fourth issue relating to Rembert’s claim for attorney’s fees based on its request for declaratory judgment. See Home Town,
VI. Impact Fee Act Claim
Appellants argue in their second issue and the remainder of their fourth issue that the trial court did not have subject-matter jurisdiction over Rembert’s Impact Fee Act claim or Rembert’s corresponding request for attorney’s fees. However, Rembert unequivocally pleaded in the trial court and asserted in its appellate brief that it does not allege a claim under the Impact Fee Act, and we do not read Rem-bert’s third amended petition to assert a claim under the Impact Fee Act.
VII. Inverse Condemnation
Rembert contends in its sole cross-issue that the trial court erred by granting Appellants’ plea to the jurisdiction as to Rem-bert’s inverse condemnation claim.
A. Applicable Law
A prohibition against taking private property for public use without just compensation is set forth in article I, section 17 of the Texas constitution, which provides that “[n]o person’s property shall be taken, damaged, or destroyed for or applied to public use without adequate compensation being made, unless by the consent of such person.” Tex. Const, art. I, § 17; see Mayhew v. Town of Sunnyvale,
As stated by the supreme court in Stafford,
conditioning government approval of a development of property on some exaction is a compensable taking unless the condition (1) bears an essential nexus to the substantial advancement of some legitimate government interest and (2) is roughly proportional to the projected impact of the proposed development.
Town of Flower Mound v. Stafford Estates, L.P.,
B. Discussion
In its third amended petition, Rembert alleged that “the number of vehicular trips from the houses in the Subdivision represent 5% or less of the capacity of the roadways Rembert was required to construct by [Flower Mound],” that “Rembert was coerced into signing (and did not consent to) the boilerplate waiver and release language to the extent [Flower Mound] was considering paying Rembert less than 100% of the Auburn Drive costs,” and that “Rembert’s understanding at the time the Agreement was signed was that Rembert would be reimbursed or credited 100% of the roadway construction costs based on the express terms of the Agreement and Chapter 42-78 of the [Flower Mound] Code.” Rembert also alleged as follows:
In the alternative, the construction cost required of Rembert for roadways related to the Subdivision does not meet the proportionality requirement for an exaction under Article I, Section 17 of the Texas Constitution. Rembert is entitled to recover from [Flower Mound] the total street construction costs incurred by Rembert related to the Subdivision (or at a minimum, 95% of the cost). [Flower Mound] does not enjoy immunity from constitutional violations for illegal exactions.
Under facts very similar to this case, the supreme court held in Stafford that Flower Mound was required to compensate Stafford for the cost of rebuilding a road abutting but not within Stafford’s development. See id. at 645. Flower Mound, as a condition of its approval of the plats for the second and third phases of Stafford’s development, required Stafford to rebuild the asphalt road next to the development. Id. at 623. Stafford objected, rebuilt the road as Flower Mound required, and sued Flower Mound for compensation. Id. at 624. After a lengthy discussion of the United States Supreme Court’s opinions in Nollan and Dolan and after rejecting Flower Mound’s attempts to distinguish those cases, the Stafford Court agreed that Flower Mound advanced legitimate government interests — such as the safety and durability of the road — by requiring Stafford to rebuild the road. Id. at 643-44. However, the court also held that Flower Mound failed to show that the required rebuild of the road bore “any relationship to the impact of the Stafford Estates de
On this record, conditioning development on rebuilding Simmons Road with concrete and making other changes was simply a way for the Town to extract from Stafford a benefit to which the Town was not entitled. The exaction the Town imposed was a taking for which Stafford is entitled to be compensated.
Id. Relying on Stafford, Rembert argues that the trial court erred by granting Appellants’ plea to the jurisdiction as to its inverse condemnation claim.
Appellants argue that Stafford is distinguishable because it “involved an off-site road improvement obligation, not an internal subdivision road.” But Appellants omit that Flower Mound required Rem-bert to not only build Auburn Road to connect F.M. 1171 and Peters Colony Road but also to acquire the land necessary to do so in the manner that Flower Mound required instead of permitting Rembert to build two points of egress on the land it already owned and that abutted those two roads. In other words, Flower Mound’s requirement that Rembert acquire additional land and construct Auburn Drive is not “the garden-variety on-site requirement” that Appellants contend it to be.
In a further attempt to distinguish Stafford, Appellants argue that the evidence that the development’s use of Auburn Drive will not exceed five percent of its capacity is not evidence of how much traffic from the development will use Auburn Drive now or in the future. Appellants posit that the development could hypothetically account for seventy-five percent of the traffic on Auburn Drive but still account for less than five percent of Auburn Drive’s capacity.- But Appellants ignore other evidence in the record that, combined with the five percent capacity evidence, presents an issue for the factfinder. For example, there is evidence that Auburn Drive was a fee-impact eligible road and that Flower Mound “anticipated that the construction of Auburn Drive would likely be necessary within the upcoming 10-year window as a roadway improvement.” While this certainly did not guarantee that Flower Mound would in fact build Auburn Drive, this evidence, combined with the evidence that the development would use only five percent or less of Auburn Drive’s capacity, presents a fact question on the proportionality prong of Rembert’s takings claim.
Appellants also argue that the trial court properly dismissed Rembert’s takings claim because Rembert consented to the alleged taking. A landowner may consent to property being taken or damaged without payment of any compensation. Tex. Const, art. I, § 17; Hale v. Lavaca Cnty. Flood Control Dist.,
Finally, Appellants contend that Flower Mound did not have the requisite intent required to support a takings claim because a breach of contract cannot result in a taking. We disagree for two reasons. First, Rembert clearly pleaded its inverse condemnation claim in the alternative to its breach of contract claim. See Tex.R. Civ. P. 48 (permitting parties to plead alternative, inconsistent claims for relief). Should the trial court determine that the Agreement and Flower Mound’s ordinances required Flower Mound to reimburse Rembert only fifty percent of the Auburn Drive construction cost, Rembert’s inverse condemnation claim would not rely on the Agreement as a basis of liability. See generally Sefzik,
Second, the cases upon which Appellants rely are distinguishable. For example, the claimants in Kirby Lake contractually agreed that the Water Authority could use the facilities for free until the Water Authority purchased the facilities and thus could not claim that the Water Authority’s use of the facilities constituted a taking. See
Here, there is evidence, some of it conflicting, that the construction of Auburn Drive may or may not have been required by Flower Mound’s ordinances, that Flower Mound conditioned approval of Rem-bert’s development on Rembert’s construction of Auburn Drive, that only then did the parties enter into a development agreement, and that Rembert never consented to building Auburn Drive without receiving full reimbursement. Should Appellants prevail on their contention that the Agreement and Flower Mound’s ordinances limit Rembert’s reimbursement to fifty percent, Rembert should be permitted to proceed on its alternative claim that Flower Mound’s ordinances and resulting development condition constituted a com-pensable taking. See generally Stafford,
On this record, given the conflicting evidence and the alternative nature of Rem-bert’s inverse condemnation claim, we hold that the trial court erred by granting Appellants’ plea to the jurisdiction as to Rem-bert’s alternatively pleaded inverse condemnation claim. See Tex.R. Civ. P. 48; see also Stafford,
VIII. Conclusion
Having overruled Appellants’ second and third issues and part of their fourth issue, we affirm in part the trial court’s denial of Appellants’ plea to the jurisdiction. • Having sustained Rembert’s sole cross-issue, we reverse the part of the trial court’s order that granted Appellants’ plea to the jurisdiction as to Rembert’s inverse condemnation claim. Finally, having sustained Appellants’ first and fifth issues and part of their fourth issue, we reverse in part the trial court’s order denying Appellants’ plea to the jurisdiction and dismiss for lack of subject-matter jurisdiction Rembert’s request for judicial declarations
Notes
. See Tex. Civ. Prac. & Rem.Code Ann. § 51.014(a)(8) (West Supp.2011) (permitting interlocutory appeal from an order granting or denying a plea to the jurisdiction filed by a governmental unit).
. See Tex. Loc. Gov't Code Ann. §§ 395.001-.021 (West 2008), .022 (West Supp.2011); .024-,079 (West 2008), .081 (West Supp.2011).
. Courts often use the terms interchangeably, but governmental, rather than sovereign, immunity is at issue in this case. See Tooke v. City of Mexia,
. See, e.g., Brown Water Marine Serv., Inc. v. Aransas Cnty. Navigation Dist. No. 1, No. 13-07-00055-CV,
. Appellants argue that "Rembert fails to distinguish between the existing road conditions suitable for the existing Country Meadow Estates Mobile Home Park located on the Property and the road access needed for the proposed 52-lot Casa de Rembert residential subdivision.” But this is a question of fact for the factfinder.
. We do not imply that the factfinder will or should make this determination and note only that it is one possibility.
. Rembert pleaded in its third amended petition that it "is not seeking an impact fee refund under § 395.025, Tex. Loc. Govt. Code” and wrote in its appellate brief that "Rembert is not making a 'claim' under Chapter 395.”
. Stafford had offered evidence that its development would increase traffic on the road by only about eighteen percent. Id. at 644.
. The parties do not dispute that the construction of Auburn Drive served legitimate government interests, the first prong of the takings analysis. See id. at 634.
. Some of the e-mails do support Appellants’ contention that all reimbursement to Rembert could not exceed fifty percent of the construction cost, but Rembert was not a sender or recipient of those e-mails.
. Also, we note that neither Stafford nor Rischon was decided after a pretrial plea to the jurisdiction and that Appellants resisted responding to discovery in this case before the trial court ruled on its plea to the jurisdiction. See Stafford,
