30 Ind. App. 490 | Ind. Ct. App. | 1903
The court below sustained appellees’ demurrer to appellant’s complaint, and rendered judgment against appellant, from which it prosecutes this appeal. The only error assigned is based on this decision of the court below.
The complaint alleges, in substance, that the appellees, Ida L. and Richard Bryson, were the owners of a certain lot in appellant town; that the board of trustees of said town, by an ordinance duly adopted, ordered a sidewalk constructed adjacent to said lot, along a street upon which said lot abuts, specifying the kind of walk to be constructed and the time in which the same must be completed, and providing that if the owners of the lots abutting on the proposed sidewalk did not construct the same within the time specified, then the construction thereof would be let to the lowest bidder, after due notice thereof, by notices posted in said town; that the appellees were duly notified of the provisions of said ordinance, but failed and refused to comply therewith, and failed‘to construct the sidewalk within the time specified; that after the lapse of time in which it was required that said waljs: should be constructed, as aforesaid, the marshal of said town, pursuant to the order of the board of trustees thereof,' duly advertised for bids for the construction of said walk; that diligent efforts were made to secure bidders, but that no one could be induced to bid on said work, and no bids.were received on the work; that being unable to secure any one to bid on said work the. board of trustees of said town, by proper resolution, ordered said marshal to procure material, employ men, and construct the sidewalk, which he did; that said sidewalk was constructed and completed in all respects in accordance with the specifications adopted therefor, and the labor and material were paid for by said town, and that said town has never been reimbursed for said expenditure, though often demanded from appellees. It is further alleged that said appellees, during the time said ordinance was being passed, and at,
The action is based upon §§4394-4397 Burns 1901. Section 4396 provides how said work shall be done if the lot owner fails to do it within the time prescribed by the ordinance. It makes it the duty of the town marshal forthwith to let out the grading, paving, or planking of such walk to the lowest bidder, first giving ten days’ notice by posting up written notices thereof in three public places in such town for that length of time; and when such grading, paving, or planking is completed said marshal shall report the same to said board of trustees, and the cost of such work shall be audited and paid out of the treasury of such town, as other claims against said corporation are audited and paid. The next section (4397) provides how said costs shall be collected by proceedings to foreclose a lien on said property therefor. The complaint avers that the-owners (appellees) did" not perform the work within the time fixed by the ordinance. It avers that after the expiration of the time fixed for appellees to do the work the marshal advertised for bids, and no bids were received, and the trustees then, ordered the marshal to do the work, and he did, and reported the cost to be $90.36, which appellant paid, and now seeks to enforce said claim against appellees and their property. These statutes do not authorize the trustees to direct the marshal to1 do the work after’ failing to receive bids.
The questions presented and discussed then on this appeal are: (1) Whether the action of the town in directing the performance of the work iii disregard of the provision of the statute is a defense to the cause of action; (2) are appellees estopped to assert such defense under the facts alleged in- the complaint ?
Appellant was without authority to direct the marshal to do the work after a failure to obtain bids. The board of trustees of incorporated towns can exercise only the powers in respect to sidewalks or street improvements expressly conferred by statute. Town of Marion v. Skillman, 127 Ind. 130, 139, 140, 11 L. R. A. 55; Case v. Johnson, 91 Ind. 477, 491, 492; Town of Tipton v. Jones, 77 Ind. 307, 314; Moore v. Cline, 61 Ind. 113; Anthony v. Cooley, 61 Ind. 323; Merrill v. Abbott, 62 Ind. 549; Overshiner v. Jones, 66 Ind. 452; Smith v. Duncan, 77 Ind. 92; Gas Light, etc., Co. v. City of New Albany, 156 Ind. 406, and authorities cited; Spaulding v. Baxter, 25 Ind. App. 485, 493, 494.
There must be at least a substantial compliance with the statute, or the proceeding will be held “invalid, illegal, and void.” Case v. Johnson, supra; Wilson v. Poole, 33 Ind. 443; Moberry v. City of Jeffersonville, 38 Ind. 198; Merrill v. Abbott, supra.
In the recent work of Smith, Munic. Corp., §1242, it is said: “In order to charge the owners of property with the cost of an improvement, the power must not only be expressly conferred by law, but the provisions of the law must be strictly pursued. The successive steps to be taken preliminary to ordering the work done, the manner of letting the contract and the mode of constructing the improvement, when provided for in the law, are intended for the protection of the property owner and are his safeguards against the exercise of arbitrary power. Each act required to be
The proposition of counsel for appellant is that under the statute the 'appellant had the right to make the improvement; it had jurisdiction of the subject-matter and of the appellees, and that by reason of such jurisdiction the decision o-f all other questions arising in the proceedings was but the exercise of jurisdiction; that the manner in which the work was done was a mere irregularity; that under such circumstances the owner who sees the improvement made, and offers no objection until the work is done, can not defeat the assessment upon the ground of irregularity. Numerous cases are cited for the purpose of sustaining the position. We do not deem it necessary to discuss them. The weight of the authorities requires a substantial compliance with the statute. The letting of the contract was essential to the exercise of juris diction. The complaint affirmatively shows that, in a proceeding under the statute to charge the property of the appellee with a burden for the public benefit, the requirements of the law as to the exercise of power were disregarded; no bids were made; no contract let.
It is claimed, under the averments of the complaint, that appellees, during the time said ordinance was being passed, and at the time the work was being done,. were
Judgment affirmed.