MEMORANDUM AND ORDER ON STATE DEFENDANTS’ MOTION TO DISMISS
This Cоmplaint is the latest chapter in a long-running saga involving the siting of a wind farm in Nantucket Sound. The dispute pits the Commonwealth of Massachusetts and the diversified energy policy espoused by Governor Deval Patrick against an obdurate band of aggrieved residents of Cape Cod and the Islands. Both sides in the dispute claim the mantle of environmentalism, although for present purposes, plaintiffs
Cape Wind is a for-profit company with plans to develop a wind-powered renewable energy generation facility in federal waters in Nantucket Sound, a triangular-shaped 750 square-milе tract of the Atlantic Ocean bounded by Cape Cod and the Islands of Martha’s Vineyard and Nantucket. The proposed wind facility is to consist of 130 horizontal-axis wind turbines dispersed over 24 square miles of open ocean, and is designed to generate 454 megawatts of electricity at peak operation.
In 2001, Cape Wind applied for a permit to build the wind facility on Horseshoe Shoals in the Sound, some five miles from the Cape Cod coastline and roughly 16 miles from the Town of Nantucket. In August of 2002, the U.S. Army Corps of Engineers granted Cape Wind a permit to build a meteorological tower to gather data in preparation for the project. As Judge Tauro presciently predicted in rejecting a suit against the Corps of Engineers’ action, this was just “the first skirmish in an eventual battle.” Ten Taxpayers Citizen Grp. v. Cape Wind Assocs., LLC,
In 2005, the Massachusetts Energy Facilities Siting Board approved the construction of two undersea electric transmission cables to connect the proposed wind facility with the regional power grid. The Alliance promptly filed suit protesting the approval.
In April of 2010, Kenneth Salazar, the United States Secretary of the Interior, issued a Record of Decision giving federal approval to the Cape Wind project.
The Green Communities Act
In 2008, the Massachusetts Legislature passed the Green Communities Act (GCA), Mass. St.2008, ch. 169.
As originally enаcted, the GCA contained a provision requiring that all eligible alternative energy suppliers be located within Massachusetts or its adjacent state and federal waters. On June 9, 2010, the DPU suspended the territorial restriction
The National Grid — Cape Wind Contract
In December of 2009, National Grid, a competitor of defendant NSTAR, sought approval from the DPU to enter into negotiations with Cape Wind over a long-term energy-supply contract.
Two separate avenues of appeal were taken from DPU’s approval of the National Grid contract. The Alliance (along with TransCanada) appealed directly to the SJC, asserting, among other claims, that DPU’s approval of the contract violated the dormant Commerce Clause. The SJC rebuffed the objections and affirmed DPU’s decision, specifically rejecting the dormant Commerce Clause claim. See Alliance, 461 Mass, at 174,
After the suspension of the geographical limitation, DPU had directed NSTAR and other utilities to reopen their Requests for Proposals (RFPs) to take bids from out-of-state generators. Compl. ¶ 58. NSTAR did so and ultimately contracted with three land-based wind generators, Groton Wind, LLC, New England Wind, LLC, and Blue Sky East, LLC. Id. ¶ 54. Plaintiffs allege that the price of wind energy from NSTAR’s contracts with the three land-based generators was approximately one-half the initial price agreed to by National Grid in its contract with Cape Wind. Id. ¶¶ 55-57. NSTAR chose not to enter a contract with Cape Wind. Id. ¶ 56. Plaintiffs allege that NSTAR’s “refusal” to contract with Cape Wind threatened the very existence of the project because National Grid had secured DPU approval to distribute only half of the wind farm’s output (the second National Grid contract, for the remaining 50% had been rejected by the DPU). Id. ¶ 58.
On November 24, 2010, NSTAR filed an application with DPU for approval of a merger between it and Northeast Utilities.
In July of 2011, DOER asked the DPU to stay the merger pending an assessment of its potential impact on consumers. NSTAR and Northeast argued that a stay would derail the merger. Compl. ¶ 68. On September 28, 2011, DOER submitted a filing urging DPU to require NSTAR to purchase off-shore wind energy as a condition for approving the merger. Id. ¶ 70. NSTAR and Northeast opposed the request, arguing a potential violation of the dormant Commerce Clause as Cape Wind appeared to be the only viable off-shore wind developer. Plaintiffs allege that NSTAR representatives subsequently entered into “secret negotiations with the Patrick Administration.” Id. ¶ 75. On February 15, 2012, NSTAR and DOER entered into a settlement agreement, which included a condition that NSTAR pursue a PPA with Cape Wind on terms that were “substantially the samе” as those of the National Grid-Cape Wind contract. The settlement agreement was subject to DPU approval.
On March 23, 2012, NSTAR and Cape Wind executed a PPA under which NSTAR agreed to purchase energy, capacity, and renewable power certificates from Cape Wind over a 15-year period. Compl. ¶¶ 84 and 86. On March 30, 2012, NSTAR submitted the PPA to DPU for approval. Id. ¶¶ 84 and 90. The contract required Cape Wind to comply with the rules of FERC and other government entities, and required Cape Wind to obtain and maintain the requisite permits and approvals from FERC, including wholesale rates clearances. Alliance intervened in the proceedings, which included three public hearings and two evidentiary hearings. On November 26, 2012, DPU approved the PPA. Neither the Alliance nor any other party to the proceedings appealed DPU’s final decision to the SJC. On January 14, 2014, over fourteen months after the DPU’s decision, plaintiffs filed this case.
DISCUSSION
Plaintiffs seek a declaration that Massachusetts violated both the dormant Commerce Clause and the Supremacy Clause “when it used its influence over NSTAR’s merger request to bring about NSTAR’s entry into an above-market wholesale electricity contract with Cape Wind, a politically favored renewable energy project in Massachusetts, to buy electricity at a particular price.” Compl. ¶ 4. Plaintiffs also seek injunctive relief to “remedy the constitutional violation” by invalidating the Cape Wind contract that “Massachusetts compelled NSTAR to enter.” Id. Plaintiffs allege that this is necessary to “alleviate the increased electricity costs that NSTAR customers such as Plaintiffs will be forced to pay as a result of the illegal, above-market contract.” Id.
Plaintiffs’ Complaint sets out two causes of action. In Count I, plaintiffs allege that DOER “intruded on FERC’s exclusive jurisdiction to regulate wholesale electric energy prices” in violation of the Supremacy Clause and the Federal Civil Rights Act, 42 U.S.C. § 1983.
The Eleventh Amendment states that “[t]he judicial pоwer of the United States shall not be construed to extend to any suit in law or equity, commenced or prosecuted against one of the United States by citizens of another State, or by citizens or subjects of any foreign state.” U.S. Const, amend. XI. “The Supreme Court ... has expanded the doctrine of sovereign immunity beyond the literal words of the Eleventh Amendment, holding that state governments, absent then-consent, are not only immune from suit by citizens of another state, but by their own citizens as well.” Guillemard-Ginorio v. Contreras-Gomez,
A suit against a government official in his or her official capacity is the same as a suit “against [the] entity of which [the] officer is an agent.” Monell v. New York City Dep’t of Soc. Servs.,
The rule is different where the relief sought is retroactive in nature. “[A] suit, although nominally aimed at an official, will be considered one against the sovereign ‘if the judgment sought would expend itself on the public treasury or domain, or interfere with the public administration, or if the effect of the judgment would be to restrain the Government from acting, or to compel it to act.’ ” Muirhead,
That the relief being sought here is retroactive and thus barred by the Eleventh Amendment is easily ascertained by turning to the specific demands set out in plaintiffs’ Complaint for Declaratory and Injunctive Relief. Prayers (a), (b), and (c) seek a declaration that (1) the DPU acted illegally in “forcing” NSTAR to enter a contract with Cape Wind at a specified price,
Plaintiffs attempt unsuccessfully to distinguish the cases in which sovereign immunity was found to compel dismissal of an action against state officials, including a recent decision by this court, Tyler v. Massachusetts,
Because the Eleventh Amendment requires that this case be dismissed, there is no reason to consider the additional grounds for dismissal advocated by defendants, other than to note that the result would be no different were the court to rule on the substance of the claims, whether brought independently under section 1983,
ORDER
For the foregoing reasons, the defendants’ motions to dismiss are ALLOWED with prejudice. The Clerk will enter judgment for defendants and close the case.
SO ORDERED.
Notes
. Town of Barnstable, Massachusetts; Hyan-nis Marina, Inc.; Marjon Print and Frame Shop Ltd.; The Keller Company, Inc.; The Alliance to Protect Nantucket Sound (Alliance); Sandra P. Taylor; and Jamie Regan.
. The State Defendants are Ann G. Berwick, in her official capacity as Chair of the Massachusetts Department of Public Utilities (DPU); Jolette A. Westbrook and David W. Cash, in their official capacities as Commissioners of the DPU; and Mark Sylvia, in his official capacity as Commissioner of the Massachusetts Department of Energy Resources (DOER).
.In the context of a motion to dismiss, plaintiff's plausible allegations of facts are assumed to be true. See Bell Atl. Corp. v. Twombly,
.In affirming the district court’s dismissal of this challenge, the First Circuit summarily held that "[i]n this case, however, we find it unnecessary to reach the question of Chevron deference [the principal ground invoked by the district court] because legislative history reveals, with exceptional clarity, Congress’s intent that [the Corps’ jurisdiction] not be restricted [in the manner the Alliance argued for].” Alliance to Protect Nantucket Sound, Inc. v. U.S. Dep’t of the Army,
. Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd.,
. Ten Taxpayer Citizens Grp. v. Sec’y Office of Envtl. Affairs,
. Both approvals were conditioned on Cape Wind obtaining the necessary permits to begin construction of the wind farm, including all necessary federal licenses.
. Other legal challenges continued to plague Cape Wind. Plaintiffs here, and others, including the Wampanoag Native American Tribe, also repaired to the federal court in the District of Columbia where they filed a series of cases asserting violations of the Administrative Procedure Act, the Endangered Species Act, the Migratory Bird Treaty Act, the National Environmental Policy Act, the Outer Continental Shelf Lands Act, the Coast Guard and Maritime Transportation Act, the Energy Policy Act, the National Historic Preservation Act, and the Rivers and Harbors Act. The cases were consolidated by the district court. On March 14, 2014, Judge Walton issued a lengthy decision allowing summary judgment for all defendants on all issues with two relatively minor exceptions (the fisheries and wildlife services were directed to consider the reasonableness of mandated turbine feathering operational adjustments and the possible incidental take of North Atlantic right whales). See PEER v. Beaudreu, F.Supp.3d -, -,
. The Energy Policy Act of 2005 authorized the Department of the Interior to grant leases for energy transmissions from the Outer Continental Shelf for sources other than gas and oil.
. Timothy H. Powell, Revisiting Federalism Concerns in the Offshore Wind Energy Industry in Light of Continued Local Opposition to the Cape Wind Project, 92 B.U. L.Rev.2023, 2037 (2012).
. The SJC in a related case summarized the mission and mandate of the GCA as follows: "The stated purpose of thе GCA is to 'provide forthwith for renewable and alternative energy and energy efficiency in the [Cjom-monwealth’.... [GCA section 83] requires electricity distribution companies to seek proposals from renewable energy developers twice in a five-year period beginning on July 1, 2009, and, if reasonable proposals are received, enter into long-term [Power Purchase Agreements (PPAs)] to facilitate the financing of renewable energy generation facilities .... In evaluating a PPA proposed under § 83, the [DPU] must consider its costs and benefits, and may only approve the contract on a finding that it is a 'cost effective mechanism fоr procuring renewable energy on a long-term basis.' " Alliance to Protect Nantucket Sound, Inc. v. Dep't of Pub. Utils.,
. Section 83 of the GCA stated that if any provision of the section was subject to a judicial challenge, the DPU would be " 'entitled to suspend the applicability of the challenged provision pending the outcome of the judicial proceeding, and to issue any necessary orders
. See TransCanada Power Mktg. Ltd. v. Bowles, No. 4:10-CV-40070-TSH,
. GCA regulations required National Grid to submit a timеtable and method of solicitation to DPU for review and approval prior to soliciting an offer.
. Because the PPAs were negotiated prior to the suspension of the geographical restriction in the GCA, DPU required National Grid to demonstrate that the contracts had not been influenced by the now-suspended limitation. DPU held thirteen days of evidentiary hearings involving National Grid and nineteen intervening parties (including the Alliance).
. The SJC also acknowledged a potential standing deficiency with respect to plaintiff Alliance. See Id. at 173 n. 13,
. "To the extent the complainants instead challenge rates as unjust and unreasonable under the FPA, they have not shown how they are unjust and unreasonable. The contracts approved by the Massachusetts Commission indicate that the wind facilities must either have QF status or file rates with this Commis
. Under Mass. Gen. Laws ch. 164, § 96, DPU has the sole authority to approve mergers of utilities subject to its jurisdiction, including NSTAR. Plaintiffs allege that, at the time of the merger application, neither NSTAR nor Northeast was involved in "significant negotiations” with Cape Wind to purchase power. Compl. ¶ 61.
. In their Complaint, plaintiffs take the position that DOER had the ultimate power to block the NSTAR-Northeast merger, although elsewhere they have acknowledged that the approval power is vested solely in the DPU (as the statute makes clear). See Dkt. # 38 at 9 (State Defendants’ brief, quoting the Alliance in other matters).
. Section 1983 "does not, by its own terms, create substantive rights; it provides only remedies for deprivations of rights established elsewhere in the Constitution or federal laws.” Kneipp v. Tedder,
. The Commonwealth has not consented to being sued for money damages in either the federal courts or in its own courts under section 1983. Woodbridge v. Worcester State Hosp.,
. While ordinarily the court will accept plausible facts set оut in the Complaint as true, this is not the case where, as here, documents referenced in the Complaint (specifically the DPU order) contradict on their face a supposed fact as plead. The allegation that DPU dictated that NSTAR procure power from Cape Wind at a specified price is misleading and ultimately untrue.
. The retrospective nature of plaintiffs’ in-junctive request is underscored by the demand that DPU take remedial steps to return the relationship between NSTAR and Cape Wind to the status quo ante. However, with respect to the PPA itself, there is nothing further for DPU (or DOER) to do&emdash;the PPA is an historical fact and neither agency has any further actiоn to take, whether of an approval
. Negron-Almeda v. Santiago,
. "42 U.S.C. § 1983 is properly invoked to redress violations of a federal statute ... if the statute creates enforceable ‘rights, privileges, or immunities,’ and if Congress has not foreclosed such enforcement in the statutory enactment itself.” Eric L. By and Through Schierberl v. Bird,
. Even assuming that a private citizen has standing (which is to say the least, highly doubtful) to act as a private Attorney General in seeking to secure FERC’s Supremacy Clause authority in approving wholesale electricity rates, there is no federal right at stake, given that the DPU order requires NSTAR and Cape Wind to file their rates for approval by FERC. Plaintiffs have essayed this argument before (that DPU violated the FPA by usurping FERC’s exclusive jurisdiction to determine wholesale rates) in challenging the DPU's order approving the contract between Cape Wind and National Grid. FERC rejected the argument then, and there is no doubt that it would do so again. See CARE,
. Plaintiffs lack standing to bring suit under the dormant Commerce Clause as they do not compete in the power generation market, as noted by the SJC previously in the National Grid case. Alliance,
. A final note. In entering this decision, the court takes no position on the underlying merits of siting a wind farm in Nantucket Sound or the wisdom of a state policy that
