530 F.2d 367 | Ct. Cl. | 1976
delivered the opinion of the court:
In the past this court has dealt with a variety of claims involving animals, including two dogs and a cat.
At the time plaintiff computed and submitted its bids on both its June and July contracts a comprehensive price freeze was in effect on the price of all commodities and services offered for sale (with certain irrelevant exceptions). This price freeze, one of the various phases of the President’s Economic Stabilization Program, was imposed by Executive Order 11723
Following the termination of the price freeze, the previously stabilized price of poultry
Plaintiff timely performed both of its contracts but due to the increase in poultry prices did so at an aggregate loss of $312,009.84 on the two contracts.
By letter dated August 9, 1973, plaintiff requested price relief from the Contracting Officer on account of the losses it sustained on the two contracts. The Contracting Officer denied this request because, as he advised plaintiff, he had “no authority, either under the contracts or the price stabilization program, to renegotiate contract prices.” The Agriculture Board of Contract Appeals dismissed plain
Plaintiff brings this suit, under the Wunderlich Act (41 U.S.C. §§ 321, 322 (1970)), seeking recovery of its excess contract performance costs allegedly caused by the termination of the President’s price freeze prior to plaintiff’s performance of either supply contract. Defendant acknowledges plaintiff’s losses in the performance of its contracts and the precipitation of those losses by the termination of the price freeze. However, in spite of these acknowledgments, defendant maintains its contractual immunity for those losses. The case comes before the court on the parties’ respective motions for summary judgment, there being no dispute as to the operative facts of the controversy. For the reasons set forth below, plaintiff is not entitled to recovery, and its motion for summary judgment is denied. Defendant’s summary judgment motion is granted, and plaintiff’s petition dismissed.
In its petition, plaintiff divided its claim (s) into two counts. Count I deals with plaintiff’s July contract and seeks recovery of excess performance costs in the amount of $209,204.55. Count II seeks recovery of $102,805.29 for losses plaintiff sustained on its June contract. For chronological purposes, plaintiff’s respective counts will be treated in reverse order.
Count II — June Contract
As Count II of its petition, plaintiff seeks price relief for its excess performance costs on its June contract. Plaintiff predicates its Count II claim on the singular contention that the termination of the existing price freeze by Executive Order with the attendant increase in the cost of plaintiff’s raw materials gives rise to a compensable contract claim. Plaintiff cites no contract provision in support of its position. Plaintiff’s contract did not contain a price escalation clause, a changes clause nor had plaintiff secured firm price commitments from its suppliers. Rather, plaintiff seeks recovery on the sole ground that “the unilateral action of the Defendant (Executive Order 11730) made the contract burdensome, oppressive and destructive of the Plaintiff’s business.” Pltf’s pet. p. 18, ¶ 18.
“* * * The two characters which the government possesses as a contractor and as a sovereign cannot be thus fused; nor can the United States while sued in the one character be made liable in damages for their acts done in the other. Whatever acts the government may do, be they legislative or executive, so long as they be public and general, cannot be deemed specially to alter, modify, obstruct or violate the particular contracts into which it enters with private persons * * * In this court the United States appear simply as contractors; and they are to be held liable only within the same limits that any other defendant would be in any other court. Though their sovereign acts performed for the general good may work injury to some private contractors, such parties gain nothing by having the United States as their defendant.” Jones v. United States, 1 Ct. Cl. 383, 384-385 (1865).10
While it is conceded that the termination of the price freeze obstructed plaintiff’s contract performance and made it more costly, plaintiff does not contend that the termination of the price freeze was other than a public and general act for the general good issued in the exercise of the sovereign power of the United States. Such an argument would undoubtedly be futile.
In its written submission to the court, plaintiff presented neither argument nor authority to refute defendant’s well presented and comprehensive argument that defendant is contractually immune from liability for the sovereign acts of the United States. Besides failing to respond to the Government’s defense presented in its summary judgment motion, plaintiff, in its motion for summary judgment, advanced neither argument nor authority in support of its own position.
■Plaintiff’s latter failing prompted defendant to ask the court to treat plaintiff’s Count II claim as abandoned. At oral argument, plaintiff’s counsel urged reliance on Dillon v. United States, 140 Ct. Cl. 508, 156 F. Supp. 719 (1957), as precedent for allowing plaintiff recovery on Count II of its petition. The marked differences between the Dillon case and the instant dispute do not readily lend themselves to valid comparison between the two oases nor provide persuasive ground for allowing plaintiff recovery.
In Dillon v. United States, supra, the court allowed a hay supply contractor his excess performance costs occasioned by a severe drought in the contemplated contract performance area. This case turned on a conclusive showing of the contemplated conditions incident to the hay supplier’s contract performance, and the fact that the contractor’s excess costs were brought about by an unforeseen natural disaster. None of these controlling circumstances are present in the instant case.
The instant case lacks any evidence as to an understanding between the parties regarding either the price stability of poultry or the continued existence of the previously imposed price freeze. The contract contained no recitals either affording plaintiff relief for increased performance costs or guaranteeing the continued existence of the price freeze.
The contractor’s losses in Dillon were brought on by an unforeseen natural disaster. There can be no comparison between contract losses caused by an unanticipated natural disaster and additional contract performance costs occasioned by the deliberate Government imposition of economic controls, the latter being an exercise of sovereign power for which the Government bears no contractual responsibility. Moreover, the removal of temporarily imposed price controls cannot legitimately be viewed as unforeseeable or beyond reasonable anticipation, especially at a time when the Government was actively utilizing a variety of measures to produce economic stability. The Executive Order imposing the price freeze, prior to plaintiff’s bidding on either contract, specified that the price controls were temporary, and of indefinite duration up to a maximum of 60 days. This Executive Order further raised the flag of future changes by directing the Cost of Living Council to formulate additional economic control policies, mechanisms and procedures. In light of these circumstances, circumstances which plain
The validity of defendant’s immunity defense, barring its contractual liability for a contractor’s losses resulting from the exercise of the Government’s sovereign powers, coupled with the absence of the factors giving rise to the contractor’s i’ecovery in Dillon, precludes plaintiff’s recovery on its Count II claim.
Count I — July Contract
Count I of plaintiff’s petition seeks recovery for plaintiff’s excess performance costs on its July contract. As with Count II, plaintiff’s Count I claim would also be barred by defendant’s immunity defense if plaintiff’s July contract is valid, and plaintiff’s claim for excess performance costs was based on the termination of the price freeze. Plaintiff attempts to avoid the sound defense of sovereign immunity by advancing the unique but nonetheless meritless argument that the termination of the price freeze created an error in its bid which the Contracting Officer failed to detect. Hence, plaintiff argues that the Contracting Officer wrongfully accepted plaintiff’s July bid, and a valid contract was not created by the Contracting Officer’s wrongful acceptance and award of the July contract to plaintiff.
The thorough and comprehensive discussion of parties’ rights, obligations and remedies for bid mistakes in Wender Presses, Inc. v. United States, 170 Ct. Cl. 483, 343 F. 2d 961 (1965) provides an ¡authoritative starting point for consideration of plaintiff’s Count I claim. Wender Presses
Plaintiff’s burden in making these showings is to adduce factors which under the facts and circumstances of the particular case should reasonably have raised the presumption of error in the mind of the contracting officer. Wender Presses, Inc. v. United States, 170 Ct. Cl. at 486, 343 F. 2d at 963; Chernick v. United States, 178 Ct. Cl. 498, 504, 372 F. 2d 492, 496 (1967); Space Corp. v. United States, 200 Ct. Cl. 1, 19, 470 F. 2d 536, 640 (1972); Welch, Mistakes in Bids, 18 Fed. B.J. 75, 83 (1958). Several of the factors which raise the presumption of error are collected in Doke, Mistakes in Government Contraéis — Error Detection Duty of Contracting Ofleers, 18 Sw. L.J. 1 (1964). Extended discussion of classical mistake factors is unnecessary as plaintiff does not rely on any of them, and even concedes
Plaintiff’s inability to find a supporting case doubtlessly stems from tbe basic flaw in plaintiff’s argument. There is no mistake in plaintiff’s bid. Legally, for there to be a mistake there must be a discrepancy between an offerer’s state of mind and his offer. Restatement, Contracts § 500 (1932); 5 Williston, Contracts §1535 (Rev. ed. 1937). See, Russell & Pugh Lumber Company v. United States, 154 Ct. Cl. 122, 127, 290 F. 2d 938, 941 (1961). Plaintiff in submitting its bid stood ready to perform the contract according to its conditions at the price stated in its bid.
Plaintiff’s losses on its July contract were not the product of a difference in plaintiff’s state of mind and its bid. Rather, as plaintiff 'acknowledges the losses resulted from the termination of the price freeze. Changes in economic conditions do not create mistakes. Mistakes are committed, not created. Certainly, between two private parties, plaintiff could not recover for the termination of the price freeze, Restatement, Contracts § 467 (1932); 6 Williston, Contracts § 1963 (Rev. ed. 1938); see, 17 Am. Jur. 2d, Contracts § 402 (1964), and when contracting the Government must be regarded as a private party. Cooke v. United States, 91 U.S. 389 (1875).
Plaintiff, in its Count I plea for relief based on the theory that the termination of the price freeze created a mistake in its bid, cites several decisions of this court, some of which are noted above, including Ruggiero v. Vnited States, supra. That case, rather than supporting plaintiff’s mistake argument, delivers the coup de grace :
* * * The mistake, to invoke such principles [recision or reformation], must be, as in the cases cited, a clear cut clerical or arithmetical error, or misreading of specifications, and the authorities cited do not extend to mistakes of judgment. * * * Ruggiero v. United States, supra, 190 Ct. Cl. at 335, 420 F. 2d at 713.
The mistake in plaintiff’s bid, if any, resulted not from any clear cut clerical, arithmetical or specification misreading error or a difference between what plaintiff intended to bid and its actual submitted bid. The mistake resulted from
Plaintiff’s legal argument, while novel, can neither be supported nor sustained, and plaintiff cannot recover on its July contract on a mistake-in-bid theory.
Lastly, plaintiff, while quick to impute liability to defendant, seemingly ignores its own culpability for its July contract losses. The price freeze was terminated on July 18, 1973. Plaintiff’s bid was not accepted until July 20,1973. If, as plaintiff says, “[t]he impact of the lifting of the price controls was swift and sure in coming and to be anticipated”,
Even with the sure, swift and immediate rise in poultry prices following the July 18, 1973 termination of the price freeze, plaintiff waited until August 9, 1973 to bring its cost increases problems to the attention of the Contracting Officer. In view of plaintiff’s actions, it is difficult to accept its contention that the Contracting Officer knew or should have known of the mistake in plaintiff’s bid created by the termination of the price freeze, when plaintiff with a two-day opportunity to withdraw its bid not only took no action but even remained silent for more than three weeks. Equally, it is doubtful whether on the termination of the price freeze, had the cost of poultry declined, that plaintiff would have clamored with as much vigor for a decrease in its bid price. Plaintiff’s apparent wait and see attitude cannot be condoned.
Plaintiff might well have considered the merits of utilizing a price escalation clause, or securing a firm price commitment from its suppliers before entering into these contracts. A Government contractor, regardless of its size, locality or experience, is bound to understand the complexities and consequences of its undertaking. Massachusetts
Plaintiff’s June and July supply contracts are valid and enforceable according to their terms. Plaintiff is not entitled to recovery on either of these contracts.
Plaintiff’s motion for summary judgment is denied, and its petition is dismissed. Defendant’s motion for summary judgment is granted.
Pedersen v. United States, 115 Ct. Cl. 335 (1950).
Pauly V. United States, 152 Ct. Cl. 838 (1961).
McGuire V. United States, 158 Ct. Cl. 285, 305 F. 23 449 (1962).
Wilfong v. United States, 202 Ct. Cl. 616, 480 F. 2d 1326 (1973).
Contract No. 12-25-3-4685.
Contract No. 12-25-4-4002.
3A CFR 1973 Comp., p. .184.
3A CFR 1973 Comp., p. 197.
While the price freeze Imposed by Executive Order 11723 did not apply to raw agricultural products, neither party contends that plaintiff’s costs of its raw materials, e.g., turkey and chicken, were not subject to the price freeze. As the record demonstrates nothing to the contrary, the court accepts the parties’ representations that plaintiff’s raw material costs were subject to the price freeze.
See, Hallman v. United States, 107 Ct. Cl. 555, 68 F. Supp. 204 (1946) ; Piggly-Wiggly Corp. v. United States, 112 Ct. Cl. 391, 81 F. Supp. 819 (1949) ; Barnes v. United States, 123 Ct. Cl. 101, 105 F. Supp. 817 (1952) ; Anthony P. Miller, Inc. v. United States, 161 Ct. Cl. 455, cert. denied, 375 U.S. 879 (1963) ; Amino Brothers Co. v. United States, 178 Ct. Cl. 515, 372 F. 2d, 485 cert. denied, 389 U.S. 846 (1967) ; Glasgow Associates v. United States, 203 Ct. Cl. 532, 495 F. 2d 765 (1974).
Cf. McNamara Construction of Manitoba, Ltd. v. United States, 206 Ct. Cl. 1, 509 F. 2d 1166 (1975).
Franklin Co. v. United States, 180 Ct. Cl. 666, 381 F. 2d 416 (1967).
Pltf’s Brief, p. ».
id.