59 F. Supp. 410 | Ct. Cl. | 1945
delivered the opinion of the court:
The plaintiff sues to recover liquidated damages assessed against him and withheld by the Government from pay
To perform the contract, the contractor had to provide the necessary airplanes and aerial cameras and take photographs of the land in each county. He would then develop the film and print “contact prints” from his negatives; arrange those prints so that an assembly of them would cover a given area of the land; photograph the assemblies of the pi'ints to a smaller scale to make “photo-index maps”; submit the contact prints and photo-index maps to the Government for approval or for partial rejection which would require re-flying and re-photographing of some of the land, and the preparation of better photo-index maps; after approval, prepare enlargements of the maps on the basis of “ratio factors” to be furnished by the Government.
A pertinent part of the continuation schedule is quoted in finding 2. It says that “Contact prints and photo-index maps for each county project shall be shipped to the (specified office of the Government) within fifteen (15) calendar days after the date final flying is completed on said county unit.”
The plaintiff did not ship these prints and maps until some four months after he had completed his original flying of each of the three counties. Liquidated damages at $10 a day for each county, the rate provided in the contract, if applicable, were assessed, which consumed nearly all that the plaintiff earned under the contract.
We have no doubt that the language of the contract quoted above obligated the plaintiff to develop his films, make his contact prints and photo-index maps of each county and ship them to the Government within fifteen days after he completed, to his own satisfaction, his flying and photo
The plaintiff points us to paragraph 32 of the specifications which provides for liquidated damages of $10 a day for delay in “delivery after expiration of the time allowance specified in paragraphs 26 (a) and 27 hereof, and in the schedule of the advertisement * * *.” All these provisions of the specifications are printed in finding 2. The fact that paragraph 32 speaks of “delivery” while the continuation schedule which was a part of the advertisement speaks of shipment, would not in itself trouble us. Shipment would amount to delivery if the contract said so, and if we found that the language of paragraph 32 was otherwise applicable, we would apply it.
But the plaintiff urges, and we agree, though with some doubt, that paragraph 32 is not otherwise applicable to delay in shipping prints and maps as required by the first sentence in the first paragraph of the part of the continuation schedule quoted in finding 2. Paragraph 32 provides for liquidated damages for “delay in undertaking the work and in delivery after expiration of the time allowance specified in paragraphs 26 (a) and 27 hereof, and in the schedule of the advertisement * * *” as follows:
Undertaking the work-$10
Contact prints with index maps- 10
Oblique photographs- 10
Katioed prints_ 10
General enlargements- 10
The Government urges that the negative provisions of paragraph 27 (d) (see finding 2) should create an implication that the liquidated damages provision covers the in
The express mention of “contact prints with index maps” as the subject of liquidated damages in paragraph 32 is fulfilled by their express mention, in the connection discussed above and not applicable to our facts, in the second sentence of the continuation schedule and in 27 (a) of the specifications.
The plaintiff may recover $3,575.40. It is so ordered.