*1 75 GINSBURG, RANDOLPH, and Before
TATEL, Judges. Circuit TIME WARNER ENTERTAINMENT CO., L.P., Petitioner,
PER CURIAM v. appeal this from the We dismiss ruling appellant has not district court’s FEDERAL COMMUNICATIONS COM given grant immunity by been the Unit MISSION and United States of States, acting through Office of ed here America, Respondents. Independent Under 28 U.S.C. Counsel. 1291, jurisdic appeals the courts No. 97-1263. appeals
tion of from “final decisions courts____” In fi district criminal cases Appeals, United States Court of “prohibits judgment appellate nal rule review District of Circuit. Columbia imposition until of sen after conviction 3, Argued Feb. 1998. Asphalt Corp. tence.” Midland v. United States, 794, 1494, 798, 489 109 U.S. S.Ct. 22, May Decided (1989). 1497, Appellant 103 L.Ed.2d has indicted, let alone convict been tried and Appellant testify ed. has refused to be refusal, jury and, grand
fore
contempt of
is
been held in
court. Nor
there
treating
appeal
basis for
under the
exception of Cohen
In
narrow
v. Beneficial
Corp.,
dustrial Loan
337 U.S.
69 S.Ct.
(1949).
1221,
Appeal dismissed.
R. argued Bruce Beckner the cause for Fleischman, petitioner, with whom Aaron I. Davidson, K. A. and Jill Seth McClelland were on the briefs. Carr, Counsel, M. Federal Commu-
James Commission, argued cause nications Klein, respondents, I. with whom Joel Assis- General, Attorney tant United De- States Justice, partment B. Robert Nicholson and Wiggers, Attorneys, Christopher Robert J. J. Counsel, Wright, Federal General Communi- cations Daniel M. Arm- Counsel, strong, Associate General were on the brief. SILBERMAN, RANDOLPH,
Before: TATEL, Judges. Circuit Opinion by Circuit the Court filed Judge SILBERMAN.
Opinion concurring part dissenting part Judge RANDOLPH. filed Circuit
SILBERMAN, Judge: Circuit Company pe- Entertainment Federal
titions for review of order setting forth Communications Commission system operators the manner which cable may recoup external cost increases incurred September the date between 1992 and subject system first became to rate costs” regulation. “effectively “[E]xternal contends were those be control,” yond operator’s cable including: it had no beeause “(1) error, issue, 405 of retransmission or to correct section consent fees cable (2) broadcasters; operators pay Act bars our review. program Communications *3 (3) costs; taxes; part ming remand. grant [state local] the and and We and (4) franchise fees and the costs associated requirements, with other including franchise I. educational, provision public, the of gov and The Cable Television Consumer Protection programming.” 171; ernmental-access Id. at 1992, Competition of No. 76.922(f)(1) (1997). and Act Pub.L. § 47 C.F.R. The (codified 102-385, 106 Stat. 1460 scattered “gap period” Sep refers to the time between U.S.C.), FCC to 30, of 47 directed the sections system tember and the date a be operators that regulate the rates cable subject regulation. opera came to rate An competition,” subject to at rate, “effective defined permissible tor’s initial least for 543(l)(1) (1994), charge § 47 U.S.C. could rate, using the full those reduction was de designed their subscribers. The Commission its on September rived from rate effect any system that a scheme to ensure intended not the actual rate in effect on the date competition facing such would neverthe system subject regulation, each became charge approximately the same rates as less permitted “lest build [the FCC] into ini competitive if it were in a market. Put tial rates rate unwarranted increases simply, system operator’s permitted a initial operators passage that cable took after of the September either was rate effect Warner, rate Act.” Time Cable 56 F.3d at on. by “competitive differ reduced not permit opera 173. The Commission did (the rate”), or was “full reduction ential” recoup any tors to cost increases external with FCC calculated accordance certain during gap period;1 only incurred those without formulas and worksheets reference system incurred date became after (the September rates in effect on subject regulation to rate could be taken into 76.922(b) rate”). “transition See 47 C.F.R. length gap account.2 The varied (1997). systems, Most the Commission has among operators full reduction rate-based said, Imple employed the former rate. See they subject regula because became to rate mentation Television times, Cable Consumer tion at different no shorter Competition and Act 1992: Protection longer long. than 11 and no than months Opinion Regulation, Rate Memorandum Warner, In held that the Time Com (Order Remand), Order 11 F.C.C.R. and preclude adjust “decision to a rate mission’s ¶ (1996). 20206, 22 designed changes ment to recover external during gap period Time Entertainment Co. costs incurred [was] arbitrary capricious,” id. at F.3d 151 we consid- and and as petitions for the rule insofar the FCC denied “vacatefd] ered consolidated gap-period of their implementing operators] recovery FCC’s orders the Act. One of [cable operators’ complaints cable ease cost at 178. In our external increases.” Id. (and view, one relevant to Time the FCC had offered “no reason to Warner’s petition) operators instant FCC unreason- doubt that cable incurred external ably operators adjust during gap period, yet did not allow “cable costs under its they regulations their rates to external cost increases would never be able to re reflect opting during gap period.” coup at 173. costs short of for eost-ofservice incurred Id. those counsel, however, op- problem, parties dispute point. The 1. FCC’s indicates permitted particular erators were to include one argues operator counsel that such an did FCC’s external cost increase—franchise fees—incurred Warner, however, not. contends Time during gap period. operator using slightly rate faced a transition April gap, began on different one that opinion Our address first Time Warner did not September but likewise end- instead system operator whether a transi- which used a system subject date the ed on the first became tion rate full rate was rather than reduction regulation. rate subject adjustment to the same external cost regu gap period if akin to current rates as external would be lation-which included, but Id. at cost increases had been did fly a blunderbuss.” shooting deficien- thought de allow them to recover revenue the Commission’s 174.3 alsoWe cies, say scope allowing recovery of than to “[t]he other its rule—that fense of requested cost increases would is reflected in War- external relief gap-period burdensome, administratively Expedited both for Re- Emergency ner’s Motion be too ...)” operators the FCC-“com (May view filed in this court cable Id., pletely unacceptable.” argument petition. Id. first ¶ 24 n. Petitioner had said in that motion 40.. decision, months after Eighteen operators lose millions of dollars that “cable seeking proposed rule or issuing a without every they eventually If day. in revenue proceed, the Com- public on how to comment *4 persuading in to rule in succeed Court response an order in to our issued mission favor, recouped. their those losses cannot be ¶¶ Remand, 21-28. See on remand. Order economic loss thus con- Their unrecoverable adjust operators to “permit[s] order The irreparable injury.” The FCC con- stitutes to permissible level] rates [the their current (or as a strued that statement concession if currently charging be operators would waiver) operators the cable were not. include increases they permitted been to had seeking to recover their revenue loss. even occurring Septem- in costs between external regula- their initial date of ber and it Petitioner contends that was absurd for added). ¶25 Id., (emphasis tion.” the Commission to have drawn distinction operators re- allow"cable to Order does not past between revenue deficiencies attribut- or in future rates otherwise the differ- cover cost increases able unrecovered external they the rates would ence between on, prospective predicated but not and rates in and had charged totally recovering, past external cost those for they allowed account external been increases; its claim to the Commission never during peri- the gap cost increases incurred worse, made that distinction.4 Even Time od, years. in their allowable rates those and argues, passage which the Warner petition not for reconsider- Time Warner did solely pertained to the Commis- FCC relied issued its Order ation after the Commission “competitive sion’s choice of 17% differen- Remand; sought it instead review here. tial,” supra gap period at not at un- Petitioner claims the FCC’s order all. counsel that it was The FCC’s insists operators ability to reasonably denies “entirely for the Commis- understandable” deficiency—which recoup the Time revenue as it Time Warner sion decide did because at than million $14 Warner estimates more “changed” never it had its indicated dollars—they during four sustained position in a to the FCC after our submission comply years, that the does not order remand, petition or in a for reconsideration. with our mandate the first Time Warner arguments He contends that the other operators that those case. It contends petition—that raises its it was employ which a transition rate are unreason- pro- not unreasonable the Commission ably opportunity to take advan- denied operators recoup all way vide a tage prospective relief full afforded deficiencies, revenue the FCC’s order operators. rate-based reduction operators treated full reduction rate-based favorably using more the transi- than those
II.
rate,
comply
and that the order
did
explain why
presented
did not
with our remand—were never
The Commission
(presumably
permitted.
operators
charge
in a
order
cable
Commission
Warner,
(citation
permitted
operator
opt
system
rules
rule.” Time
56 F.3d at
regulation; we
omitted).
cost-of-service
into conventional
said,
however,
that "because
cost-of-service
regulatory proceeding
expensive
is
for the cable
issue,
4. The
asserted
dissent’s formulation
operator,
oper-
can be
FCC
confident that
Commission,
ly
to the
see Dissent
option
lightly
will not
choose that
and it will
ator
is misstated.
limited'exception
general
indeed remain a
instance,
it was not foresee-
Bartholdi Cable Co. v.
reconsideration because
able that
would draw the F.3d 274
section
Commission
held
did).
remedial distinction that
Petitioner was not
party
satisfied because the
claiming
exhausted its administra-
therefore
improperly rejected
attor
by
tive remedies
our review foreclosed
ney-client
work-product privileges
had
405(a)
Communications Act.
section
not raised
claims before
those
the Commis
response
primary
is that
Time Warner’s
sion. The
the privileges
FCC discussed
directly implicated
issues it raises were
dicta,
but
concluded
because the
reasoning
prior
of our
decision and were
“flagged”
issue was not
the Commission did
therefore
remand order.
covered
not have a
on it. Id.
fair
405(a)
at 279-80. Bartholdi Cable thus fits within
Section
somewhat differ-
worded
the category of cases in which we
ently
provision.
than the
exhaustion
have said
normal
that even
provides:
It
where an issue has been “raised”
if it is done in a
order, decision,
less
report,
After an
or action
complete way,
than
see Northwestern Ind.
any
proceeding
has been made or taken
Tel. Co. v.
1210 n.
any
thereto,
party
...
(D.C.Cir.1987) (appellant “point[ed] out” a
aggrieved
person
other
or whose
circumstance,
adversely
argu
not make an
thereby,
did
interests are
affected
*5
ment); WATCH,
(appellant
We
with
scope
the claim. Even after the Commission
question.
of relief
Because
Com-
sider
Remand, Time
argue
chose not
merits in the
issued its Order on
Warner
mission
alternative,
a motion for reconsideration.
we have no choice but
vacate
could
filed
Again,
alley searching
it chose to remain silent. Section 405
for a distinction between
Communications Act therefore stands
something
called a “technical” defect and
judicial
an additional bar to
review of
as
something
“policy”
described as a
difference.
recoupment
Time
claim.
In the
Warner’s
maj. op.
See
at 80-81. As
I
best
can make
§‘405,
§
of
47 U.S.C.
the Commis
words
out,
majority
thinks it has discovered a
opportunity
pass” upon
“no
sion had
litigants
trend:
trying to raise “technical”
“legal questions”
by arguments
raised
Time
defects
court without having raised them
making
Warner
now
for the first time
lose,
litigants
Commission will
legal arguments
this court. Those
consist of
raising “policy” differences for the first time
analogies
dealing
to Commission decisions
court,
without having presented their ar-
“Exchange
with the
Network Facilities for
guments
to .the
might.just get
Access,” to
of
Interstate
decisions
the Feder
away with it.2
Energy Regulatory
allowing
al
gas pipelines
impose
tell,
retroactive sur
So far as I can
this technical-policy
obvious,
charges, and so on. To state the
up playing
trend winds
no discernible
role
Commission never had a chance to
Still,
on the outcome.
a few words about the
legal arguments concerning
Time Warner’s
majority’s digression
are
order.
For
agency’s
remedial discretion because
starters,
the distinction
any
lacks
coherent
argu
never
those
rationale.
majority suggests
The
that re
is,”
ments to the Commission. “It
we recent
quiring
litigant
procedural
to raise a
or
reiterated,
ly
“only through the adversarial
point
“technical”
agency may
with the
allow
(or
circumstances)
process
analogous
that the
agency
to correct its error before the
Commission is
such an
afforded
maj.
case reaches
op.
the court. See
at 80-
meaning
§
within the
of
405.” Bartholdi
true,
81. This is
but it is also true about
(D.C.Cir.
Cable Co. v.
114 F.3d
“policy”
Besides,
or “substantive” mistakes.
1997).
up
We also
that it
stressed
is not
knows,
as
student of administrative law
pleadings
Commission to
and docu
“sift
allowing
agency
the chance to correct its
predict
might
ments”
an effort to
what
only
many
errors is
one of
reasons behind
argued
litigant
have been
if the
had taken
instance,
the raise-it-or-waive-it rule. For
279;
present
the claim.
trouble
Id. at
recognizes
“exhaustion doctrine
the no
also, e.g.,
Vintage
Russian River
Broad
tion, grounded
Congress’
in deference to
del
(D.C.Cir.
casting v.
egation
authority
of
to coordinate branches
1993).1
Government,
courts,
agencies,
not the
majority
ought
primary responsibility
refuses to follow this well-
to have
for the
Instead,
path.
up
programs
marked
it
Congress
charged
heads
blind
them to
review,
majority
quite
supposing
judicial
parties
present
1. The
mistaken in
must
those
judicially-imposed
§
require-
405 ousts the
claims to the
renders its
parties present
rulemaking
adjudicatory
light
ment
their claims to
decision.
statutory gap,
may
agency
the federal courts
fill it
Commission before the
decides the mat-
insisting
parties
that if
to raise
Maj. op.
fail
their claims
ter.
at 79 n.5. Section 405 deals
action,
prior
agency
reconsideration,
to final
those
will not
petitions
agency
claims
which
judicial
McCarthy
be considered on
review.
necessarily come after the Commission's deci-
Madigan, 503 U.S.
112 S.Ct.
majority
sion. To read
405 as the
does sub
1085-86,
(1992),
very
refused
reach the
of either issue
(D.C.Cir.
v.
46 F.3d
ASTV
reasons,” namely
“substantially the same
1995),
argu
to consider ASTVs
refused
“petitioners
failed to
their reme
exhaust
system’
ment that “wireless cable is
‘cable
by
alleged
declining
bring
...
[the
dies
Act,
to raise
under
because ASTV failed
first
Id. To
error]
before
Commission.”
case,
Engi
Commission”—surely
a substan
take another recent
Freeman
Associates,
tive,
neering
“policy”
Inc. v.
matter rather
than what
Cisneros,
Darby
inoperative pending
v.
113 S.Ct.
review.”
U.S.
made
(1993),
by
the ma
peccadillo. AMERICAN FEDERATION OF GOV EMPLOYEES, ERNMENT LO majority ultimately comes to rest on The 2343, Petitioner, CAL technical-policy than grounds other its di- chotomy. loses it The Commission because something “gotcha,” playing called “unfair,” its of the matter was view FEDERAL LABOR RELATIONS “farfetched,” “disingenuous it relied on a AUTHORITY, Respondent. Maj. gimmick.” op. at 81-82. All this ex- No. 97-1355. at a footnote in the citement directed Commission’s decision remand. Appeals, United States Court of quoted a footnote Time Warner motion con- District of Columbia Circuit. ceding operators recoup that cable could they incurring “they even if the losses were Argued March 1998. ultimately persuading succeed in this Court favor,” to rule Memorandum of Law May Decided Company, of Time Entertainment Warner Support Emergency L.P. of Its Motion Consideration, Expedited pp. 17-18. directly
That concession contradicts Time position. current Warner’s The Commission rightly took the statement context: Time referring delay- Warner was to the effect of ing “rate-regulation review of the entire is,” Id. rulemaking.” at 17. “The truth according majority, parties “that often
claim that drastic harm will occur when
seeking expedited Maj. op. consideration.” so, Maybe point. at 81. but that misses the If Time Warner believed that it was entitled' losses, recoup company its if thought open despite was still what it court, upon told this it was incumbent to make its views known to the ample opportunity Commission. It had so, pend- do while the matter was remand, ing agency but also after the Commission handed down deci-
sion. Time Warner nevertheless remained mute. simple, majority
Pure and has offered good rejecting no reason for the Commis- legal sion’s determination not to decide claim sup- Time Warner neither raised nor ported pertinent “got- authorities. If “disingenuous gimmick”
cha” and are meant embody legal principle, I confess—the principle eludes me. I therefore dissent portion majority opinion.
from this
