50 N.Y.S. 511 | N.Y. App. Div. | 1898
On the 26th of April, 1893, the plaintiff, who is a contractor, entered into a written contract with one John H. Smith to erect a large office building in the city of Buffalo. By the terms of this contract the building was to be completed by the 10th day of April, 1894, and the price to be paid therefor was $124,000. In the month of August following the execution of the contract the defendant was duly substituted as a party thereto in the place of Smith, who was at that time the defendant’s president, and this action is brought to recover a balance of $3,117.45, which it is claimed is due the plaintiff upon the contract, and for extra work done and materials furnished by him, after deducting the sum of $371.27 for work and materials embraced in the contract which were omitted by direction of the defendant. The plaintiff’s demand consists of seven items, the first of which is for a balance of $1,700, claimed to be due upon the contract proper, and the remainder are for “extras.” With the exception of the item of $459.25 for “extra work and materials, concrete in quicksand pockets,” the correctness of the plaintiff’s claim was not disputed upon the trial; but it was nevertheless asserted by the defendant that it was under no legal liability to pay the same, for the reason that at the time this action was commenced the plaintiff had omitted to furnish the certificate of the architects which was required by the contract as a condition precedent to final payment, and for the further reason that the item of $459.25 above mentioned was for work and materials which were properly embraced in and contemplated by the contract. It
So far as the defense relied upon by way of counterclaim is concerned, but little need be said. The contract and specifications provided that:
“The finished wood floors of the entire building are to be of clear Georgia or Southern pine, thoroughly seasoned and kiln-dried, matched and laid closely, and blind-nailed to place. This flooring must be 1%" thick, and the face not over 3" wide. This flooring must be of the very best selection, every board quarter-sawed,. sometimes called ‘riff-sawed’; and unless it is perfectly well, matched, so that it lays thoroughly even and smooth, it must be hand-planed .after being laid.”
The evidence on the part of the defendant tended to show that the material used in the floors was of an inferior quality to that above specified, in that it was what is termed “sappy,” and that, in consequence of this defect, it very soon changed color, and looked dark and dingy. It was, however, made to appear upon the trial that there are several grades of Georgia or Southern pine; that the only grade which does not contain any sap is what is termed “heart-face” lumber, which is never used unless specifically mentioned in the contract; that the next grade, which is termed “first and second clear pine,” contains 10 per cent, of sap; and a number of witnesses called by the plaintiff testified that the term “clear Georgia or Southern pine” meant this grade, and that this was the grade used by the plaintiff in fulfilling his contract. It was further contended by the olaintiff that the change in the color of the flooring was due to .the fact that it had been improperly treated by the defendant after it was laid, and some evidence was given tending to sustain this contention. It is very apparent, therefore, that, as respects this particular feature of the case, an issue of fact was raised, and, as this issue was submitted to the jury in a charge which was exceedingly fair, it must be deemed settled by the verdict.
The defendant’s contention in respect of the claim for extra work in the “quicksand pockets” is subject to very much the same ■stricture.' It séems that the original specifications provided that, •“if any pockets of quicksand are found, this contractor shall excavate the same, and then fill in solidly with cement, concrete, and broken stone.” This provision was objected to by the plaintiff before bidding for the work, and the architects thereupon assured him that it was a mistake which would be corrected, and that he might bid upon the assumption that he would not have to fill the quicksand pockets over one cubic yard in size without extra compensation. Subsequently the specifications were corrected so as to read: “If any pockets of
We come, therefore, to a consideration of what may doubtless be regarded as the paramount question in the case. At the time the plaintiff presented his claim, and demanded payment thereof, the structure had been completed, and was in the possession of the defendant. This fact makes it perfectly obvious that the amount claimed was in full satisfaction of all moneys which the plaintiff would-be entitled to receive under his contract. In short, it was the “final payment” which the plaintiff was demanding, and both he and the defendant so understood it. The contract provided that payments were to be made upon the written order of the architects, “it being understood that the final payment shall be made within thirty days after this contract is completely finished; provided, that in each of the said cases the architects shall certify in writing that all the work upon the performance of which the payment is to become due has been done to their satisfaction” ; and it was insisted upon the tidal that no such certificate as is here contemplated was presented by the plaintiff, and that, consequently, he was in no position to enforce the payment of his claim. So much of this contention as is based upon the failure of the plaintiff to furnish a certificate which complied literally with the requirements -of the contract is not controverted. ^Neither is it denied that a certificate of the architects was, within the strict requirements of the contract, a condition precedent to the right of the plaintiff to insist upon a
“We recommend, under the terms of the contract dated April 26, 1893, for work upon Union Central Life Building, that Mr. ,T. H. Tilden, contractor for mason, iron, steel, carpenter, painting, glazing, and roofing work, be paid three thousand one hundred seventeen forty-five hundredths dollars. * * *
“Green & Wicks, Architects.”
This was sent to the defendant by the architects, accompanied by a letter in which they'Stated that they inclosed “final recommendation in favor of Mr. J. H. Tilden for work on the Union Central Life Building, as per his bill attached.” The statement thus furnished would seem to be amply sufficient to inform the defendant that, in the opinion of the architects, the plaintiff was entitled to his final payment under the terms of the contract, which, as we have seen, he was not entitled ■ to until the work had been performed to the satisfaction of the architects. No fraud, mistake, or bad faith upon the part of the architects in giving this certificate was charged upon the trial, and, in the absence of any of these elements, we think the certificate, within the principle of the cases' above cited, was the same, in effect, as if it had contained the statement that the work was completed to the satisfaction of the parties signing it. In view of the fact that the defendant had virtually accepted the building, and that at' the time the plaintiff’s demand was made it was in full occupation of the same, it may well be doubted whether the plaintiff was required to furnish the certificate of the architects that the contract had been fully performed to their
There is no pretense that any fault was found with the form of the certificate prior to the commencement of this action, and as late as October 9, 1894, the defendant’s president, in a letter to the plaintiff’s attorneys, wherein he stated Ms reasons for refusing payment of the' plaintiff’s demand, and intimated that, if sued, the action would be defended upon the grounds therein specified, makes no allusion whatever to the insufficiency of the certificate; and we think that, in these circumstances, the trial court would have been justified in holding, as matter of law, that the defendant had waived any right which it might otherwise have had to insist that the architects’ certificate should have been of a different character from the one furnished. Instead of taking this course, the question was submitted to the jury as one of fact; a disposition of the matter which certainly ought to evoke no complaint from the defendant. The learned counsel for the appellant insists, however, that the question of waiver was not properly before the court, inasmuch as it was not pleaded in the complaint. We do not regard this proposition as tenable, in view of the facts disclosed by the record; but, as we have held that the certificate was sufficient to answer the requirements of the contract, it is unnecessary to consider tMs aspect of the case.
Several’ exceptions taken to the rulings of the trial court during the-progress of the trial are pressed upon our attention. We have given careful examination to the same, and, while one or two seem at first blush to be somewhat questionable, we are persuaded that, if erroneous, they were not sufficiently prejudicial in their character to require the granting of a new trial; and our conclusion of the whole matter is that, the judgment and order appealed from should be affirmed.
Judgment and order affirmed, with costs. All concur.