Tibbetts Contracting Corp. v. O & E Contracting Co.Tibbetts Contracting Corp. v. O & E Contracting Co.
Under a contract with defendant Vioe, defendant O
&
E agreed to do excavation, grading and drainage work on property which Vioe was developing for lease to S. Klein Department Stores, Inc. Plaintiff subcontracted to lay certain drainage pipes. In March,
1959 O &
E removed its" equipment from the job site and on the basis of that and other alleged breaches of the contract Vioe declared O & E in default. Plaintiff completed the drainage work, to the knowledge of Vioe, after Vioe had declared the principal contract broken by O & E. O
&
E did not pay plaintiff and plaintiff filed a notice of mechanic’s lien for the amount owed to it by O & E. This action was commenced to foreclose the mechanic’s lien. Another action by Vioe against O & E for breach of contract commenced in New York C'ounty was consolidated with this action for trial. Defendant O & E alleged counter
The trial court found that O & E did not abandon or breach the contract, that O & E was entitled to recover from Vioe the balance due for work, labor and service's and materials furnished, plus loss of profits because of breach of contract by Vioe, that plaintiff was entitled to judgment against O & E for the amount due it and to establishment of its mechanic’s lien on the land. *
The Appellate Division found that Vioe was justified in terminating the contract with O & E for O & E’s refusal to comply with demands to resume performance of the contract, O & E’s removal of its equipment from the job site and its refusal to furnish a performance and payment bond; that a determination that Vioe owed O & E nothing at the time plaintiff filed its notice of lien would have been justified, and, therefore, no fund was in existence to which the lien attached and the lien was unenforeible at least through the subcontract with O & E; that, in order to prevent unjust enrichment of Vioe, plaintiff was entitled to relief (on a cause of action which was added pursuant to permission by the Appellate Division) in the form of a money judgment against Vioe on quasi-contract or constructive trust (implied in law) for work done and materials supplied by plaintiff, Vioe having permitted plaintiff to continue to perform under its subcontract and having fostered and promoted such performance by plaintiff.
Defendant Vioe argues,
inter alia,
in support of its appeal that the court below erred in holding that plaintiff is entitled to any judgment against Vioe; that it was error to grant the plaintiff’s motion to amend its complaint to allege a new cause of action against Vioe, because it was deprived of an opportunity to meet the issues raised by the new cause of
Defendant O & E argues on its appeal that the Appellate Division erred, both in law and fact, in holding that ‘ ‘ a damage award in favor of Vioe against O & E would have been justified ’ ’; that Vioe’s notice of contract termination was ineffective, unwarranted and improper under the provisions of the contract, and, in any event, was cancelled or waived by Vioe’s later conduct; that, at the time of the filing of plаintiff’s mechanic’s lien, a fund existed sufficient to pay the lien which was subject to -appropriate action to foreclose.
The plaintiff, also appealing, argues, inter alia, that O & E did not abandon the contract; that the permitting and acceptance of performance of plaintiff’s subcontract constituted a waiver in law of the termination of the contract, thus making Vioe liable -under its contract with O & E and to plaintiff.
Since the Appellate Division modified on the law and the facts, it is incumbent on us to decide which version of the facts more nearly accords with the evidence. Our conclusion is that the trial court’s findings are nearer to what is disclosed by the record than those of the Appellate Division, i.e., that Vioe rather than O & E broke the principal contract. We cоnclude that Vioe owes money to O & E, out of which Tibbetts (plaintiff) is entitled to be paid. In that posture of the case, it becomes immaterial whether Tibbetts could recover against Vioe on .some quasi-contract theory of unjust enrichment.
The contract between Vioe and O & E was entire; it provided a flat price of'$127,750 for the performance of “ all excavating, filling, drainage, grading and related work required by the Drawings and/or as described in this Specification, generally as follows” (cf. contract Exhibit A, p. 582) after which the work is more particularly described. Unit prices applied only to
“
additions and/or deductions ”, resulting- from modification of the contract as the work progressed. The subcontract between O
&
E and Tibbetts, as has been stated, was for drainage. O
&
E happened to deal with Tibbetts in this manner: it came аbout that in preparing this site for an S. Klein Department Stores, Inc., shopping development in Yonkers,
On March 18, 1959 Yioe notified O & E that it had abandoned its contract unless alleged defaults in performance were rectified under the terms of the contract within three days, and on March 27 notification was given that the defaults had not been rectified, that the contract had been terminated and that O & E would be charged with excess costs of completion. The O & E contract work (except what had been subcontracted to Tibbetts) was completed by a concern known as County Asphalt Corporation to which Yioe relet the balance of the work at a charge of $87,229.49 in excess of the figure of $127,750 for which O & E had contracted to do the entire job including the amount payable under the subcontract to Tibbetts. Having
Under the judgment of the trial court Vioe broke the contract, and the amount owing by O
&
E to Tibbetts is part of the damages which O & E was held to be entitled to recover from Vioe. Tibbetts was awarded a lien on the proceeds to satisfy its debt from O
&
E (Lien Law §§ 4, 70, 71;
Dempsey
v.
Mount Sinai Hosp.,
The testimony differs, as testimony does, but money talks, and if Vioe paid O & E for 70% of the work purporting to be covered by its contract, and, in addition, received the benefit of what was done for O & E by Tibbetts, we are inclined to credit the version given by Tibbetts and by O & E.
The ground was frozen on March 17,1959, when O & E moved its bulldozers and рans to the nearby job at Idlewild. O & E claims to have done so with the consent of Vioe, which disputes that its consent was given. However that may be, O & E asserts that it would take but a short time to move its machinery back to the Klein job. There is no question that it was more costly to refill and grade in frozen ground. It is no answer to say that the frozen ground did not prevent Tibbetts from digging trenches and laying drаinage pipes. Doing that is different from backfilling and grading. These operations could not be commenced, regardless of frozen ground, until after the laying of drainpipes had been completed by Tibbetts, on both the job that Tibbetts did directly for Vioe and on the one for which it subcontracted from O & E. Even the expensive job done by County Asphalt, working on a cost plus basis through the Winter regardless of frost, was evidently not finished in all its details until September 12, 1959. At least the dates of its invoices ranged from March 24 to September 12.
It is evident that O & E did not intend to abandon the job on March 17, 1959, and expected to return when the progress of Tibbetts’ work and the weather conditions made it easier. Vioe
In spite of all this, the contract contains no specified date for completion. Delays caused by the weather or other contractors have provision made for them. At a time when the briefs and subsequent correspondence would indicate Vioe was disgusted with O & E’s performance, Vioe offered the 84-inch pipe storm sewer job to O & E in preference to Tibbetts, which got the contract after O & E’s refusal for which Tibbetts was paid $91,500.
Language in contracts placing one party at the mercy of the other is not favored by the courts, and, while such clauses have some effect, the literal absolutism with which Vice’s counsel insists upon language construed to mean that O
&
E had to resort to any means whatever to expedite a cоntract entered into without completion date, at the categorical dictation of the other party, is not supported by the decisions
(Sanford
v.
Brown Bros. Co.,
In this view of the case, the effect of the general release given by Tibbetts to Vioe at the time of payment of the $91,500 for the separate job contracted directly with Vioe becomes immaterial. It has been contended that this discharged Vioe not only from its obligation to pay Tibbetts for that job but also for any other job on account of which on any theory Vioe might be held liable. Since Tibbetts’ recovery is against O & E, the liability of Vioe
Our conclusion is that the failure of O & E to resume performance within three days on demand, and taking its equipment temporarily to the neighboring job at Idlewild, at a time when continuance or resumption of the work would have been futile or inordinately costly in view of the frozen condition of the ground (preventing backfilling and grading operations) and the lack of completion of the trench and drainage operations, did not constitute a breach of the contract. The belated demand for a pеrformance bond, as well as any other defects which may have existed in performance, was waived in any event through the acquiescence of Vioe and its acceptance of the work done by Tibbetts under subcontract from O & E. The O & E contract was entire, as has been stated, nor is that circumstance altered by the language of the agreement purрorting to permit Vioe, under certain circumstances, to “ employ others to complete all or part of the remaining portion of your contract ’ ’. It is apparent that these words could not make severable a contract which by its structure is entire, so as to continue it partly in existence when once it has been repudiated.
As was well stated by the trial court (p. 645): “ The contract being for the lump sum of $127,500 for both the excavation and drainage work is a single, entire and undivisible contract
(New Era Homes Corp.
v.
Forster,
The order of the Appellate Division should be reversed, as well as its new findings, and the findings and judgmеnt of the trial court reinstated, with costs in this court and in the Appellate Division to plaintiff-respondent-appellant and to defendant-respondent-appellant.
Order of Appellate Division reversed and judgment of the Special Term reinstated, with costs in this court and in the Appellate Division to plaintiff and defendant 0 & E Contracting Company, Inc., against defendant Vioe Realty Corp.
Notes
The amount of the recovery allowed to O & E by the trial court was computed by awarding in excess of the $74,000 already paid, as damages, the $30,217 owing to Tibbetts on the subcontract, $14,000 represented by the retained percentage, plus the sum of $4,783 representing extras and loss of profits, making in all the sum of $49,000 — out of which Tibbetts would be paid.