BACKGROUND
Plaintiff-appellant Thyssen, Inc. (“Thys-sen”) contracted for a cargo of steel coils and the cargo’s delivery • to the United States with a Hong Kong company, Me-talsrussia, on October 26, 1996. Delivery was to be completed by January 31, 1997. Metalsrussia arranged to ship the coils by subchartering the MARKOS N from Western Bulk Carriers, which had previously chartered the ship from its owner, Defendant-appellee Calypso Shipping Corp., S.A. (“Calypso”).
Two bills of lading issued for Thyssen’s cargo from an agent of Western Bulk Carriers on January 23 and 24,1997, referencing the above-mentioned charter party. Both bills of lading contain, as the first condition of carriage, the provision: “All terms and conditions, liberties and exceptions to the Charter Party, dated as overleaf, including the Law and Arbitration Clause, are herewith incorporated.”
When the coils arrived in the United States, they were damaged by rust. Despite the damage, Western Bulk Carriers was paid by Metalsrussia, which was in turn paid in full by Thyssen. The dispute now is between Thyssen and the vessel’s owners and managers and the ship itself in rem.
Thyssen brought suit in the Southern District of Texas on March 5, 1997, which issued a warrant for the arrest of the MARKOS N and ordered expedited discovery to allow inspection of the vessel. In exchange for the release of the ship, Thyssen accepted a “Club Letter of Undertaking” from the vessel’s insurer, which promised to pay up to $600,000 in the event of a final judgment for the plaintiff. The letter reserved all defenses.
The parties agreed to transfer the action to the Southern District of New York in August of 1997. On March 11, 1998, a little more than one year after the alleged damage took place, Calypso filed an answer on behalf of itself and the vessel.
The district court (Mukasey, J.) stayed the federal court proceedings. It found (1) that Thyssen’s bill of lading incorporated the London arbitration clause of the MAR-EOS N charter party between Western Bulk Carriers and Metalsrussia; (2) that there was adequate evidence of the incorporation by reference of a written arbitration provision into the charter party; (3) that the charter party contained a “broad” arbitration clause sufficient to bind nonsig-natories; (4) that Thyssen’s in rem action against the vessel was arbitrable; (5) that Calypso had not waived its right to arbitrate the dispute by allowing the litigation to proceed; and (6) that whether Thys-sen’s claims were time-barred was a matter for the arbitrator to decide.
London arbitrators were appointed, but the parties agreed to allow the Commercial Court in London to decide whether or not Thyssen’s claims were time-barred. (English law, like COGSA, includes a one-year time bar on damaged-goods claims.) That court decided that the claims were indeed time-barred and, finding that the delay was Thyssen’s fault and doubting Thyssen’s claims that it had tried and failed to obtain copies of the charter parties, refused to exercise its discretion under the English Arbitration Act to grant an extension. The Commercial Court thereupon dismissed Thyssen’s claims in a decision that Thyssen did not appeal.
The case returned to the federal district court, which confirmed the arbitration award and finally disposed of all of Thys-sen’s claims. In so doing, the court turned aside arguments by Thyssen that (1) the arbitration was aborted and should therefore be voided pursuant to 9 U.S.C. § 10(a)(4), and (2) that since arbitrators have no in rem jurisidiction under English law, any contractual clause purporting to force London arbitration of in rem claims would be void under COGSA, 46 U.S.C. § 1303(8).
Thyssen appeals these two decisions of the district court on four grounds: (1) Calypso waived arbitration by waiting as long as it did before raising its right to arbitrate. (2) Dismissal of Thyssen’s in rem action against the MAREOS N deprived Thyssen of a remedy. (3) Requiring London arbitration of Thyssen’s in rem claims violates COGSA § 3(8).(4) The arbitration clause in the charter party should not be enforced, because neither party to the bill of lading was a signatory of the charter party, and because Thyssen was unaware of the charter party’s contents.
DISCUSSION
I. Waiver
We review de novo a district court’s decision regarding waiver of a party’s right to arbitrate, but we review the factual findings on which the district court relied for clear error. See S & R Co. of Kingston v. Latona Trucking, Inc.,
“[TJhere is a strong presumption in favor of arbitration^ and] waiver of the right to arbitration is not to be lightly
The key to a waiver analysis is prejudice. “[Wjaiver of the right to compel arbitration due to participation in litigation may be found only when prejudice to the other party is demonstrated.” Rush v. Oppenheimer & Co.,
In the instant case, it is clear that Thyssen did not face excessive costs. Though there was a significant length of time between the filing of the complaint and the assertion of Calypso’s right to arbitrate, there was no evidence of extensive discovery or substantive motions by Calypso. This Circuit has refused to find waiver in a number of cases where delay in trial proceedings was not accompanied by substantial motion practice or discovery. See, e.g., Shearson Lehman Hutton, Inc. v. Wagoner,
In arguing substantive prejudice, Thys-sen offers two theories. First, it contends that Fed.R.Civ.P. 8(c) requires all affirmative defenses, and arbitration in particular, to be pleaded in the answer. Accordingly, Thyssen cites McDonnell v. Dean Witter Reynolds, Inc.,
This argument runs afoul of the applicable precedent of this Court: “Absent a demonstration of prejudice by [the defendant], the bare fact that the defendants filed an answer is inadequate by itself to support a claim of waiver of arbitration.” Rush,
Thyssen’s second argument is that it was substantively prejudiced by the fact that its claim was time-barred by the time arbitration was reached. But Calypso correctly responds that the applicable one-year limitation period had effectively expired before the defendant even answered. Thus, there was no substantive prejudice. We therefore agree with the district court’s conclusion that there was no waiver. Cf. e.g., Rush,
II. In Rem Claims
Thyssen makes two separate but related arguments regarding the refusal of the district court to entertain its in rem action against the vessel. First, Thyssen claims that its in rem rights, which it maintains are distinct and separable from its in per-sonam rights against Calypso, were not and could not be adjudicated by the London arbitrators and hence should not have been made to depend on that arbitration. Second, Thyssen asserts that under COG-SA § 3(8), 46 U.S.C. § 1303(8), its in rem rights could not properly be submitted to London arbitration.
A. FAA Section 8 Precludes Thys-sen’s In Rem Claim.
Thyssen argues that the district court erred in dismissing its in rem claim because the arbitrator ruled only on the in personam claim. English law does not grant arbitrators in rem jurisdiction, and, Thyssen argues, this means that the dismissal of the in personam claim should have no bearing on its in rem action. Section 8 of The Federal Arbitration Act (“FAA”), however, addresses this concern directly, making clear that where there is an arbitration clause in a contract, in rem proceedings serve to provide a plaintiff with security while the in personam claim awaits arbitration. See 9 U.S.C. § 8. The very applicability of the FAA to maritime contracts rests on this point. Almost all maritime disputes generate both an in personam and an in rem claim; if plaintiffs were able to bring in rem claims in court after the failure of their in personam claims before an arbitrator, parties would have no incentive to arbitrate maritime matters.
The FAA provides that the Act applies to arbitration agreements in maritime transactions, which include “charter parties, bills of lading of water carriers ... collisions, or any other matters in foreign commerce which, if the subject controversy, would be embraced within admiralty jurisdiction.” 9 U.S.C § 1. All of these transactions give rise to in rem claims against ships. Section 8 of the Act explains clearly how such in rem claims must be handled:
If the basis of jurisdiction be a cause of action otherwise justiciable in admiralty, then ... the party claiming to be aggrieved may begin his proceeding here*107 under by libel and seizure of the vessel or other property of the other party according to the usual course of admiralty proceedings, and the court shall then have jurisdiction to direct the parties to proceed with the arbitration and shall retain jurisdiction to enter its decree upon the award.
Id. § 8. Under § 8, the plaintiff may seize the ship in rem, obtain a bond, and proceed with arbitration. If the plaintiff wins but cannot recover against the owner of the vessel, it can recover against the vessel itself. See Diana Compania Maritima, S.A. v. The Subfreights of the S.S. Admiralty Flyer,
B. Referral of Thyssen’s In Rem Claim to a London Arbitrator Does Not Violate COGSA § 3(8).
COGSA § 3(8) states that “[a]ny clause, covenant, or agreement in a contract of carriage relieving the carrier of the ship from liability for loss or damage to or in connection with goods, arising from negligence, fault or failure ... shall be null and void and of no effect.” 46 U.S.C. § 1303(8). Thyssen argues that, given the London Arbitrator’s lack of in rem jurisdiction, the arbitration clause in the charter party operated as such a clause, and hence upholding the arbitrator’s decision violates § 1303(8). Even assuming arguendo that the lack of an in rem cause of action could be considered a violation of COGSA (a ruling that would contradict most case law on the matter, see, e.g., Fireman’s Fund Ins. Co. v. M.V. DSR Atlantic,
III. Applicability of the Arbitration Clause to Non-signatories of the Charter Party Ignorant of the Charter Party’s Contents
Thyssen does not dispute that it can be bound to arbitrate its claims by signing a document that incorporates another document by reference. Rather, it claims it
CONCLUSION
Having reviewed all of Thyssen’s claims and finding them to be without merit, we AFFIRM the district court’s grant of summary judgment to the Defendant-appel-lees.
Notes
. Defendant-appellee A.M. Nomikos & Son Ltd. manages the ship.
. We do not decide today the issue of whether admiralty claims in rem can ever survive the dismissal of in personam claims.
