13 Minn. 498 | Minn. | 1868
By the Oowrt
I. —The relief sought in this action is the removal of a dám by which the plaintiff claims that his lands are unlawfully overflowed and damaged. The defendants insist that as the dam complained of was erected more than-two. years prior to the commencement of this action, the plaintiff is denied the rig'ht to recover damages by section 17, page 819, Public Statutes, which is substantially the same as section 17, page 211, General Statutes, which reads as follows: “No action for damages occasioned by the erection and maintenance of a mill dam shall be sustained unless such action is brought within two -years after the erection of said dam,” &c.; and that as he cannot recover damages he cannot maintain this action to abate the dam.
The same point was made in Eastman et al. vs. St. A. Falls W. P. Co. et al., 12 Minn., 137, and we there held ■ that “ whether the right of action at law for damages is barred, or not, is immaterial, as this is an equitable action for the removal of a nuisance, and governed by Sec. 12, Chap. 60 of the Public Statutes.” See also Cooke vs. Kendall, ante, p. 324.
II. —The defendants claim that “this action should have been dismissed because of the pendency of a former suit.” The Court below finds “ that another action was commenced by the plaintiff against the defendants with other persons for the same cause of action, (as alleged in the answer) and issues of fact and law framed upon the pleadings therein. That the issue of law in said action was tried and determined in this Court, while the issues of fact therein were still pending and undetermined, and from the decision and order in defendants’
As a corresponding conclusion of law it is found “ that said proceedings to dismiss said former action were operative, and that no action was pending for the same cause at the time this suit was brought.”
As to the issues (in the former action) which remained pending in the District- Court, the discontinuance would appear to be sufficient under the provisions of Seo. 4,page 537, Pub. Stat.
As to the issue of law to which the appeal in the former action related, we find upon the records of this Court an order of dismissal entered subsequently to and in pursuance .of the determination of such appeal, and on the 22d day of March, which was .before the commencement of the present action. This order recites the payment of the costs and was entered upon the application of the appellants in that case. These facts which show that the former action spoken of was not pending in this Court at the time when the present action was commenced, were not made to appear to the Court
Por the purpose of upholding the determination of the Court below, when it is' so manifestly correct, we feel warranted in taking notice of our own records. So doing, we are of opinion that the Court was right in finding for the plaintiff upon the issue, as to the pendency of the former action.
III. — The defendants are evidently mistaken in stating that the judgment is too broad because it requires “ the removal of the whole dam instead of so much thereof as occasioned the overflow.” The defendants are only.required to remove it “so as not to overflow the plaintiff’s land.”
Judgment affirmed.