73 W. Va. 618 | W. Va. | 1914
The decree complained of is one enforcing a mechanic’s lien. Barringer, himself a contractor and builder, began the erection of a house on a lot owned by him. Some time thereafter, he contracted1 in a general way with Thorn, a material man, to be furnished with all materials necessary to be used in the building. Barringer under the contract ordered from Thorn many shipments of materials which went into the building. When the main part of the house was nearly done, and after a cessation of work thereon for several weeks,
. Heatwole, on the day that the property was conveyed to him, executed a deed of trust thereon to secure a loan from "Williams, and the same was at once duly recorded. SO' we have observed that during the process of the execution of Thorn’s contract with the owner for furnishing the materials necessary to be used in the house, the property was conveyed away by the owner and was incumbered by the grantee.
In this suit by Thom to enforce the lien, the purchaser, the deed of trust holder, and the trustee in the deed of trust were of course joined with Barringer as parties. The circuit court decreed that Thorn’s lien was a valid one against the property for the amount due him for all materials furnished under the contract and used in the building, notwithstanding some of them were furnished after the time of the conveyance and incumbrance. The lien was given priority over the conveyance and the deed of trust. Prom the decree, Heatwole, the purchaser, has appealed.
Appellant maintains that the materials were not furnished under one continuous contract; that the materials furnished Barringer while he was actually the owner constituted a claim for a distinct lien under Code 1906, ch. 75, sec. 2, the statutory time for the filing of which had expired at the time of the conveyance; and that the materials furnished Barringer after he became a contractor under the vendee constituted a claim
The court below evidently viewed the contract between Thom and Barringer as a continuous one upon which a valid lien could be claimed for all the materials furnished thereunder, as an entirety. The evidence justified such a view. Though the contract did not define just what materials should be furnished or the exact price of the same, yet it contemplated one settlement for all materials that Barringer should order from Thorn and use in the building under process of erection at the time. It was not limited to any particular part of the building. It was broad enough to embrace the furnishing of any materials that might be necessary in making ever so large a house of the ineompleted building. As long as Barringer continued to order materials from Thorn for use in the build-ins’. the contract continued, forming in the end an entire one. “When work or material is done or furnished, all going to the same general purpose, as the building of a house or any of its parts, though such work be done or ordered at different times, yet if the several parts form an entire whole, or are so connected together as to show that the parties had it in contemplation that the whole should form but one, and not distinct matters of settlement, the whole account must be treated as a unit, or as being but a single contract. ’ ’ Phillips on Mechanics’ Liens, see. 229. The contract between Thorn and Barringer being a continuous one, the lapsing of the statutory period for filing a lien, between items of materials furnished thereunder, can not make separate contracts out of it; nor can the same defeat right to a lien based on the contract as an entirety, if filed in time at the end. D. L. Billings Co. v. Brand. 187 Mass. 417; O’Niel v. Taylor, 59 W. Va. 370.
Under our law Thorn’s lien attached to the oroperty, for all materials furnished by him under ibe contract and used in the building, as of the time that his furnishing the materials and the use of them began. Cushwa v. Improvement &c. As
One purchasing premises on which buildings are in process of erection must táke notice of any mechanic’s lien right that has attached prior to his purchase. He must inquire what contracts are in course of execution on a property he is about to buy. He must further inquire what has been done and may. be done under any such contracts that he finds. “A party purchasing premises on which buildings are in the process of erection, having knowledge of the same, is bound to make inquiry as to t'he rights of parties furnishing materials or performing work thereon, and is • charged with constructive, if not actual notice of their lien.” Phillips on Mechanics’ Liens, sec. 227. “The fact that the work is in progress, is a notice to all of the rights of the mechanic, and all conveyances made during that time are made subject to the mechanic’s rights.” Rockel on Mechanics’ Liens, sec. 150. Appellant therefore when he purchased from Barringer was charged with notice of Thorn’s right to a lien for all done and to be done under the contract, and took the property subject to the same. The house was an incompleted one. He was bound to inquire into the rights of those who had done work thereon or furnished the materials therefor, and to view those rights under the law. It is said that as no work had been done on the building for more than sixty days prior to his purchase, he could assume that all incipient or unfiled claims to liens had ended. But he was obliged to go further and inquire .for such continuous contracts as' the one with Thorn, as to which a cessation of work meant nothing if the contract was afterwards carried out. The incompleted state of the house gave appellant notice that partially performed continuous contracts for work or materials were likely to exist as to it. In reason he was bound to know that Barringer, who had begun the building and whom he retained to complete it, could have such contracts and could continue to get materials under them.
Where mechanic’s liens attach as of the time when perform-
Thorn’s lien was properly claimed and perfected under Code 1906, eh. 75, sec. 2, which provides for a lien for materials furnished “by virtue of a contract with the owner.” Where one furnishes materials under a contract with the owner, as did Thorn in this case, that section alone governs. It requires no giving of direct notice to one who steps in as a purchaser from the owner after the lien has attached by part performance under the contract. Thorn had no contract with Barringer as contractor under appellant, so the provision for notice to the owner under Code 1906, ch. 75, sec. 3, does not apply. The notice to the owner demanded by the latter section is as to a lien claimed under a contract with a principal contractor or his sub-contractor. We have no such case before us, for Thorn furnished the materials for which he filed the lien wholly under a contract with Barringer as owner, and no part of them under a contract with Barringer as a contractor. He was the owner when the contract on which the lien is based was made and when the lien attached by performance begun under that contract. Barringer having been owner then, he is rightly to be considered owner in
Thorn cross-assigns error as to the allowance of a credit on the lien amount claimed by him. Under the evidence we would not be warranted in disturbing the finding of the commissioner and the decree in this particular.
In the light of the foregoing we conclude that the mechanic’s lien is a valid one, taking priority over the conveyance and the deed of trust, and that the decree must be affirmed.
Affirmed.