136 Mo. App. 404 | Mo. Ct. App. | 1909
This is an action for damages caused by negligente. On the 21st day of November, 1906, the defendant as a common carrier received from the plaintiff at Mecca, on the line of its railroad, two carloads of hogs, consisting of one hundred and ninety-eight head, for transportation to market at gt. Joseph, Missouri. The hogs Avere loaded at about 4:40 o’clock p. m. of the day in accordance with the directions of defendant’s agent. The hogs Avere to be transported to Osborn and then to be delivered to the Chicago, Burlington & Quincy Railroad, over which they were to be carried to their destination. The train that was expected to carry the shipment was derailed before it reached Mecca and did not arrive, and the hogs remained loaded on the cars until about 3:38 p. m. of the next day, when they were carried to Osborn, where they were received by the connecting carrier and by it were delivered at gt. Joseph, but arrived many hours
The evidence tended to show that in consequence of the delay the plaintiff suffered a loss in a decline of the market; that some of the hogs were crippled, and some of them suffocated.
The defendant, in order to show that the delay was caused by an unavoidable accident, introduced in evidence the testimony of the employees in charge of the train, which was to the effect that they examined the track at the place of derailment and that there was nothing wrong with its condition and that they could discover nothing, in their opinion, that caused the derailment. The persons in charge of the track were also introduced to prove the good condition of the tracks. And the car inspector was introduced, whose testimony was that the cars were in good condition. It was a mixed train, and the evidence was that the derailment was caused by the front wheels of the baggage car leaving the track. The court: by appropriate instruction submitted the issues to the jury which returned a verdict for plaintiff, upon which judgment was rendered, and defendant appealed.
The defendant contends that under the evidence the plaintiff was not entitled to recover, and that, therefore, the court committed error in not sustaining its demurrer to plaintiff’s evidence. It is conceded that it was the duty of defendant as a common, carrier to have safely delivered plaintiff’s hogs at their destination Avithin a reasonable time; and that the only causes that would justify, a breach of duty in that respect are those which could not be reasonably anticipated, such as the act of God, that of the public enemy, unavoidable accident, etc. . Results, attributed to a defective roadbed or tracks and defective equipments, afford no excuse for the non-performance of the carrier’s duty to safely deliver the goods of the shipper to their destination within a reasonable time. [McFall v. Rail
When it was shown that the delay was caused by a wreck of the train, which it was intended should carry plaintiff’s hogs, prima facie a case of negligence was made out, which shifted the burden of proof upon defendant to show that it was the result of unavoidable accident. [McFall v. Railway, supra; Vencill v. Railway, supra; Keyes-Marshall Bros. Livery Co. v. Railroad, 105 Mo. App. 556.] This, defendant undertook to do by evidence as to the good condition of its track and its cars. But it was still a question for the jury and not for the court to say whether defendant had made good its defense in that respect, and that question was properly submitted to the jury.
Affirmed.