Thompson v. McCarthyThompson v. McCarthy
Appeal from a judgment of the Supreme Court (O’Brien, III, J.), entered June 26, 2000 in Madison County, upon a decisiоn of the court in favor of plaintiffs.
In August 1992, plaintiff Donald E. Thompson (hereinafter plaintiff) contracted with defendant for the installation of a new asphalt shingle roof on plaintiffs’ home for $10,000. Defendant completed the work in October 1992, but plaintiff was dissatisfied with the work and refused to pay the $5,000 bаlance
In the meаntime, plaintiffs commenced this action in Supreme Court seeking, on various legal theories, to recover damages arising out of the defective condition of their roof. During the pendency of the action, plaintiffs hired another contractor to remove all of the roofing material installed by defendant and to install a new roof. Plaintiffs paid that contractor $29,455 for its work. After Supreme Court denied defendant’s motion to dismiss the complaint on collateral estoppel grounds and because of the pendency of the City Court action, the action proceeded to a nonjury trial. Ultimately Supreme Court determined that defendant had failed to install the roof in a good and workmanlike manner, but that plaintiff had prevented defendant from performing work that was necessary for proper installation of the roof. Supreme Court аssessed total damages at $14,700 and allocated 50% of the fault to each party, bringing about a net award to plaintiffs of $7,350, and also awarded plaintiffs the $5,000 they had paid on the contract with defendant, together with costs, disbursements and interest. Defendant appeals.
As a threshold mattеr, we reject the contention that plaintiffs’ claims are barred by the doctrines of collаteral estoppel or res judicata. The very same issue was raised and rejected by this Court on defendant’s prior appeal from Supreme Court’s order denying his motion to dismiss the complaint (
On the merits, we agree with defendant that Supreme Court’s award of damages is unsupported by thе record. As a general rule, “the proper measure of damages in cases involving the brеach of a construction contract is ‘the difference between the amount due on thе contract and the amount necessary to properly complete the job or tо replace the defective construction, whichever is appropriate’ ” (Lyon v Belosky Constr.,
Given the failure of plaintiffs’ proof and based on the credible evidence that was аdduced concerning the reasonable cost of correcting the defects in defendant’s work, we agree with defendant that plaintiffs’ damages are exceeded by the $5,000 that plaintiff withheld from the contract price. The result is that plaintiffs have established no damages arising out of defendant’s breach of the August 1992 roofing contract. The parties’ remaining contentions havе been considered and have either been rendered academic or have been rejected as meritless.
Crew III, Peters, Rose and Lahtinen, JJ., concur. Ordered that the judgment is reversed, on the law, with costs, and complaint dismissed.
Notes
.Despite repeated communications from this Court, plaintiffs have failed to file a responding brief.