143 Va. 451 | Va. | 1925
delivered the opinion of the court.
This is a controversy, in the main, between mechanic’s lien creditors over a fund in the hands of an owner of a building. Incidentally, there is also involved a question as to the extent of the liability of such owner. A number of questions have been raised and discussed by counsel, but it will not be necessary to. consider them, as a brief statement of the evidence in the ease will show that the case is controlled by Schrieber v. Citizen’s Bank, 99 Va. 257, 38 S. E. 134, which we fully approve and adhere to.
In Schrieber v. Bank, supra, the Citizens Bank of Norfolk had contracted with one May for the construction of its banking building, at a cost of upwards of $95,000. At the conclusion of the work the bank had in hand some $4,400. Subcontractors had- filed mechanic’s liens for claims largely in excess of this amount, and the bank brought suit to have the rights of the parties determined. The bank claimed the right to deduct from the amount apparently in its • hands certain claims for work and material which had entered into the building, and for which it had paid or
“Adverting to the alleged errors in the order of their assignment, the court is of opinion that it was not error to allow the bank credit for the sum of $808.13 paid by it for work done and materials furnished by Julian C. Smith, a subcontractor. Smith had been employed by the general contractor to do certain asphalt paving around the building. Being in doubt whether the general contractor would pay him, he declined to undertake the work unless the bank would guarantee the payment of his claim. This the bank was obliged to do in order to have the pavement completed in accordance with the plans and specifications. The contract provided that in case the general contractor failed in the performance of any of his agreements, the owner should be at liberty to supply the deficiency and deduct the cost from any money due or to become due under the contract. This item for the paving done by Smith was clearly covered by that provision. ifc :$« ifc
“The court is further of opinion that there was no error in allowing the bank credit for notes held by it which had been executed by the general contractor, and endorsed by the several subcontractors to whom they were payable, and discounted by the bank for the benefit of the latter. Nor was it error to allow the
In the instant case the facts are as follows: On October 7, 1922, Mrs. McCauley entered into a written contract with C. V. Lang, doing business as C. V. Lang & Co., to erect for her a dwelling house near the University of Virginia, at the price of $6,500. Of this sum $4,000 was to be paid in installments of $1,000 each at stated times specified in the contract, and the remaining $2,500 on the completion of the job. Shortly after entering into the contract C. V. Lang & Co. made off a bill for the principal part of the materials and lumber to be used in the construction of the house and furnished it to the Charlottesville Lumber Company with request for prices. The parties agreed on the price and the lumber company furnished a small part of the bill. But Lang had°a bad reputation for paying his bills and was insolvent. The Charlottesville Lumber Company had previously had trouble about getting their money and had adopted the practice with him of getting a guaranty of payment from the owner.
In April, June and July, 1923, within the time prescribed by law, the appellants docketed mechanic’s liens for the amounts severally claimed by them. In April, 1923, the Charlottesville Lumber Company also docketed a claim for the balance claimed by it, and in August, 1923, brought this suit to enforce its mechanic’s lien. The bill sets out all of the foregoing facts, and claims priority of payment of its claim out of the $2,500 left in Mrs. McCauley’s hands. Mrs.
It will be observed that if the guaranty of Mrs. McCauley to the Charlottesville Lumber Company be upheld as valid, then at the time of the filing of the mechanic’s liens of appellants she was not indebted to C. V. Lang & Co. in any amount and hence there was nothing to which their liens could attach. Code, sec. 6428. It is obvious, therefore, that the validity of this guaranty is the chief, if not the only, question in controversy. Its validity is fully established by Schrieber v. Bank, supra.
The bill of lumber had been ordered by Lang & Co. and had been accepted by the Charlottesville Lumber Company. The quality, quantity and price thereof had .been agreed upon by the parties, and Mrs. McCauley had the right to guarantee its payment without notice to other creditors. Notwithstanding the terms of the contract between Mrs. McCauley and Lang, she could, with his consent, have paid the whole construction price to Lang in cash, or have accepted orders from him in favor of other subcontractors, or have paid his
In any view of the case, Mrs. McCauley is entitled to the credit claimed by her and awarded by the trial court.
Much was said in the argument about the failure of Mrs. McCauley to give notice to other contractors of her guaranty to the Charlottesville Lumber Company. She was under no obligation to do so. All persons have the right to stand on their legal rights. These transactions took place while the Code of 1919 was in full
Counsel point out no substantial difference between the instant case and Schrieber v. Bank, supra. In the petition it is said: “Your petitioners respectfully represent that this case does not come under the decision of Schrieber v. Bank, 99 Va., p. 257, 38 S. E. 134, as that case was governed by the terms of the contract between the bank and the contractor, which contract provided, as stated by court at page 260: ‘The contract provided that in case the general contractor failed in the performance of any of his agreements, the owner should be at liberty to supply the deficiency and deduct the cost from any money due or to become due under the contract.’ ” But it is manifest that the owner had this right independent of any contract stipulations, and it is also expressly provided for by section 6432 of the Code.
In the reply brief it is said that in Schrieber v. Bank, supra, “all of the funds for which said bank was allowed credit had been actually paid and not contracted or promised to be paid.” This is error. The opinion shows that one of the large items was for concrete work, the payment for which had simply been guaranteed by the bank. But we should not regard it as material whether payment had been actually made or simply guaranteed, where the owner was abundantly solvent.
It is said in the petition that Mrs. McCauley “per
The decree of the trial court is plainly right and will be affirmed.
Affirmed.