73 A. 722 | Md. | 1909
The appellant sued the appellees and Isaac S. Filbert for injuries alleged to have been sustained to his properties on the southwest corner of Broadway and Hoffman streets in the City of Baltimore, numbered 1328-1336 North Broadway. The case has some peculiar features. Although the Filbert Paving and Construction Company was made a party by amendment, the declaration alleges that the Mayor and City Council of Baltimore, being the owner of the beds and alleys in the city and particularly of the beds of Broadway and Hoffman streets and the "ten foot" alley in the rear of the plaintiff's premises, undertook with the assistance of the defendant, Isaac S. Filbert, "to change the grade of Hoffman street at said point and to repave the street, the said work *133 being done in such a careless and negligent manner as to seriously damage the said properties of the plaintiff, and the water which had hitherto for years been accustomed to pass out of said alley in the rear of said properties and out Hoffman street was diverted from its usual course and dammed up in such a careless and negligent manner by said defendants as to cause the same to overflow and flood the properties above mentioned of the plaintiff, whereby the same were greatly damaged," etc. It will be observed that the Filbert Paving and Construction Company is not alleged to have been connected with the work, and during the trial the case against Isaac S. Filbert was dismissed. There is no reference to the company in the narr. excepting in the beginning where it is mentioned as one of the defendants.
Then in the evidence, as will be seen later, the cause of the injury was claimed to be the alleged negligent filling and repaving of the alley near Hoffman street. At the conclusion of the plaintiff's testimony the Mayor and City Council of Baltimore and the Filbert Paving and Construction Company, each offered a prayer that there was no evidence legally sufficient to entitle the plaintiff to recover against it and the verdict must therefore be for it. Both of the prayers were granted, a verdict was rendered for the defendants and from the judgment entered on that verdict, this appeal was taken. The prayers do not refer to the pleadings and hence their correctness must be determined entirely by a consideration of the evidence. 2 Poe, sec. 302;Con. Ry. Co. v. Pierce,
It is not denied that there was evidence of injury to the plaintiff's property, and hence we need only determine *134
whether there was legally sufficient evidence that such injury was caused by the defendants, or either of them, in a way which made them liable. It is contended on the part of the city that it is relieved from liability because the work was done by an independent contractor. The general principles applicable where work is to be done by a contractor, upon his own responsibility, who is not subject to the control of the employer as to the manner in which it is to be performed, have been well established in this State since they were so clearly announced by JUDGE ALVEY in DeFord v. State,
That distinction has been consistently recognized in our decisions since DeFord's Case was determined and may be illustrated by citing some of them. In Moores' Case,
In O'Donnell's Case,
It cannot be denied that it was the duty of the city to have this work so done that it would not cause unnecessary injury to the public, or to the owners of adjoining properties, and it could not relieve itself of all liability by having the work *137 done by an independent contractor. There was evidence tending to show that the cause of the trouble was that at the end of the alley, next to Hoffman street, there was a pond of water resulting from it being dammed up after the street was finished, and a drain which had conducted the water from the alley to a sewer on Broadway had been taken up; that dirt was then hauled to the alley and "dumped into this slushy part until it was filled up." The plaintiff told the superintendent "that isn't going to be a job," but they paved the alley, which was then slushy ground, according to the plaintiff's testimony. There was a fill on the east side of the alley of three feet and one the west side of three feet seven inches — making a slope of seven inches towards Broadway. In paving, by reason of the slope, they deflected the gutter stones from the center of the alley to the curbstone at the corner of the building line of Hoffman street and the North-eastern end of the alley. The theory of the plaintiff was that by reason of paving the alley in the condition in which it was, owing to the dirt being dumped in the water and causing slush, the stones sank and let the water from the alley go down under the stones and run under the sidewalk on Hoffman street to Broadway, and then, by reason of the solid foundation under the pavements on Hoffman street and on Broadway, the water was backed up until, the foundation of his house being weaker, it found its way into his cellar. There is ample evidence to sustain that theory, and it also shows that there was a crevice between the gutter stones about half an inch wide and eight to twelve inches long, through which some of the water, passing down the alley, went and eventually got into the plaintiff's cellar.
The plaintiff's testimony also tended to show that the conditions complained of existed from time to time from October 10th, 1903, until sometime in 1905, when he finally ascertained what the cause was and corrected the trouble. He testified that the floodings of his cellar occurred on over twenty different occasions he had made note of — including from October 10th, 1903, to February 13th, 1905; that before *138 the improvements were made he had never had any trouble with water in his cellar and that since he had some concreting done in the alley, in October, 1905, no water had gone in "and it is as dry as a bone, as it used to be before." He complained to the city authorities at least as soon as the early part of 1904 and about the 23rd of February of that year the City sent a man to fix the alley. He caulked the gutter stones which stopped the water for a little while, but it did not last. As early as March 8th, 1904, there was some correspondence between the plaintiff and the City Engineer.
We have thus referred at some length to the evidence in reference to the conditions existing to show that for a long time after the work was done by the contractor the plaintiff suffered injury by reason of its faulty construction. Even if the city could have escaped liability from injuries sustained by the plaintiff while the work was still in the hands of the contractor, it could not have done so for those sustained after it had taken control of the street and alley. Sipe v. P.R.R.Co., 71 At. Rep. 847; 26 Cyc., 1566, where many cases are cited.
But the evidence also shows that the Assistant City Engineer "saw the work being done every day while it was in progress and mostly under his inspection." The contract provided that "All material furnished and work done, not in accordance with these specifications, shall be removed within twenty-four (24) hours after written notice from the city engineer, by and at the expense of the contractor; or in case of failure to do so, it shall be removed by the city and the cost charged to the contractor and deducted from the amount due him." There is a provision that "All soft and spongy material below the sub-grade shall be removed and filled with clean, sharp sand or gravel or other material satisfactory to the city engineer, and thoroughly rammed and rolled;" and another that: "Wherever the city engineer is mentioned in these specifications it is understood to be the city engineer in person, assistant city engineer, or the assistant engineer in *139 charge of the work." There are a number of other provisions giving the city engineer more or less control over the work. Under such circumstances we can have no doubt of the liability of the city for defects in the work, causing injury to the plaintiff. It is not only its duty to have such work done, but to have it properly done, so that others will not suffer from it being improperly performed. Our own cases recognize the rule that an employer is not relieved by having a contractor, when he retains control of the work himself. In Bonaparte v. Wiseman,supra, "a party who employs an independent contractor to do certain work, without reserving any control over it is not liable," etc. In Symons Case the fact was noted that the road engineer of Allegany County had no control over the work. See also Stork v. Philadelphia, 199 Pa. St. 462; 16 Am. Eng.Ency. of Law, 187; 26 Cyc., 1565. In this contract there was more than a mere reservation by the city to supervise the work, for the purpose of determining whether it was being done in conformity to the contract. It rather indicates that the city officers realized that they owed a duty to the public, and to those who might be specially interested, to see that the work was properly done. We are, then, of the opinion that the city could not be relieved from this action by reason of the contract made with the Filbert Paving and Construction Company.
The remaining question to be determined is whether there was any legally sufficient evidence to entitle the plaintiff to recover. The Assistant City Engineer testified that the paving, grading and curbing of Hoffman street, from the west side of Broadway to the east side of Bond street, was done by the City of Baltimore, "by and through the Filbert Paving and Construction Company," and the evidence tended to show that what was done in the alley was done by that company in connection with the work on Hoffman street. It was suggested at the argument that this was a private alley, but, however that may be, the work was undertaken by the city in connection with the grading and paving of Hoffman street, and there was unquestionably some evidence tending *140
to show that the work was defectively done and that by reason of the negligent construction the plaintiff suffered loss. The testimony does not show that it was merely an incidental or consequential injury such as may result from the change of a grade of a street, done under legislative authority, and for which the municipality is not liable. "In such cases, if the work be done with care so as to avoid unnecessary injury to adjacent property, and there be no invasion of such property, its owners must suffer the injury resulting from the work thus done to promote the public welfare." Guest v. Church Hill,
It is well settled that, although the powers granted a municipality by its charter to open, grade and pave streets, and to construct such gutters and sewers as in its judgment the public convenience may require, are discretionary, "any particular plan that may be adopted must be a reasonable one, and the manner of its execution thence becomes, with respect to the right of the citizen, a mere ministerial duty; and for *141
any negligence or unskilfulness in the execution or construction of the work, whereby injury is inflicted upon pirvate right, the municipality will be held responsible." Hitchins v.Frostburg,
So within deeming it necessary to discuss other grounds of recovery, as claimed by the appellant, we are of the opinion that there was sufficient evidence in the case to require the Court to submit it to the jury. Of course a further question may arise as to what damages, if any, can be recovered against the defendants jointly as only such as they are jointly liable for can be recovered in an action against the two defendants. 1 Poe, sec. 492. But we are of the opinion the prayers ought not to have been granted and hence the judgment must be reversed.
Judgment reversed and new trial awarded, the appellees to paythe costs above and below.