60 Fla. 372 | Fla. | 1910
The appellees, the City of Pensacola and its contractors, filed a bill in equity in the Circuit Court for Escambia county to declare and enforce a lien against the property of the appellant for sidewalk improvements. A plea was filed denying that the complainants had in all things complied with the ordinances of the city and the laws of the State in directing, ordering and constructing the. sidewalk and that the sidewalk was constructed in ac-
The decree should be construed with reference to the proceedings had, and if it can be so interpreted as to comport with proper proceedings in equity it may be sustained if it is supported by the evidence as submitted by all parties. See Pearson v. Helvenston, 50 Fla., 590, 39 South. Rep., 695; Stackpole v. Hancock, 40 Fla., 362, 24 South. Rep., 914, 45 L. R. A., 814.
Under the old equity practice a replication to a plea in equity admits the legal sufficiency of the plea as a defense to the entire bill of complaint, and puts in issue the averments of the plea. If the plea be proven a dismissal of the bill followed without reference to equities alleged but not met by the plea. See 18 Ency. Pl. & Pr., 685; Pearce v.
Equity Rule 50 provides that: “If upon an issue the facts stated in the plea be determined for the defendant, they shall avail him, as far as in law and equity they ought to avail him.” U. S. Equity Rule, 33, Dewhurst’s Rules of Practice in U. S. Courts, 369. This rule enables a complainant to obtain relief that would under the old practice be denied him where upon replication filed the truth of the plea is proven. Westervelt v. Library Bureau, 118 Fed Rep., 824. The rule allows the averments of the plea to avail the defendant “as far as in law ana equity they ought to avail him,” but no further. The old technical rule of procedure that a plea proven avoids the bill without reference to equities, upon the theory that by filing a replication to a plea the complainant rests the case entirely on the truth of the plea, has been modified. Under the rule the facts averred in a plea if proven avails not to dismiss the bill, but to avoid the equities alleged in the bill as far as in law and equity they should. The decree appealed from in effect allowed the plea to avail the defendant as far as in equity it ought in the judgment of the court to avail him as a defense to the equities alleged. This interpretation being put upon the decree, it should not be reversed unless there is error on the merits.
While the findings and conclusions of a chancellor, where the testimony is not taken before him, but before a master or examiner, by reason whereof he is not afforded an opportunity of seeing and hearing the witnesses, are not entitled to the same weight as the verdict of a jury, yet even in that case they should not be disturbed by an appellate court, unless they are clearly shown to be erroneous. In equity, as well as at law, every presumption is in favor of the correctness of the ruling of the trial judge,
Where a municipality has authority to require land owners therein to construct sidewalks adjacent to their property, and under a valid ordinance a land owner is notified to make the improvement and that in default thereof it will be done by the municipality and a statutory lien therefor acquired on the property, and upon nonobservance of such notice the municipality by contract has the sidewalk put down, the statutory lien may be enforced where there is a substantial compliance with the contract and it is not made to appear that the improvement as made is unsuited to its purpose and not of practical value. A land owner who disregards a proper notice to make a lawfully required improvement or it will be done by the municipality at his expense, cannot successfully resist the acquisition of an authorized statutory lien for the improvement if it is made in substantial compliance with a valid contract, and the improvement is not unsuited to its purpose. See 3 Page on Contracts, Chapters 1385-8; People ex rel. Raymond v. Whidden, 191 Ill., 374, 61 N. E. Rep., 133, 56 L. R. A., 905 and notes.
Under the averments of the plea the lack of the specified thickness appears to be the important deficiency, therefore the real value of the sidewalk, if otherwise constructed in substantial compliance with the contract, may be ascertained and equitably enforced, in the absence of a defense that because of the deficiency in thickness the sidewalk is not suited to its purpose and not of practical value.
The city engineer testified in effect, that he supervised the work, personally examined some of it, and regarded
As there is evidence to sustain the finding for the complainants, and as it does not clearly appear from the whole record that the decree is erroneous on the facts there must be an affirmance, and it is so ordered.