46 Ct. Cl. 521 | Ct. Cl. | 1911
Lead Opinion
delivered the opinion of the court:
The question now arises on the claimant’s motion for a new trial and to amend findings on the ground of error of law as well as error of fact. We will therefore review the case.
The contract in this case for the construction of the battleship Massachusetts is identical with that between the same parties for the construction of the battleship Indiana, and the breaches complained of are in effect the same — that is, by reason of the delay of the Government in furnishing the armor plate in the order which, by the terms of the contract it agreed to do, the completion of the vessel was delayed for two years sis months and nine days, which delay the Secretary of the Navy under the authority of the contract decided was due to the failure of the United States to furnish the materials in the order as aforesaid, and for that reason the time within which to complete the vessel, and thereby release the claimant from the penalties provided for in the ninth clause of the contract was extended by the Secretary a corresponding length of time, to wit, to May 29, 1896, on which date the vessel so contracted for was completed and delivered.
The defense is that the extension of time so granted operated to release the Government from any damages which might have accrued by reason thereof, and, further, that the execution of the modifications of the contract and the releases thereunder, as well as the final release as set forth in Findings V and VI, operated to release the United States from all claims of any kind or description under or by virtue of the contract, including claims for unliquidated damages of the character described in the petition.
The contract and the releases in the case of the Indiana were considered by the Supreme Court (206 U. S., 118, 127), and the judgment of this court was reversed (41 C. Cls., 164). There the contention was as to the effect of the final
“ 6. When all the conditions, covenants, and provisions of this contract shall have been performed and fulfilled by and on the part of the party of the first part, said party of the first part shall be entitled, within ten days after the filing and acceptance of its claim, to receive the said ‘special reserve,’ or the surplus, if any, of the said ‘ reserve fund,’ or so much of either as it may be entitled to, on the execution of a final release to the United States in such form as shall be approved by the Secretary of the Navy, of all claims of any kind or description under or by virtue of this contract.”
In construing that provision of the contract the Supreme Court, among other things, said:
“ Manifestly included within this was every claim arising not merely from a change in the specifications, but also growing out of delay caused by the Government. The language is not alone ‘ claims under,’ but ‘ claims by virtue ’ of the contract — ‘claims of any kind or description.’ All the claims for which allowances were made in the judgment of the Court of Claims come within one or the other of these clauses. It may be that, strictly speaking, they were not claims under the contract, but they were clearly claims by virtue of the contract. Without it no such claims could have arisen. Now, it having been provided in advance that the contract should be closed by the execution of a release of this scope, it can not be that the company, when it signed the release, understood that some other or lesser release was contemplated. It must have understood that it was the release required by the contract — a release intended to be of all claims of any kind or description under or by virtue of the contract, and that the form of words which the Secretary had approved was used to express that purpose.”
And further, in commenting on the release, the court said:
“ Indeed the general language of the release itself and the number of words of description in it show that it was the intent of the Secretary of the Navy to have a final closing of all matters arising under or by virtue of the contract. Stipulations of this kind are not to be shorn of their efficiency by any narrow, technical, and close construction. The general language ‘ all and all manner of debts,’ etc., indicates a purpose to make an ending of every matter arising under or by virtue of the contract. If parties intend to leave some things open and unsettled their intent so to do should be made manifest.”
Following that decision this court, under a like contract between the same parties for the construction of the ironclad Alabama (43 C. Cls., 202, 218), held that when the conditions, covenants, etc., had been performed and final payment made the claimant was obligated to sign the release provided for by the terms of the contract releasing the Government from “ all claims of any kind or description under or by virtue of said contract; ” that the rights of the parties were determined by the contract itself and not by the language of the release. On appeal, however, the case was reversed (216 U. S., 494) on the ground that the proviso to the release in that case excluded claims arising under said contract, which the Secretary of the Navy had no authority to entertain, and in respect of which the court said:
“It results therefrom that a release executed in accordance with the terms of the contract would have extinguished all claims of the company against the United States growing out of the contract (206 U. S., 118); that the Secretary of the Navy had no power to pass upon and adjudicate claims for unliquidated damages; that he had power to accept a release such as was given, and that the proviso left for determination in the courts claims for unliquidated damages growing out of the contract.”
From this it follows that in the present case the claimant must be denied a recovery for the unliquidated damages claimed because the final release it signed was in accordance with the terms of the contract, no reservation being made therein.
The claimant, however, contends that the facts in this case differ from those in the Indiana both in respect of the modifications of the contract and releases thereunder and final release in this, that at the time of the execution of the modifications of said contract and releases thereunder the claimant was, by reason of its financial embarrassment
The claimant’s contention is that the language of the sixth paragraph of the nineteenth clause of the contract was not intended to embrace unliquidated claims, and that, therefore, the language of the final release should be so re-formed as to exclude them. This is a question of law, and was the view of this court in the case of the Indiana; and if the same should be held the correct view now the claimant company would probably be entitled to relief without the re-formation of either the contract or the final release.
But, as the final release, as held in the case of the Indiana, is in conformity with the contract, its re-formation would not avail the claimant without also reforming the contract; and as the evidence disclosed by the findings fails to show that there was any mutual mistake in the contract (nor is any averred in the petition), there is no ground for re-formation. The effect of the claimant’s contention is that under the contract the Secretary of the Navy might, as in the case of the Alabama, have prescribed two forms of receipt; and having prescribed but one, as in the case of the Indiana — though the claimant made no demand otherwise — the
The question then is, do the matters on which the claimant company relies bring the case within the authorities which govern the reformation of contracts? That the claimant has not established by its propositions that there was a mistake in fact in the execution of either the contract or the intermediate contracts or the final release will be seen by a review of the authorities.
As held in the case of Citizens National Bank v. Judy (146 Ind., 322), “In every case it must clearly and satisfactorily appear that the precise terms of the contract had been orally agreed upon, and that the writing afterwards signed fails to be, as it was intended, an execution of such previous agreement, but, on the contrary, expresses a different contract.” That holding is supported by the highest courts in many, if not most, of the States, as will be seen by examining the American & English Encyclopedia of Law, volume 15, page 651, note 5.
In the case of Hearne v. Marine Insurance Co. (20 Wall., 488, 490) the court went further and said: “ The party alleging the mistake must show exactly in what it consists and the correction that should be made. The evidence must be such as to leave no reasonable doubt upon the mind of the court upon either of these points. The mistake must be mutual and common to both parties to the instrument. It must appear that both have done what neither intended. A mistake on one side may be ground for rescinding, but not for re-forming the contract: Where the minds of the parties have not met there is no contract, and hence none to be rectified.”
Later, in the case of United States v. Budd (144 U. S., 154, 161), the court, quoting from the case of Maxwell Land Grant (121 U. S., 325, 381), said: “We take the general doctrine to be, that when in a court of equity it is proposed to set aside, to annul, or to correct a written instrument for fraud or mistake in the execution of the instrument itself, the testimony on which this is done must be clear, unequivocal, and convincing, and that it can not be done upon a bare preponderance of evidence which leaves the issue in doubt.”
In the Milliken Imprinting Company Case (40 C. Cls., 81), where a circular had been issued by the Commissioner of Internal Revenue inviting bids for imprinting stamps, and under the belief that the terms recited in the circular had been set out in the contract the claimant signed the same, but afterwards discovered that certain material portions thereof had been omitted, this court held that there was such mutual mistake as to justify a re-formation; but on appeal the case was reversed (202 U. S., 168) on the ground that there was no mutual mistake justifying the re-formation of the contract.
Therefore the mistake must not only be shown beyond a reasonable doubt, but it must be mutual, “unequivocal and convincing,” and common to both parties; and in this respect .the court, in the case of Diman v. Providence, W. & B. R. Co. (5 R. L, 130), held: “If,the court were to re-form the writing to make it accord with the intent of one party only to the agreement, who averred and proved that he signed it, as it was written, by mistake, when it exactly expressed the agreement as understood by the other party, the writing, when so altered, would be just as far from expressing the agreement of the parties as it was before, and the court would have been engaged in the singular office, for a court of equity, of doing right to one party at the expense of a precisely equal wrong to the other.”
Hence it is uniformly held that a unilateral mistake is no ground for re-formation in the absence of fraud or other inequitable conduct by the other contracting party; and even in such case, if fraud be shown, relief will be granted on that ground rather than for a mistake; nor can the contract be reformed on the ground of mistake arising from ignorance of the law (Hunt v. Rhodes et al., admrs., 1 Pet., 1, 14), unless the party seeking such re-formation was misled as to his legal rights by the statements of the other party — not contended in the present case — (Schell v. Atlantic F. & M. Ins. Co., 98 U. S., 85), but a mere mistake of law without other circumstances constitutes no ground for the re-formation of written
In the case of Hunt v. Rhodes et al., cited above, the Supreme Court, in speaking of the re-formation of a contract on the ground of mistake arising from ignorance of the law, said: “ The question, then, is, Ought the court to grant the relief which is asked for upon the ground of mistake arising from any ignorance of law ? We hold the general rule to be that a mistake of this character is not a ground for re-forming a deed founded on such mistake; and whatever exceptions there may be to this rule, they are not only few in number, but they will be found to have something peculiar in their character.”
This case has been followed by the Supreme Court in many cases since, and the last case is that of Utermehle v. Norment (197 U. S., 40, 56), where, in speaking on this subject, the court said: “ It has been held from the earliest days, in both the Federal and State courts, that a mistake of law, pure and simple, without the addition of any circumstances of fraud or misrepresentation, constitutes no basis for relief at law or in equity, and forms no excuse in favor of the party asserting that he made such mistake.”
It may therefore be laid down as a well-established rule that where there is no mixed question of law and fact and no fraud, undue influence, or deceit a court of equity will not grant relief. In the case of Lyon v. Richmond (2 John (N. Y.) Ch., 51, 60) Chancellor Kent said: “ The courts do not undertake to relieve parties from their acts and deeds fairly done on a full knowledge of the facts, though under a mistake of the law. Every man is to be charged at his peril with a knowledge of the law. There is no other principle which is safe and practicable in the common intercourse of mankind.”
It is manifest from the findings as well as from the evidence that there was no duress, nor was there mutual mistake between the parties either as to the facts or the law, as
But as the re-formation of .a contract is an equitable proceeding, and the Supreme Court reserves to itself the right, if deemed competent and material, to examine and review the evidence independent of the findings, we deem it unnecessary to review the evidence — in the main matter of opinion — or give the substance thereof. The sole ground for a reformation of the final release was the misconception of the claimant company as to its legal rights under the contract, i. e., that the claimant company was damaged by reason of the delay of the Government in furnishing the armor plate in the order agreed upon; that the same was not satisfied by the corresponding extension of time; and that therefore the language of the final release was not intended to embrace claims arising from such delays.
Such was the view of this court in the case of the Indiana, but on appeal the Supreme Court held that the final release was in conformity with the contract and reiterated the same in the case of the Alabama. It follows that to reform said release excluding claims of the character here involved it must be upon the theory that such claims xvere not embraced within the language of the sixth paragraph of the nineteenth clause of the contract. In víoav of the adjudications of the. Supreme Court to the contrary we do not feel at liberty to so hold; nor do we feel at liberty to insert in the final release by construction language reserxdng to the claimant the right to be heard in court when it might, by protest and demand, haxre had the same inserted with the consent of the Secretary. So in the final analysis the case resolves itself into this: Was the language of the final release authorized by the sixth paragraph, clause 19, of the contract? This is a question of construction and not of re-formation, and is answered by the Supreme Court in the case of the Indiana; and as the Secretary, who had the power so to do,
The claimant’s motion for a new trial is overruled. The motion to amend the findings is allowed in part and overruled in part. The former findings of fact and opinion are withdrawn and new findings and opinion are this day filed, the former judgment dismissing the petition to stand.
Dissenting Opinion
dissenting from .the conclusions:
This is a proceeding under the equity powers of the court to reform a contract entered into between plaintiff and defendants for the construction of a battleship known as the Massachusetts; and to reform certain intermediate receipts, and especially to reform the terms of a final receipt given to defendants under an agreement for the construction of the vessel.
Immediately upon the signing of the contract plaintiff prepared the necessary drawings and templates according to the design of the agreement, but the Government decided to use nickel steel in the construction of the armor, thereby suspending their use, and delayed the manufacture of the armor. New sets of both had to be prepared and plaintiff supplied the second set within the time required by the contract. Plaintiff proceeded to that stage when the diagonal armor plates were necessary to go further with the Avork. Some of this armor belt was furnished about a year thereafter, but delivery was not completed until 14 months after the armor plates were called for by the contractor. The delivery of other armor was unreasonably delayed and more than a jrear consumed in harveyizing the plates after they had been finished (according to the original plan), growing out of the election of the Government to substitute the harveyized plates for the original plates. Other necessary material wa's not furnished on contract time, causing a delay of two and a half years. By reason of the several delays and defaults on the part of the Government, plaintiff was put to extra cost and expense and subjected to heavy loss and damage by the interruption to its work, thereby making it necessary for the contractor to provide special
The court is in full accord as to the amount of these items of cost and expenses during the period of delay, and eliminating all claim for interest and every doubtful item the court finds that the actual cost of the care and maintenance of the vessel was $216,000, according to the schedule appearing elsewhere. When the vessel was structurally ready for the trial trip to which, under Article III of the contract, it was entitled without armor (the Government having failed to furnish it), the claimants advised the United States and were prepared to do the necessary temporary work to make it seaworthy for such trial, and upon such trial the claimant company was entitled immediately to a payment of earned money aggregating over $700,000.
The Secretary of the Navy, while admitting and confessing that the delays in the completion of the vessel had been brought about by the default of the United States, refused to permit a trial trip to be made without armor, notwithstanding the provisions of Article III, deeming it to the best interests of the United States to make no trial until the vessel was entirely completed and declined to pay any of the moneys conceded to be earned under the contract unless petitioner would agree to release its claims against the Government on account of its losses and damages. The record shows that at the date of these intermediate receipts, aside from the $730,000 earned on the Massachusetts and withheld because she had had no trial trip, there was due from the United States on other vessels and withheld, on the 10th day of October, 1894, the date of the first receipt, $1,614,013.95, and on the
There is no dispute as to the fact of the Government’s delay and the consequences of that delay to plaintiff, nor is there anjr dispute that the Secretary of the Navy took the intermediate receipts in the belief that the contractor had a remedy either before Congress or in the Court of Claims for its losses growing out of the Government’s delinquencies. But Mr. Cramp was apprehensive at the time the receipts were exacted of and signed by him, and protested vigorously.
At that time, it will be seen hereafter, the Cramps were in considerable financial trouble. They had to pay several thousands of employees to carry on the company’s shipbuilding work and maintain their plant. Under all these circumstances the contractor was obliged to respond to the arbitrary demand of the Secretary according to the department formula in paying for ship construction or abandon its business. As these facts are neither disputed nor denied, and as the intermediate receipts were exacted under an erroneous construction of law, plaintiff insists that the department should not take advantage of its own wrong, not only because of the surrounding circumstances, but also because of the duress and coercion exercised in the matter of these receipts. When the vessel was completed a receipt or final release under the contract was exacted in the manner following the usual departmental form under the contract provision requiring a release. The claimant company insisted that neither the contract provision nor the final release demanded under it was intended by either of the parties thereto to cover damages accruing to the company by reason of the defaults of the Government. Thereupon the company invoked the equity powers of the court to reform both the contract provision and the receipt, should the language be capable of such con
The reform of the final receipt prayed for was denied May 16, 1910 (the writer not being present and taking no part in the decision), in an opinion filed by Peelle, C. J., for the following reasons, viz:
(1) That evidence was not admissible to vary the terms of the contract.
(2) Because the final release was not such a mistake, inadvertence, or accident as the court could relieve, though the claimant company might have mistaken its legal effect.
(3) Because, regardless of the intent of the parties, this court could not give a different construction or interpretation to the language used, as the same language had been considered and passed upon between the same parties in another case. -206 U. S., 118.
Subsequently the cause was remanded for argument upon the following propositions:
(1) Is the contract or the final release thereunder the subject of reformation when the plaintiff could by diligence have protected itself against the mistake which it complains of by securing a provision in the-release reserving for determination by the court the validity of the claims it now asserts, as was done in the case of the Alabama, 216 U. S., 494 ?
(2) If said contract or the final release be the subject of re-formation, is the evidence adduced competent and sufficient therefor ?
• Both parties had liberty to take further testimony, which seems to have been a concession by the court that' parol testimony was admissible.
I .am unable to see how a doubt could ever have existed as to the right to re-form upon proper evidence. Courts of equity would have but little to do in re-forming agreements except for the use of parol testimony outside of the written contract and unless mutual mistakes appear from extrinsic proof in reducing to writing the intention of the parties. Evidence of fraud or mistake is seldom found in the instrument itself.
The Supreme Court of the United States said in Walden v. Skinner, 101 U. S., 507, that “ Courts of equity afford relief in case of mistake of facts and allow parol evidence to vary and reform written contracts and instruments when the defect or error arises from accident or misconception, as properly forming an exception to the general rule which excludes parol testimony offered to vary or contradict written instruments. Where the mistake is admitted by the other party, relief, as all agree, will be granted if it be fully proved by other evidence.”
“The jurisdiction in equity to decree the correction of errors which have been caused by mutual mistake is firmly established and needs no citation of authority to sustain it.” Zartman v. First National Bank, 216 U. S., 134.
There is a class of written agreements where parol testimony is inadmissible to interpret them. These, for instance, are policies of insurance, which of themselves furnish the only way by which their terms can be waived or changed. The case now before the court is unlike the last class.
Although this court can not exercise some of the peculiar powers of a court of equity — as, for instance, to decree specific performance — it has the equitable power to determine the money relief to which claimants may be entitled, whether arising out of an equitable or legal demand. United States v. Jones, 131 U. S., 18. The jurisdiction to reform under the act of March 3, 1887, 24 Stat., 505, was so well defined in South Boston Iron Works v. United States, 34 C. Cls. R., 174, the Supreme Court in District of Columbia v. Barnes, 197 U. S., 152, approved the opinion of this court, stating this principle and giving the relief prayed for in the Barnes case. Mr. Justice Day in that case said that one having the right to money relief upon a contract mistakenly omitted to be reduced to writing in accordance with the true agreement of the parties has a claim for equitable cognizance, so that the contract should be reformed to meet the intention of the parties and, as corrected, to be adjudged a valid claim.
The Court of Claims is not bound by special rules of pleading, the main purpose being to arrive at and adjudicate the justice of claims against the United States. The forms of pleading are not of so strict a character as to require omissions to be held fatal to the rendition of such judgment as the facts demand. United States v. Burns, 12 Wall., 254; United States v. Behan, 110 ib., 339; Clark v. United States, 95 ib., 543; United States v. Carr, 132 ib., 650; Wisconsin Central v. United States, 164 ib., 190.
It has appeared that at the outset the majority excluded as incompetent and inadmissible all evidence tending to explain the intent of the parties and the true character of the instrument because the final receipt given could not be varied by parol testimony and because of the decision of the appellate court as to the effect of the naked release. The ground taken in refusing evidence for the purposes indicated and with respect to the matter of mutual mistake being no ground for reformation (practically brought forward in the present opinion of my brethren of this bench) seems so fundamentally erroneous, reasons are now presented from the highest authority to show' to the contrary. No court has gone further than the Supreme Court of the United States (except the highest court in Mississippi) .in overthrowing all three propositions of the majority of the court.
Chief Justice Chase, in an opinion (which alone will carry him into history as a just judge and as worthy of his great office), said for the court over which he presided that evidence could be received to prove that a promise expressed
Equity afforded relief where no mistake appeared as to the facts, but where there was a mistaken opinion on the part of ,a public officer, in Mullan v. United States, 118 U. S., 271. There the Secretary of the Interior had approved lists of public land under which selections were made and titles had passed. It was held that these selections could be vacated and titles under them annulled in a suit in equity brought directly for that purpose. The court found that the mistake, although one of law, could be corrected, and relief was accordingly given in a court of equity for the benefit of the United States.
In Patch v. White, 117 U. S., 210, an error in a will was rectified not alone by the context of the will but by parol evidence. There it appeared that a testator had devised certain lots to each of his near relations, and to his brother a lot described as No. 6 in square 403. He then devised to his infant son the balance of his real estate, to consist of certain lots, describing a number of them, but not describing lot No. 3 in square 406. It was held by the court that the testator intended to dispose of all his real estate, and thought he had done so, and that in the devise to his brother he believed he was giving him one of his own lots. On this state of affairs the court held that parol evidence might properly be received to show that the testator did not and never did own lot 6 in square 403, but he owned lot 3 in square 406. This raised a
In Hall v. Lafayette Co., 69 Miss., 539, it was held that an agreement- should not fail of execution by reason of ignorance, whether of fact or of law, in expressing intention in the instrument used. There it appeared to have been the intention of all concerned to make a bond covering all kinds of funds, but the parties made a bond covering only county funds. The law required a special bond for school funds, and the default was of school funds. It was held that while equity could not make contracts for parties and where parties, through erroneous views of law, reject one sort of contract and make another, led thereto by a mistaken opinion ,as to the law, as in Hunt v. Rousmanier, 1 Pet., 1, equity would not relieve. But where parties contract for a particular result and intend to effect it and fail to accomplish it, even through ignorance or mistake of law, equity will effectuate the intent. If in putting the agreement into form it fails to express and stipulate for that which the parties understood and intended, a case is made for a court of chancery.
In Hunt v. Rousmanier, supra, the early English principle was enunciated that equity had no power to make agreements for parties and then compel them to execute the same. Belief was denied because one party gave and another party received a power of attorney authorizing the creditor to sell certain property of the debtor and apply the proceeds of sale to the payment of the debt; but the power having become annulled by the death of the debtor, equity could not direct a new security to be given or a lien to be fixed on the property as security for the debt even though the parties acted in ignorance of the rule of law which made the death of the constituent a revocation of the jiower.
In Hall’s case, supra, the whole contract was for funds not taken. The court was asked to enlarge the terms of the bond, so as to include liability for something beyond its promise. The general bond of the defaulting officer was not security for school funds. Nevertheless, the instrument was reformed
In Gillespie v. Moon, 2 Johns, Ch., 585, Chancellor Kent said that he had looked into most if not all of the cases, and that it appeared to be established that relief could be had against any deed or contract in writing founded in mistake or fraud.
In Snell v. Insurance Co., 98 U. S., 89, the great commentator’s opinion was quoted as the settled law of the Supreme Court, and stated that the court was careful in Hunt v. Rousmanier to say that it was not its intention “ to lay it down that there may not be cases in which a court of equity will relieve against a plain mistake arising from ignorance of law.”
Rules which govern the exercise of the power to reform “ are founded in good sense.” Hearne v. Marine Ins. Co., 20 Wall., 490. This terse statement of the Supreme Court was supplemented by the statement that the mistake must be common to both parties to the instrument. The evidence is clear here that the contract when executed did not contemplate anything except the contract price agreed upon for the construction of the ship. The contract was not executed to be discharged by the arbitrary action of any officer of the Government for breaches of the contract causing losses to the contractor beyond the price agreed upon. Ex-Secretary Tracy declares in his testimony that when the contract was made he did not understand that the contractor was to be
Ex-Secretary Tracy’s understanding and intent is further corroborated by his incorporating into the third article of the Cramp contract a provision by which he put upon the United States the expense incident to the care and preservation of the Massachusetts arising out of any delays for defaults on the part of the Government: (1) By covenanting to deliver the armor “ within the time and within the order to carry on the work properly; ” and (2) that in the event of Government failure so to do to accept the vessel without armor. So there is no merit in the contention that Secretary Tracy intended by clause 6 of article 19 to demand a waiver of damages or to compel a release of claims for losses upon the penalty of compelling the contractor to forfeit its claims for nondelivery of the armor on time. Article 3 is explicit with respect to the commencement of the delivery of the
Admiral Hichborn was charged with the preparation of the specifications for building the vessel and with the details for its construction. He is positive that the proviso was inserted to protect the contractor against loss for any delay. At the time the Government had never before purchased armor. It had no experience, and the making of armor was in the experimental stage. The armor makers had so little experience and the naval architects and experts being without any experience at all, the time of delivery and the quality of the armor became subjects of consideration as to whether armor could be delivered on time or in the order required. The head of the shipbuilding company, according to Admiral Hichborn, expressed great doubt to that officer whether the Government would be able to get the armor, stating to the admiral his apprehensions of delay whilst the Government was holding him up to penalties and the contracting company was getting no corresponding security.
The proviso to the contract came about as the result of a discussion between the Judge Advocate, the Secretary of the Navy, the chief constructor, and the men who were to bid on the contract, and the object was to protect the shipbuilders against loss in case the Government failed to carry out its part of the contract.
Secretary Herbert knew this. As early as March, 1896, vigorous protests against relinquishment of claims for loss and damage inflicted upon the contractor were made to Secretary Herbert.
Negotiations for the armor way before the contract period had expired. The contractors objected because of the lateness of the change and because of the necessity arising to subject the armor to the new process. They said it would delay the completion of the work and entail loss and damage. Ex. Doc. 69; letter Aug. 22, 1893, p. 89. The Secretary of the Navy became possessed of exact knowledge that if the armor should be harveyized in the interest of the United States claims would arise for loss and damage.
The Secretary knew that by the application of the Harvey process “ it would delay completion of the vessel for a long-period of time.” He did not think that the delays would be as great as they subsequently proved to be. After the process was applied it was found difficult, “ almost impossible, if not quite,” to drill holes in the armor with the tools then in hand because of the hardness of the plate and its resistive power. A new process had to be invented annealing plates at points where they were to be perforated. Secretary Herbert says he recognized that the delays “ would increase the cost because of the care, docking, increased insurance,” and other expenditures resulting in claims against the Government for a breach of the contract. But the Secretary adds that he thought the contractor would be remitted either to a court or to Congress, and supports his statement from independent memory as well as by a reexamination of the correspondence. The Secretary is emphatic in the statement that it was not for him to determine the losses and damages of the Cramps after he had decided that the Navy Department had no jurisdiction. Hence the official action with reference to the settlements as the work progressed, and the delays were meantime prolonged. Concurrently with the damages imposed upon the contractor, Cramp & Co. presented claims for their losses. IT. R. Doc. 69, 2d sess. 54th Cong. This shows that both the Secretary and the Cramps
When the final receipt was taken Mr. Herbert states positively that he had no intention to include any part of the claim for losses and damage. He acted in accordance with the uniform precedent that his department had no jurisdiction to pass upon this class of claims. In his letter to Congress relating to all the claims of Cramp & Co. — which included the claim of the Massachusetts — the Secretary said that “ the interests of justice demand that they (the claims) should be referred to the Court of Claims, which can consider these matters with more deliberation and care than could be devoted by the committees of the two Houses of Congress.” At the very time this final release was signed under which the balance of the contract price, $51,536.60, was paid, November 23, 1896, there was pending before him under the act of June 10, 1896, the present claim, aggregating $483,757.49 as presented, and within 17 days thereafter he made the report to Congress, above referred to, never suggesting that he had taken 17 days before an absolute relinquishment of the entire claim, although he does specifically call attention to the two partial releases, coupling it with the statement that it was claimed that they were procured by coercion and duress.
After the release the Secretary proceeded to investigate and examine the claims submitted under the act of June 10, 1896.
The senior Cramp corroborates Secretary Herbert, and from the two statements it appears that the same intent was in the mind of Secretary Herbert in taking the receipt as controlled Secretary Tracy in making the contract.
According to Mr. Cramp, Secretary Herbert never intimated that under the contract the contractor was obliged to submit to the increased expense in the care and maintenance of the vessel (Rec., 67) arising out of the breach. There was no understanding, agreement, or suggestion either on the part of the Secretary of the Navy or the contracting company that the final receipt given in November covered in any manner claims for losses submitted September 30, 1896.
So that, whatever view may be taken of the effect of the intermediate receipts pending the construction of the ironclad, there is nothing left to doubt as to the matter of mutual mistake with reference to the meaning and effect of the final receipt in all good conscience and law, if human testimony be the subject of belief.
It seems that Secretary Herbert was considering reference’ for settlement of losses sustained by the Cramps for the Government’s breach of the contract to the Court of Claims when the final receipt was taken. That is the unmistakable evidence.
It must be understood that when final payment was due under the contract the Secretary of the Navy did not claim to have jurisdiction to settle the company’s demands for its losses growing out of the failure of the Government to deliver armor for the ironclad. The Secretary had refused to make advances because he did not feel that he had the right, as an executive officer, to modify the original agreement without a new consideration. Consequently the Secretary refused to make partial payments unless the contracting company would give him a bond'not only for the refunding, if necessary, of all advances then made, but would accompany this bond with a release of all claims for damages that might have accrued before that time on account of the company’s claim that the Government had delayed the builders in the completion of the work. Mr. Cramp insisted that the Secretary “ should not take advantage of his circumstances in that way.” That was in 1894. The company was financially embarrassed at that time. It appears that it was in need of .funds and a working capital to carry on its business. Its indebtedness was steadily increasing, and the stringency of the money market was most pronounced during the year that the payments on the contracts were due. The fact, even if it
Though defendants allege that dividends were paid on the capital stock outstanding from October, 1894, to February, 1896, these dividends had not been earned. If dividends had not been paid, the contractor’s credit would, perhaps, have been wholly impaired with banks. It is certain that the company was in distress and was experiencing much difficulty in extending its loans. Money to carry on the business was badly needed, and this fact was brought to the attention of the Secretary of the Navy at the time the payments were made to it and at a time when the Secretary was refusing to pay anything unless the company would release its claims for damages. The record is full of testimony that the Cramps were heavy borrowers of money. It is historical that there was a scarcity of money in the country at the time. The financial condition of the Cramps was such at the time that it was impossible for the company to raise money except on its contract for the building of this particular ship and two sister ships. The effort to show that the financial embarrassments of the Cramps were due to unprofitable contracts outside of the building by the company of ironclads for the Government does not change the well-established fact that at the time these intermediate receipts were given the company was on the verge of bankruptcy. In this state of affairs, and after much discussion
Secretary Herbert’s view that he must obtain a consideration for the change of contract stipulation as to partial payments is distinctly shown by the decision of the Supreme Court in the case of the Alabama to have been erroneous because the appellate court commended Secretary Long for the alteration of the terms of the contract and distinctly affirmed his right and power to change it.
Add to the foregoing conditions the fact that the Secretary of the Navy had the arbitrary power in case progress on the part of the contractor was unsatisfactory to him to declare the contract forfeited, it will be readily seen that the Cramps were in the power of the official acting so unjustly. The contractor was completely at the mercy of the official. The Secretary of the Navy and the president of the contracting company did not stand on equal terms against an ultimatum which required the company to subject itself to a forfeiture of its contract or to execute a receipt surrendering its rights.
The proof is clear and positive that the Secretary had knowledge of the fact that the Cramps could not carry on their business unless they could get money, and that the money had been earned, and at the time the intermediate receipts were given the Cramps could not obtain the cash anywhere else.
The acceptance of a less amount of money by reason of financial embarrassment was coercion where the party paying was apprised of the situation and had himself done something that caused the embarrassment. Wheeler v. Smith, 9 How., 55; United, States v. Huckabee, 16 Wall., 414; Swift v. United States, 111 U. S., 32 and cases cited; Robertson v. Frank, 132 ib., 23; R. R. Co. v. Oonn., 98 U. S., 543; United States v. Lee, 101 ib., 196.
Early decisions respecting duress required the employment of physical force or threats of violence that would frighten and intimidate the most courageous. The cases cited sub
The present case for damages relates to the Massachusetts. It is a wholly different case from that of the Indiana, 206 U. S., 126. The latter case was an action at law, and the appellate court was unaided by any extraneous evidence as to the technical meaning of the word “ construction ” as used in the contract, and assumed the intent of the parties in the matter of the releases from the erroneous belief that the claim had not been presented until about a year and a quarter after the execution of the final receipt. Said the Supreme Court: “As bearing upon this matter it may be noticed that while the release was signed and the contract between the building company and the Government closed on May 18, 1896, this action was not brought until August 10, 1897, nearly a year and a quarter thereafter.” It was not the appellate court’s fault that the matter of further claim was deemed an afterthought, because it was further said by the court — dealing with supposed claims of more than a half million of dollars — that by the execution of the receipt the parties “ surely never intended to leave such a bulk of unsettled matters.” The case of the Indiana turned “on the release.” If the court had been made aware that the claim was not an afterthought; that it was asserted at the very beginning; that it had been refused cognizance by the Secretary of the Navy for want of jurisdiction; that Congress had directed an examination of the claim, and that it was pending before the Secretary of the Navy at the very time the release was signed and favorably reported by the head of the Navy Department to Congress within a few days thereafter, it is reasonably certain the court could not have reached the conclusion it did. The inferences of the court clearly appear to have been based not only on the evidence not now presented, but on the erroneous assumption that the Cramp claims were without merit, gotten up for the special purpose of defrauding the Government.
In the case of the Alabama, 216 U. S., 494, the appellate court sustained the judgment of the Secretary of the Navy in refusing to settle claims for unliquidated damages on the ground that as an executive officer he was without authority to settle for them. Under a proviso to a release which did include claims arising under a contract under the terms of which the Secretary of the Navy did not have jurisdiction to entertain, the contractor was held not to be barred from prosecuting his demands for unliquidated damages before the Court of Claims. The case of the Alabama was reversed because this court did not follow two decisions of its own in order to give effect to the proviso. (This writer did not hear the case of the ATbama and took no part in its decision.)’
An examination of the case of the Alabama, likewise of the Indiana, discloses that there was no proof in this court or the higher court of what the parties intended except what the face of the written agreements disclosed. There was no effort to reform according to the intention. There was no attempt to explain the use and meaning in the receipt given for “ the construction ” of the ship. Both cases involved claims for unliquidated damages. Plaintiff by the language used and the failure to present extraneous proof had mistakenly restricted the court to the literal terms of the releases. The meaning of both decisions, in the last analysis, determines that although claims for unliquidated damages required for their settlement the application of the qualities of judgment and discretion, executive officers were without
There is no estoppel. When the intermediate receipts were exacted and taken upon conditions like those at bar, there can be no estoppel. The grounds of estoppel against plaintiff here are not nearly so strong as against defendants, and in this respect the case is not unlike that of Sturm v. Boker, 150 U. S., 337. A party is not estopped from asserting his claim unless his conduct has either damaged the Government or caused it to change its position by the acquiescence, silence, or other conduct of the claimant. Alforcl v. United States, 95 U. S., 356. Estoppel operates to prevent the truth from being heard where a claimant by his conduct has made it unconscionable for him to assert it. In this matter nothing was done to the detriment of the Government. Estoppels must always be reciprocal. Herman, sec. 328, 8 Wend., 480.
Nor is there any question of diligence or of laches. Where a party seeking relief has unreasonably delayed application for redress or where the circumstances raise the presumption that he acquiesces in the written agreement, equity may decline to grant relief. Graves v. Boston Marine Ins. Co., 2 Cranch, 419. With knowledge by the Government that a claim was pending for all the damages and losses when the final receipt was given, that it was a matter understood and acted upon by both parties to the final receipt at the time it was signed, and that the claims were under investigation as separate demands and were to remain open to settlement in the proper forum, there is eliminated any question of diligence.
There is nothing in any action heretofore taken on cases at law asking reimbursement for losses which prevents the court from reforming the contract and the receipts given thereunder. In a proceeding in equity to reform a general bond to include all kinds of funds a judgment at law can not be pleaded as res judicata. Hall v. Lafayette
But as this is an .equity case to reform written instruments this court can not prevent a review of all the facts by limiting its findings to matters within the discretion of the trial tribunal. The rules touching the effect of the findings do not apply from the adjudication of this court on a claim which requires it to exercise equity jurisdiction to do justice. Harvey v. United States, 105 U. S., 671; United States v. Old Settlers, 148 U. S., 464.
As there is some question as to the sufficiency and extent of the duress and coercion when the intermediate receipts were given I will not say that plaintiff company is entitled to have relief against the settlement covered by these intermediate receipts although the Cramps were put to the alternative of sustaining loss under their contract by the withholding on the part of the Secretary of the Navy of moneys partly due under the contract unless the Cramps would execute these intermediate receipts.
But as to the final receipt .and the amount then paid the right of the plaintiff company to relief seems to me to be entirely clear. On this last proposition I am willing to stand because the evidence fully justifies the conclusion. The appellate court can not be restricted by the findings here because the case now is one of equitable procedure.
While it is the duty of the courts to protect the Treasury against unjust demands, it is equally obligatory upon the judiciary when the truth is ascertained to give it effect to prevent wrong to individuals who deal with the United States. ;0ur Government should not build battleships and be permitted to escape the consequences of its delinquencies. While this observation might w^ell go. without saying, it is said, because this writer does not believe that anyone would more readily afford relief on the whole record as it is now presented than the late Mr. Justice Brewer, who wrote the opinions in the case growing out of the contract for the construction of the Indiana as well as for the construction of the Alabama.