139 F. 812 | E.D. Va. | 1905
This case is now before the court on the exceptions filed by the proctors for the libelants and respondent, the Sovereign of the Seas, to the report of Commissioner George E. Bowden, filed hérein on the 18th day of January, 1905, ascertaining the damages sustained by the libelants by reason of a collision between their barge the Juniata and the barge Sovereign of the Seas, the question of fault having heretofore been ascertained to be solely that of the Sovereign of the Seas. The commissioner reports the damages to be $3,236.06, and that interest should run from the 3d day of November, 1900. The items making up 'the total of
The collision occurred on the night of the 17th of February, 1900, at Newport News, Va., and, upon a survey being had, it was ■determined to make temporary repairs to the Juniata, and accordingly she was taken to the Newport News Shipyard at noon on the 20th of February, and remained there until 10:30 a. m. on the 24th •of February. After she commenced loading, on the 27th of February, she sprung a leak, and was returned to the shipyard at 8 o’clock •on the morning of the 28th, and the leak was on that day stopped. She was at the shipyard in all 5 days and 3J4 hours. It is claimed that by reason of the collision she originally lost her right to a berth for coal, and also lost time by having to leave after she was berthed, to return to the shipyard a second time. The Juniata arrived in port on the 17th of February, 1900, and her master claims that he could have loaded, but for this collision, by the 20th of February at the outside; and that as a matter of fact he did not ■finish until the 3d day of March, 1900. He was thus detained at Newport News from the 17th of February to the 3d of March, 14 •days in all; and the commissioner allowed on account of demur-rage 12 days; which is at least 2 days more than should be allowed on the Juniata’s master’s own showing. Nine days’ time would seem to be a full allowance for the demurrage caused by making the ■temporary repairs. After the completion of this temporary repair, ■the barge continued in her regular business in the coal trade, with•out interruption, until the fall of the year 1900, though she leaked some, when heavily laden, from time to time. On the 17th of September, at Philadelphia, it was determined to have permanent ^repairs made to the barge, and Rylatt & Barrett Dry Dock Company
“Q. What did those repairs consist of? A. Well, on her starboard quarter her sheathing was taken off, and the plates were repaired. Q. Do you know how many plates were repaired? A. There were three at least, and I think that there were four plates, but I am certain there were three. When these plates had been put on, the sheathing was put back again. Q. After this work was done, was there any trouble with the leaking? A. Well, when we first loaded, there was a little, but not much. Q. Did the work which was done upon the barge in the fall of the year practically stop her leaking? A. Yes, sir; after her first trip. Q. Captain, I wish you would state whether those repairs were necessary to restore the vessel to her former condition. A. Yes, sir; it was necessary. It was necessary they should be done, as the barge was leaking badly, and could not do her work properly until she was repaired.”
And David Matticks, the foreman of the Rylatt & Barrett Dry Dock Company, thus described the work that was done:
“Well, we took off the sheathing — the sheathing plank over the iron — so as to allow the repairs to be made to the ironwork which was made in our yard by a gang of men from Neafie & Levy’s shipyard here; and after they were through with the ironwork I went back with the gang and had the sheathing put back again.”
Just why it should have taken 33 days to do this work upon this barge, the total cost of which was only $888.92, is hard to conceive of. Certain it is no court would be warranted in allowing demur-rage for so long a time for doing the work. The barge was not sent to a shipyard that seems to have been equipped for fully doing the work in hand, or at least it did not so do this work, for the woodwork seems to have been done at the shipyard of the Rylatt & Barrett Dry Dock Company, whereas the ironwork was done by a gang of men from another yard, namely, that of Neafie & Levy; and the barge does not appear to have been put in the dry dock, or upon a marine railway, at all, but, on the contrary, as described by the Juniata’s master on page 47 of his evidence, as follows:
“Q. In making these repairs in the fall of 1900, was the barge put on a railway or in a dry dock, or, if not, how was the work done? A. No, sir; she was not put on a railway, but in the mud. She would ebb out at low water. She only just floated at high water. Q. Was that a cheap and economical way of repairing her or not? A. Yes, sir; it was. It was much less expensive than if she was hauled out on a railway.”
While it may be doubtless true that this method of doing the work was cheaper, it does not follow that it could not have been performed more expeditiously, and it is with the matter of the time it took to do the work that we are now dealing. The libelants reiterate the fact that they were economical in making the repairs, because they did not know at the time on whom the loss would fall, as the fault of the collision had not been settled; but it by no means appears that they were in a hurry in doing the work, as they might not at that time have been busy with their barge; and
After a careful review of the entire evidence in the case, the conclusion reached by the court is that an allowance of 10 days for the permanent repairs would be the utmost that ought to be given, making in all an allowance for demurrage for permanent and temporary repairs of 10 days, or $855, for doing $1,138.66 worth of work. The commissioner's allowance of $2,025 for demurrage will be disallowed, and in lieu thereof the sum of $855. To allow such an award as $2,025 on a barge of the size and value in question should not be considered seriously, unless under some extraordinary circumstances, which do not appear in this case.
Coming to the question of interest, the exception to the commissioner’s report should also be sustained, and interest on the demur-rage allowed only as of the date of the decree confirming the report. The allowance of interest upon demurrage is a matter within the discretion of the court, and in this case should only be allowed as of the entry of the decree, instead of the time the claim arose. The length of time which has occurred during the prosecution of this suit would of itself cause the court to hesitate to allow interest even upon the other items covered by the commissioner’s report, to the end that the practice of allowing admiralty causes to be prolonged as in this case should be discouraged; and certainly interest will not be given upon the allowance for demurrage.
Counsel for libelants insist that the commissioner’s award of $1,485 demurrage during the making of the permanent repairs in this case should be approved, and as a reason urge that 'the original claim as made was for $3,240, namely, for 45 days at $72 per day, instead of 33 days at $45 per day, as allowed by the commissioner; and, moreover, insist that the commissioner’s finding should not be disturbed unless plainly wrong. Suffice to say as to the latter proposition that in this case but little of the evidence of importance was taken by the commissioner, and he did not, therefore, have any better opportunity to judge of the weight of the evidence than the court; and hence the rule insisted upon as to the weight to be given to the findings of the commissioner has little application. So far as the size of the bill is concerned, the fact that the libelants asserted a plainly excessive and exorbitant demand does not com
It follows from what has been said that the exceptions of the Sovereign of the Seas should be sustained as above indicated, and that an award should be made in behalf of the Juniata for the amount of the four items above named, aggregating $72.40, and for the repair bill of $1,138.66, with interest from the 3d day of November, 1900, until paid, and for demurrage of $855, with interest thereon from the date of the entry of the decree carrying out this decision.