This appeal by the plaintiff from summary judgment for the defendants in a diversity case requires us to consider the meaning, under Wisconsin contract law, of “economic duress” as a defense to a settlement of a contract dispute.
On this appeal, we must take as true the following facts. The plaintiff, Selmer, agreed to act as a subcontractor on a construction project for which the defendant Blakeslee-Midwest Prestressed Concrete Company was the general contractor. Under the contract between Blakeslee-Midwest and Selmer, Selmer was to receive $210,000 for erecting prestressed concrete materials supplied to it by Blakeslee-Midwest. Blakeslee-Midwest failed to fulfill its contractual obligations; among other things, it was tardy in supplying Selmer with the prestressed concrete materials. Selmer could have terminated the contract without penalty but instead agreed orally with Blakeslee-Midwest to complete its work, provided Blakeslee-Midwest would pay Selmer for the extra costs of completion due to Blakeslee-Midwest’s defaults. When the job was completed, Selmer demanded payment of $120,000. BlakesleeMidwest offered $67,000 and refused to budge from this offer. Selmer, because it was in desperate financial straits, accepted the offer.
Two and a half years later Selmer brought this suit against Blakeslee-Midwest (the other defendants’ liability, being derivative from Blakeslee-Midwest’s, does not require separate consideration), claiming that its extra costs had amounted to $150,-000 ($120,000 being merely a settlement offer), and asking for that amount minus the $67,000 it had received, plus consequential and punitive damages. Although Selmer, presumably in order to be able to claim such damages, describes this as a tort rather than a contract action, it seems really to be a suit on Blakeslee-Midwest’s alleged oral promise to reimburse Selmer in full for the extra costs of completing the original contract after Blakeslee-Midwest defaulted. But the characterization is unimportant. Selmer concedes that, whatever its suit is, it is barred by the settlement agreement if, as the district court held, that agreement is valid. The only question is whether there is a triable issue as to whether the settlement agreement is invalid because procured by “economic duress.”
If you extract a promise by means of a threat, the promise is unenforceable. This is not, as so often stated, see, e.g.,
Totem Marine Tug & Barge, Inc. v. Alyeska Pipeline Serv. Co.,
Sensitive — maybe oversensitive — to this danger, the older cases held that a threat not to honor a contract could not be considered duress. See, e.g.,
Sistrom v. Anderson,
Alaska Packers’ Ass’n shows that because the legal remedies for breach of contract are not always adequate, a refusal to honor a contract may force the other party to the contract to surrender his rights — in Alaska Packers’ Ass’n, the appellant’s right to the libelants’ labor at the agreed wage. It undermines the institution of contract to allow a contract party to use the threat of breach to get the contract modified in his favor not because anything has happened to require modification in the mutual interest of the parties but simply because the other party, unless he knuckles under to the threat, will incur costs for which he will have no adequate legal remedy. If contractual protections are illusory, people will be reluctant to make contracts. Allowing contract modifications. to be voided in circumstances such as those in Alaska Packers’ Ass’n assures prospective contract parties that signing a contract is not stepping into a trap, and by thus encouraging people to make contracts promotes the efficient allocation of resources.
*928
Capps v. Georgia Pac. Corp.,
Although
Capps
is not a Wisconsin case, we have no reason to think that Wisconsin courts would reach a different result. Cf.
Mendelson
v.
Blatz Brewing Co.,
Matters stand differently when the complaining party’s financial distress is due to the other party’s conduct. Although Selmer claims that it was the extra expense caused by Blakeslee-Midwest’s breaches of the original contract that put it in a financial vise, it could have walked away from the contract without loss or penalty when Blakeslee-Midwest broke the contract. Selmer was not forced by its contract to remain on the job, and was not prevented by circumstances from walking away from the contract, as the appellant in Alaska Pack *929 ers' Ass’n had been; it stayed on the job for extra pay. We do not know why Selmer was unable to weather the crisis that arose when Blakeslee-Midwest refused to pay $120,000 for Selmer’s extra expenses— whether Selmer was undercapitalized or overborrowed or what — but Blakeslee-Midwest cannot be held responsible for whatever it was that made Selmer so necessitous, when, as we have said, Selmer need not have embarked on the extended contract.
To assimilate this case to one of the conventional categories of duress Selmer argues that Blakeslee-Midwest withheld $21,000 in “retainage” in order to force Selmer to settle the dispute over the extras, and in thus withholding Selmer’s property was guilty of “duress of goods,” see, e.g.,
Williams v. Phelps,
The precise allegation concerning retainage, however, is that Blakeslee-Midwest’s take-it-or-leave-it offer of $67,000 included the retainage of $21,000. Since the retainage was 10 percent of the contract price, Selmer must have received 90 percent of the price, or $189,000, and that plus $67,000 would equal $256,000. But Selmer in fact received a total of $280,000 from Blakeslee-Midwest. As this must have included the retainage, the retainage allegation was discredited and so did not create a triable issue. It might of course have been duress for Blakeslee-Midwest to say to Selmer, “we will give you your retainage of $21,000 plus $67,000 if and only if you abandon your claim for any additional extra payments,” but that is not Selmer’s contention. It says it was offered $67,000 including the retainage — not that it was offered $88,000 — and this is inconsistent with the uncontradicted evidence that the entire contract price of $210,000 was paid plus the $67,000 in extras. Moreover, Selmer waived its subcontractor’s lien, indicating it had been paid in full. This waiver, incidentally, was signed after Selmer received the $67,000 it claims to have accepted under duress. This is additional evidence that Selmer was not acting under duress when it made the settlement that years later it tried to repudiate.
Affirmed.
